TxDOT contract A00206691 bid tabulation
Hazard Elimination & Safety, FM 907 (0.1 Mi. N. of Owassa Rd. to 0.1 Mi. S. of Owassa Rd.). Let by Texas DOT on May 6, 2026, Hidalgo, Pharr District. 5 bids received; low bid $1,927,531 by Traf-Tex, Inc., -19% against the engineer's estimate of $2,365,384.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 97
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Traf-Tex, Inc. | $1,927,531 | Low | -19% |
| 2 | The Levy Company, Inc. | $2,008,578 | +4.0% | -15% |
| 3 | Austin Traffic Signal Construction Co., Inc. | $2,019,095 | +5.0% | -15% |
| 4 | Icos Management, LLC | $2,491,818 | +29% | +5.0% |
| 5 | Sice, Inc. | $2,812,548 | +46% | +19% |
Engineer's estimate: $2,365,384.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Traf-Tex, Inc. | 2. The Levy Company, Inc. | 3. Austin Traffic Signal Construction Co., Inc. | 4. Icos Management, LLC | 5. Sice, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 303.50 | $40.00 | $60.00 | $90.00 | $20.00 | $78.90 | |
| 2 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 160 | $427.50 | $339.44 | $290.00 | $305.00 | $471.30 | |
| 3 | Mobilization (500-7001) | LS | 1 | $400,000 | $82,958 | $200,858 | $105,000 | $427,000 | $268,358 |
| 4 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $6,000.00 | $1,649.00 | $5,145.25 | $4,500.00 | $10,000 | $7,605.74 |
| 5 | TMA (stationary) (505-7001) | DAY | 120 | $150.00 | $205.00 | $60.05 | $280.00 | $250.00 | $829.33 |
| 6 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,440 | $4.50 | $8.40 | $5.40 | $10.00 | $12.00 | $8.11 |
| 7 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,440 | $1.00 | $3.05 | $1.98 | $2.00 | $5.00 | $1.90 |
| 8 | Concrete sidewalks (4") (531-7001) | SY | 188.60 | $73.00 | $90.00 | $130.00 | $90.00 | $118.36 | |
| 9 | Curb ramps (type 1) (531-7005) | EACH | 35 | $3,116.00 | $2,650.00 | $3,550.00 | $3,200.00 | $3,484.91 | |
| 10 | Curb ramps (type 5) (531-7008) | EACH | 1 | $4,634.00 | $3,100.00 | $3,950.00 | $4,000.00 | $4,076.69 | |
| 11 | Curb ramps (type 7) (531-7010) | EACH | 5 | $3,704.00 | $2,650.00 | $3,420.00 | $3,800.00 | $3,484.91 | |
| 12 | Curb ramps (type 10) (531-7011) | EACH | 2 | $3,761.00 | $2,650.00 | $3,420.00 | $4,000.00 | $3,484.91 | |
| 13 | Conduit (PVC) (schedule 40) (1") (618-7021) | LF | 155 | $16.50 | $12.35 | $4.96 | $17.00 | $10.00 | $13.98 |
| 14 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,140 | $16.90 | $16.43 | $10.00 | $13.00 | $21.00 | |
| 15 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 785 | $22.10 | $26.35 | $26.00 | $25.00 | $39.45 | |
| 16 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 1,450 | $17.00 | $38.40 | $22.93 | $20.00 | $15.00 | $25.11 |
| 17 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 780 | $35.00 | $29.59 | $38.00 | $30.00 | $47.34 | |
| 18 | Electrical conductor (no.8) bare (620-7007) | LF | 700 | $1.60 | $2.03 | $1.50 | $1.75 | $1.50 | |
| 19 | Electrical conductor (no.8) insulated (620-7008) | LF | 40 | $1.70 | $2.05 | $3.00 | $1.85 | $1.76 | |
| 20 | Electrical conductor (no.6) bare (620-7009) | LF | 3,740 | $8.00 | $1.80 | $2.26 | $1.70 | $1.75 | $2.01 |
| 21 | Electrical conductor (no.6) insulated (620-7010) | LF | 990 | $4.50 | $2.20 | $2.53 | $1.80 | $1.95 | $2.38 |
| 22 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 6,250 | $4.50 | $2.90 | $3.01 | $2.25 | $3.70 | $3.30 |
| 23 | Ground box type A (122311)W/apron (624-7002) | EACH | 35 | $1,127.00 | $1,183.42 | $1,050.00 | $965.00 | $2,363.15 | |
| 24 | Ground box type D (162922)W/apron (624-7008) | EACH | 9 | $2,750.00 | $1,150.00 | $1,586.54 | $1,350.00 | $1,085.00 | $3,029.89 |
| 25 | Zinc-coat steel wire strand (3/16") (625-7001) | LF | 6,210 | $2.50 | $1.95 | $3.09 | $1.80 | $3.35 | $6.59 |
| 26 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 12,420 | $5.00 | $2.40 | $3.13 | $2.20 | $3.35 | $6.96 |
| 27 | Remove electrical services (628-7002) | EACH | 2 | $460.00 | $359.57 | $450.00 | $545.00 | $2,269.43 | |
| 28 | Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322) | EACH | 2 | $4,047.00 | $3,720.30 | $2,550.00 | $2,700.00 | $2,765.82 | |
| 29 | Elc SRV type T 120/240 000(NS)GS(N)TP(O) (628-7328) | EACH | 1 | $5,402.65 | $4,278.73 | $3,250.00 | $4,500.00 | $3,450.57 | |
| 30 | Aluminum signs (type A) (636-7001) | SF | 1,266.25 | $30.00 | $27.05 | $27.04 | $40.00 | $24.00 | $63.53 |
| 31 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 3 | $1,030.00 | $1,115.80 | $995.00 | $680.00 | $1,203.28 | |
| 32 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 36 | $950.00 | $1,123.00 | $1,267.96 | $1,305.00 | $925.00 | $1,328.21 |
| 33 | Remove SM RD SN sup&AM (644-7073) | EACH | 13 | $125.00 | $125.50 | $304.31 | $240.00 | $40.00 | $144.66 |
| 34 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 116 | $3.10 | $4.00 | $3.50 | $4.00 | $3.68 | |
| 35 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 4,440 | $1.10 | $2.45 | $0.88 | $2.00 | $0.88 | $2.89 |
| 36 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,384 | $6.50 | $9.80 | $7.00 | $12.00 | $7.00 | $11.57 |
| 37 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 2,800 | $1.80 | $2.50 | $2.00 | $2.50 | $2.11 | |
| 38 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 4,400 | $1.70 | $2.00 | $1.70 | $2.00 | $1.97 | |
| 39 | Pavement sler 6" (666-7347) | LF | 47,876 | $2.70 | $0.61 | $0.42 | $0.60 | $0.42 | $0.72 |
| 40 | Pavement sler 8" (666-7348) | LF | 4,556 | $2.80 | $0.90 | $0.48 | $0.70 | $0.48 | $1.05 |
| 41 | Pavement sler 12" (666-7350) | LF | 1,686 | $1.30 | $1.80 | $0.62 | $1.10 | $0.62 | $2.11 |
| 42 | Pavement sler 24" (666-7352) | LF | 2,395 | $3.80 | $3.11 | $1.50 | $2.10 | $1.50 | $3.68 |
| 43 | Pavement sler (arrow) (666-7353) | EACH | 35 | $30.00 | $22.22 | $25.00 | $20.00 | $25.00 | $26.30 |
| 44 | Pavement sler (word) (666-7354) | EACH | 34 | $32.00 | $22.22 | $35.00 | $20.00 | $35.00 | $26.30 |
| 45 | Pavement sler (bike arrow) (666-7368) | EACH | 3 | $22.22 | $25.00 | $14.00 | $25.00 | $26.30 | |
| 46 | Pavement sler (bike symbol) (666-7369) | EACH | 3 | $22.22 | $25.00 | $14.00 | $25.00 | $26.30 | |
| 47 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 1,140 | $0.90 | $2.00 | $1.00 | $2.00 | $1.05 | |
| 48 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 15,320 | $0.85 | $0.83 | $0.84 | $1.00 | $0.84 | $0.99 |
| 49 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 580 | $1.35 | $3.00 | $1.50 | $3.00 | $1.58 | |
| 50 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 23,636 | $0.65 | $0.90 | $0.84 | $1.00 | $0.84 | $1.05 |
| 51 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 771 | $16.00 | $16.00 | $15.00 | $16.00 | $18.94 | |
| 52 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 35 | $175.00 | $255.50 | $150.00 | $250.00 | $150.00 | $302.47 |
| 53 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 34 | $225.00 | $289.00 | $250.00 | $300.00 | $250.00 | $341.92 |
| 54 | Prefabricated PM type C (W)(bike arrow) (668-7113) | EACH | 3 | $200.00 | $100.00 | $200.00 | $100.00 | $236.71 | |
| 55 | Prefabricated PM type C (W)(bike symbol) (668-7115) | EACH | 3 | $200.00 | $250.00 | $200.00 | $250.00 | $236.71 | |
| 56 | Prefabricated PM type C (Y)(12")(solid) (668-7125) | LF | 1,801 | $6.00 | $7.55 | $5.50 | $8.00 | $5.50 | $8.94 |
| 57 | Reflectorized pavement marker type I-C (672-7002) | EACH | 329 | $6.00 | $5.35 | $7.50 | $6.00 | $7.50 | $6.31 |
| 58 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,275 | $4.30 | $4.90 | $5.00 | $6.00 | $5.00 | $5.79 |
| 59 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 5 | $8.70 | $7.50 | $20.00 | $15.00 | $10.26 | |
| 60 | Eliminating existing PM & markers (4") (677-7001) | LF | 40,076 | $0.30 | $0.70 | $0.55 | $0.70 | $0.55 | $0.79 |
| 61 | Eliminating existing PM & markers (8") (677-7004) | LF | 4,212 | $0.58 | $1.35 | $0.65 | $1.40 | $0.65 | $1.58 |
| 62 | Eliminating existing PM & markers (12") (677-7006) | LF | 2,221 | $2.20 | $0.75 | $1.80 | $0.75 | $2.63 | |
| 63 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,008 | $2.50 | $3.70 | $2.00 | $3.00 | $2.00 | $4.34 |
| 64 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 37 | $50.00 | $66.60 | $75.00 | $70.00 | $75.00 | $78.90 |
| 65 | Eliminating existing PM & markers (word) (677-7015) | EACH | 25 | $48.00 | $66.60 | $75.00 | $70.00 | $75.00 | $78.90 |
| 66 | Eliminating existing PM & marks (bike arrow) (677-7025) | EACH | 2 | $66.60 | $75.00 | $70.00 | $75.00 | $78.90 | |
| 67 | Eliminating existing PM & marks (bike symbol) (677-7027) | EACH | 2 | $66.60 | $75.00 | $70.00 | $75.00 | $78.90 | |
| 68 | Pavement surface preparation for marking (6") (678-7002) | LF | 47,876 | $0.35 | $0.20 | $0.01 | $0.03 | $0.01 | $0.03 |
| 69 | Pavement surface preparation for marking (8") (678-7004) | LF | 4,556 | $0.40 | $0.11 | $0.02 | $0.15 | $0.02 | $0.13 |
| 70 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,801 | $0.35 | $0.60 | $0.03 | $7.00 | $0.03 | $0.66 |
| 71 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,155 | $1.00 | $1.10 | $0.10 | $1.30 | $0.10 | $1.32 |
| 72 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 35 | $26.50 | $5.60 | $5.00 | $6.50 | $5.00 | $6.58 |
| 73 | Pavement surface preparation for marking (word) (678-7016) | EACH | 34 | $26.00 | $5.60 | $5.00 | $6.50 | $5.00 | $6.58 |
| 74 | Pavement surface preparation for marking (bike arrow) (678-7026) | EACH | 3 | $5.60 | $5.00 | $6.50 | $5.00 | $6.58 | |
| 75 | Pavement surface preparation for marking (bike symbol) (678-7028) | EACH | 3 | $5.60 | $5.00 | $6.50 | $5.00 | $6.58 | |
| 76 | Install highway traffic signal (isolated) (680-7002) | EACH | 3 | $38,538 | $31,032 | $31,500 | $33,900 | $30,592 | |
| 77 | Removing traffic signals (680-7004) | EACH | 2 | $5,170.00 | $2,587.67 | $2,500.00 | $5,700.00 | $35,591 | |
| 78 | Install highway traffic signal (upgrade) (680-7011) | EACH | 6 | $8,000.00 | $10,215 | $3,894.57 | $7,500.00 | $3,700.00 | $4,530.78 |
| 79 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 66 | $310.00 | $258.00 | $330.31 | $320.00 | $265.00 | $294.59 |
| 80 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 23 | $325.00 | $258.00 | $337.28 | $320.00 | $265.00 | $293.59 |
| 81 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 70 | $310.00 | $258.00 | $330.30 | $320.00 | $265.00 | $293.23 |
| 82 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 38 | $320.00 | $258.00 | $337.28 | $320.00 | $265.00 | $295.21 |
| 83 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 66 | $310.00 | $258.00 | $330.31 | $320.00 | $265.00 | $294.59 |
| 84 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 22 | $350.00 | $258.00 | $337.31 | $320.00 | $265.00 | $293.65 |
| 85 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 21 | $290.00 | $277.00 | $127.88 | $90.00 | $215.00 | $588.47 |
| 86 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 67 | $305.00 | $250.00 | $111.15 | $90.00 | $150.00 | $531.75 |
| 87 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 6,590 | $1.95 | $2.03 | $1.70 | $1.75 | $2.13 | |
| 88 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 13,605 | $2.85 | $3.20 | $3.35 | $2.50 | $2.85 | $2.91 |
| 89 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 4,155 | $3.75 | $4.20 | $4.42 | $3.00 | $3.50 | $3.45 |
| 90 | Ins traffic signal PL AM (S)STR(type B) (686-7007) | EACH | 1 | $6,337.00 | $7,596.30 | $7,500.00 | $7,400.00 | $14,132 | |
| 91 | Ins traffic signal PL AM (S)STR(type B)lum (686-7008) | EACH | 7 | $7,073.00 | $8,577.16 | $8,700.00 | $8,600.00 | $15,191 | |
| 92 | Ins traffic signal PL AM (S)STR(type D)lum (686-7020) | EACH | 2 | $8,234.00 | $9,995.10 | $10,250 | $9,800.00 | $18,339 | |
| 93 | Pedestrian pole assembly (687-7001) | EACH | 42 | $3,540.00 | $2,538.71 | $2,250.00 | $2,300.00 | $3,573.48 | |
| 94 | Pedestrian detect push button (APS) (688-7001) | EACH | 44 | $814.00 | $932.10 | $860.00 | $1,000.00 | $1,120.13 | |
| 95 | Pedestrian detector controller unit (688-7003) | EACH | 7 | $3,807.00 | $3,683.49 | $3,200.00 | $4,500.00 | $5,309.78 | |
| 96 | RVDS (presence detection only) (6008-7001) | EACH | 33 | $5,600.00 | $5,150.00 | $6,722.09 | $6,500.00 | $11,345 | $7,129.66 |
| 97 | RVDS (advance detection only) (6008-7002) | EACH | 32 | $5,800.00 | $5,279.00 | $6,717.11 | $7,450.00 | $8,375.00 | $7,185.27 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.