TxDOT contract A00208947 bid tabulation

Resurface Roadway, FM 1694 (SH 44 to FM 665). Let by Texas DOT on March 4, 2025, Nueces, Corpus Christi District. 4 bids received; low bid $4,423,799 by CK Newberry, LLC, -14% against the engineer's estimate of $5,114,930.

Owner
Texas DOT
Letting
04 MAR 2025
Pay items
44
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1CK Newberry, LLC$4,423,799Low-14%
2Hunter Industries, LTD.$4,582,870+4.0%-10%
3J E Construction Services, LLC$4,593,352+4.0%-10%
4Anderson Columbia Co., Inc.$4,672,531+6.0%-9.0%
TxDOT contract A00208947: bids by rank

Engineer's estimate: $5,114,930.

Bid tabulation

LinePay itemUnitQuantityEstimate1. CK Newberry, LLC2. Hunter Industries, LTD.3. J E Construction Services, LLC4. Anderson Columbia Co., Inc.
1Removing concrete (mowstrip) (104-7004)CY108$20.00$70.00$13.20$19.00$151.00
2Removing concrete (driveways) (104-7011)SY80$40.00$45.00$19.80$14.00$44.00
3Backfill (type A or B) (134-7004)STA350$175.00$170.00$176.00$142.00$216.00
4Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070)GAL40,226$3.75$3.25$3.96$4.00$3.10
5Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212)CY1,064$100.00$130.00$142.92$162.00$170.00
6D-GR HMA type D sac-B PG70-22 (341-7050)TON25,256$120.00$125.00$118.80$119.00$126.50
7Tack coat (341-7082)GAL9,187$2.75$4.00$3.19$4.00$4.25
8Planing asphalt concrete pavement(0" to 2.25") (354-7075)SY114,923$3.50$1.00$2.09$2.00$2.00
9Riprap (mow strip)(4 in) (432-7013)CY100$700.00$500.00$583.98$435.00$705.00
10Cleaning and sealing existing joints (438-7001)LF90$50.00$60.00$81.00$61.00$106.00
11Clean existing culverts (480-7001)EACH12$1,750.00$1,500.00$1,200.11$2,923.00$1,430.00
12Mobilization (500-7001)LS1$459,266$260,000$329,201$312,914$96,250
13Barricades, signs and traffic handling (502-7001)MO7$9,000.00$5,000.00$9,209.77$6,100.00$13,200
14Portable changeable message sign (503-7001)DAY226$20.00$25.00$40.63$81.00$65.00
15TMA (stationary) (505-7001)DAY98$300.00$100.00$152.37$201.00$342.00
16TMA (mobile operation) (505-7003)DAY15$350.00$100.00$812.65$364.00$549.00
17Temporary sediment control fence (install) (506-7039)LF1,280$5.00$7.50$4.46$3.00$9.40
18Temporary sediment control fence (remove) (506-7041)LF1,280$1.50$2.00$2.68$2.00$1.30
19Intersections (ACP) (type 1) (530-7003)SY958$130.00$50.00$39.60$39.00$39.00
20Driveways (concrete) (530-7006)SY80$130.00$150.00$232.46$62.00$132.00
21Driveways (ACP) (type 1) (530-7011)SY2,499$75.00$35.00$31.90$29.00$38.00
22Driveways (ACP) (type 2) (530-7012)SY667$150.00$65.00$44.00$68.00$91.00
23Mill rumble strips (asphalt) (shoulder) (533-7001)LF59,054$0.75$0.10$0.16$0.50$0.25
24Mill rumble strips (asphalt) (centerline) (533-7002)LF29,527$1.00$0.15$0.22$0.50$0.25
25Metal W-beam guard fence (timber post) (540-7001)LF1,000$28.00$28.00$50.40$28.00$36.00
26Metal beam guard fence trans (T101) (540-7007)EACH8$1,000.00$1,800.00$2,105.25$1,123.00$2,290.00
27Remove metal beam guard fence (542-7001)LF1,000$2.00$2.00$10.50$3.00$2.60
28RM metal beam guard fence trans (T101) (542-7005)EACH8$300.00$250.00$845.25$246.00$305.00
29Guardrail end treatment (install) (544-7001)EACH8$3,000.00$3,100.00$5,040.00$2,236.00$4,010.00
30Guardrail end treatment (remove) (544-7003)EACH8$200.00$450.00$945.00$436.00$564.00
31Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016)EACH24$4.50$22.00$25.00$23.00$27.00
32Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH24$30.00$45.00$45.00$32.00$52.00
33Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH21$150.00$95.00$95.00$68.00$113.00
34Remove delin & object marker assms (658-7078)EACH21$22.00$18.00$20.00$18.00$21.00
35Work zone pavement marking removing (W)6"(solid) (662-7068)LF69,174$0.50$0.32$0.32$1.00$0.40
36Work zone pavement marking removing (Y)6"(broken) (662-7098)LF8,308$0.55$0.72$0.72$1.00$0.85
37Work zone pavement marking removing (Y)6"(solid) (662-7100)LF3,540$0.50$0.72$0.72$1.00$0.85
38Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,729$3.00$0.50$1.63$3.00$3.65
39Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH697$3.50$2.00$1.63$3.00$3.10
40Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF40$20.00$20.00$20.00$18.00$24.00
41Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF69,174$0.55$0.66$0.66$1.00$0.80
42Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419)LF8,328$0.50$1.10$1.10$1.00$1.35
43Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF4,730$0.70$1.10$1.10$1.00$1.35
44Reflectorized pavement marker type II-A-A (672-7004)EACH865$7.00$5.00$5.00$4.00$6.05
TxDOT contract A00208947: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy