TxDOT contract A00207336 bid tabulation
Intersection Improvement, FM 518 (At FM 528 to .). Let by Texas DOT on September 2, 2026, Galveston, Houston District. 4 bids received; low bid $373,983 by Vaca Underground Utilities Inc, -21% against the engineer's estimate of $474,315.
- Owner
- Texas DOT
- Letting
- 02 SEP 2026
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Vaca Underground Utilities Inc | $373,983 | Low | -21% |
| 2 | Castillo Aranda LLC | $400,185 | +7.0% | -16% |
| 3 | Third Coast Services LLC | $719,975 | +93% | +52% |
| 4 | Ragle Construction, Inc. | $789,523 | +111% | +66% |
Engineer's estimate: $474,315.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Vaca Underground Utilities Inc | 2. Castillo Aranda LLC | 3. Third Coast Services LLC | 4. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavement) (104-7001) | SY | 46 | $30.00 | $12.00 | $20.00 | $101.17 | $100.00 |
| 2 | Removing concrete (medians) (104-7008) | SY | 180 | $8.00 | $25.00 | $20.00 | $59.51 | $50.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 195 | $16.00 | $20.00 | $20.00 | $59.51 | $30.00 |
| 4 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 114 | $5.00 | $10.00 | $10.00 | $23.80 | $50.00 |
| 5 | Backfill (type B)(vehicle) (134-7007) | CY | 10 | $100.00 | $100.00 | $50.00 | $136.21 | $600.00 |
| 6 | Spec excavation work (vehicle) (158-7005) | CY | 40 | $60.00 | $275.00 | $100.00 | $162.98 | $300.00 |
| 7 | Block sodding (162-7002) | SY | 1,740 | $8.00 | $10.00 | $7.00 | $4.11 | $14.00 |
| 8 | Vegetative watering (168-7001) | TGL | 44 | $30.00 | $20.00 | $95.00 | $49.59 | $65.00 |
| 9 | Concrete pavement (CRCP)(fast TRK) (13") (360-7077) | SY | 143 | $250.00 | $175.00 | $150.00 | $624.86 | $300.00 |
| 10 | Mobilization (500-7001) | LS | 1 | $44,589 | $35,000 | $40,500 | $71,997 | $78,000 |
| 11 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $16,000 | $2,500.00 | $15,500 | $14,507 | $68,500 |
| 12 | TMA (stationary) (505-7001) | DAY | 84 | $300.00 | $175.00 | $300.00 | $0.05 | $300.00 |
| 13 | TMA (mobile operation) (505-7003) | DAY | 14 | $370.00 | $175.00 | $800.00 | $550.51 | $620.00 |
| 14 | Temporary sediment control fence (install) (506-7039) | LF | 185 | $4.00 | $1.00 | $6.00 | $4.46 | $3.75 |
| 15 | Temporary sediment control fence (remove) (506-7041) | LF | 185 | $1.00 | $1.00 | $2.00 | $1.19 | $1.00 |
| 16 | Concrete curb (slotted) (529-7013) | LF | 1,090 | $16.00 | $16.50 | $11.00 | $101.17 | $80.00 |
| 17 | Concrete curb (dowel) (529-7014) | LF | 276 | $40.00 | $30.00 | $9.00 | $119.02 | $100.00 |
| 18 | Concrete sidewalks (4") (531-7001) | SY | 162 | $100.00 | $65.00 | $85.00 | $267.80 | $100.00 |
| 19 | Curb ramps (type 1) (531-7005) | EACH | 1 | $2,500.00 | $3,200.00 | $1,600.00 | $6,546.16 | $1,550.00 |
| 20 | Curb ramps (type 22) (531-7014) | EACH | 1 | $6,000.00 | $3,500.00 | $1,650.00 | $6,546.16 | $2,900.00 |
| 21 | Curb ramps (type 5) (mod) (531-7031) | EACH | 3 | $8,000.00 | $5,800.00 | $1,700.00 | $6,546.16 | $4,100.00 |
| 22 | Concrete median (536-7002) | SY | 234 | $150.00 | $102.00 | $85.00 | $278.51 | $85.00 |
| 23 | Concrete directional island (536-7004) | SY | 30 | $250.00 | $102.00 | $90.00 | $297.55 | $170.00 |
| 24 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 620 | $15.00 | $14.00 | $12.00 | $13.24 | $9.00 |
| 25 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 450 | $33.00 | $15.00 | $20.00 | $20.04 | $12.00 |
| 26 | Conduit (RM) (2") (618-7078) | LF | 5 | $32.00 | $50.00 | $150.00 | $29.70 | $100.00 |
| 27 | Electrical conductor (no.8) bare (620-7007) | LF | 620 | $2.50 | $2.25 | $3.50 | $2.22 | $2.80 |
| 28 | Ground box type D (162922)W/apron (624-7008) | EACH | 5 | $1,800.00 | $1,500.00 | $1,150.00 | $1,368.14 | $950.00 |
| 29 | Remove ground box (624-7013) | EACH | 4 | $150.00 | $450.00 | $200.00 | $113.51 | $150.00 |
| 30 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 330 | $3.00 | $8.00 | $8.00 | $2.22 | $6.00 |
| 31 | Aluminum signs (type A) (636-7001) | SF | 52.50 | $55.00 | $40.00 | $30.00 | $34.83 | $18.00 |
| 32 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 7 | $1,000.00 | $1,100.00 | $1,000.00 | $951.99 | $895.00 |
| 33 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 3 | $800.00 | $2,100.00 | $2,000.00 | $907.73 | $1,774.00 |
| 34 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 1 | $800.00 | $2,400.00 | $2,500.00 | $1,412.15 | $2,060.00 |
| 35 | Remove SM RD SN sup&AM (644-7073) | EACH | 7 | $150.00 | $150.00 | $150.00 | $239.87 | $125.00 |
| 36 | Reflectorized pavement marking type II (W) 36" (yld tri) (666-7201) | EACH | 4 | $80.00 | $5.50 | $80.00 | $89.26 | $65.00 |
| 37 | Reflectorized pavement marking type II (Y)(curb) (666-7221) | LF | 1,855 | $1.50 | $1.35 | $2.00 | $4.23 | $1.15 |
| 38 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 1,190 | $1.50 | $1.75 | $2.00 | $1.31 | $1.50 |
| 39 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 560 | $3.00 | $2.30 | $2.50 | $1.79 | $2.00 |
| 40 | Reflectorized pavement marking type III (W)(6")(DOT) (666-7238) | LF | 201 | $2.00 | $2.30 | $2.50 | $1.79 | $2.00 |
| 41 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 2,170 | $2.00 | $2.30 | $2.50 | $2.38 | $2.00 |
| 42 | Reflectorized pavement marking type III (W)(8")(DOT) (666-7241) | LF | 450 | $1.50 | $2.30 | $2.50 | $2.38 | $2.00 |
| 43 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 799 | $10.00 | $12.50 | $13.00 | $13.09 | $11.00 |
| 44 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 686 | $2.00 | $1.75 | $2.00 | $1.79 | $1.50 |
| 45 | Reflectorized pavement marking type III (Y)(8")(solid) (666-7251) | LF | 230 | $3.00 | $2.30 | $3.00 | $2.38 | $2.00 |
| 46 | Reflectorized pavement marking type III (Y)(12")(solid) (666-7252) | LF | 100 | $7.00 | $3.50 | $4.00 | $5.95 | $3.00 |
| 47 | Reflectorized pavement marking type III (W)(arrow) (666-7254) | EACH | 16 | $250.00 | $230.00 | $250.00 | $297.55 | $200.00 |
| 48 | Reflectorized pavement marking type III (W)(double arrow) (666-7255) | EACH | 2 | $400.00 | $455.00 | $450.00 | $357.06 | $400.00 |
| 49 | Reflectorized pavement marking type III (W)(word) (666-7257) | EACH | 15 | $350.00 | $230.00 | $250.00 | $297.55 | $200.00 |
| 50 | Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262) | LF | 560 | $3.00 | $2.85 | $3.00 | $1.79 | $2.50 |
| 51 | Reflectorized pavement marker type I-C (672-7002) | EACH | 8 | $8.00 | $8.00 | $11.90 | $7.00 | |
| 52 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 36 | $6.00 | $8.00 | $8.00 | $11.90 | $7.00 |
| 53 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 176 | $6.00 | $8.00 | $8.00 | $11.90 | $7.00 |
| 54 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,864 | $1.00 | $0.50 | $1.00 | $1.19 | $0.40 |
| 55 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,151 | $1.00 | $0.95 | $1.00 | $1.19 | $0.80 |
| 56 | Eliminating existing PM & markers (12") (677-7006) | LF | 1,188 | $2.00 | $1.75 | $2.00 | $2.38 | $1.50 |
| 57 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,028 | $3.00 | $3.50 | $3.50 | $3.57 | $3.00 |
| 58 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 11 | $75.00 | $60.00 | $55.00 | $29.76 | $50.00 |
| 59 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 2 | $100.00 | $120.00 | $125.00 | $29.75 | $100.00 |
| 60 | Eliminating existing PM & markers (word) (677-7015) | EACH | 10 | $100.00 | $60.00 | $60.00 | $29.75 | $50.00 |
| 61 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,951 | $1.00 | $0.12 | $0.50 | $1.19 | $0.10 |
| 62 | Pavement surface preparation for marking (8") (678-7004) | LF | 2,850 | $1.00 | $0.25 | $0.50 | $1.19 | $0.20 |
| 63 | Pavement surface preparation for marking (12") (678-7006) | LF | 100 | $1.00 | $0.35 | $0.50 | $1.19 | $0.30 |
| 64 | Pavement surface preparation for marking (24") (678-7008) | LF | 799 | $2.00 | $0.45 | $0.50 | $1.19 | $0.40 |
| 65 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 16 | $12.00 | $10.25 | $10.00 | $17.85 | $9.00 |
| 66 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 2 | $40.00 | $17.00 | $20.00 | $17.85 | $15.00 |
| 67 | Pavement surface preparation for marking (word) (678-7016) | EACH | 15 | $15.00 | $10.20 | $10.00 | $17.85 | $9.00 |
| 68 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $12,000 | $15,000 | $4,000.00 | $5,025.62 | $3,600.00 |
| 69 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 2 | $350.00 | $400.00 | $320.00 | $279.45 | $280.00 |
| 70 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 2 | $350.00 | $400.00 | $320.00 | $279.45 | $280.00 |
| 71 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $350.00 | $400.00 | $320.00 | $279.45 | $280.00 |
| 72 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 2 | $240.00 | $250.00 | $250.00 | $274.69 | $200.00 |
| 73 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 1,555 | $2.50 | $3.00 | $3.00 | $1.89 | $2.20 |
| 74 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 1,555 | $4.00 | $4.00 | $3.00 | $3.32 | $2.40 |
| 75 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 30 | $4.65 | $5.00 | $8.00 | $4.25 | $6.00 |
| 76 | Pedestrian pole assembly (687-7001) | EACH | 7 | $2,000.00 | $3,500.00 | $3,000.00 | $2,864.92 | $2,600.00 |
| 77 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $918.00 | $900.00 | $1,000.00 | $1,120.23 | $888.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 2, 2026. Compiled by Mirage Metrics.