TxDOT contract A00212479 bid tabulation

ILLUMINATION MAINTENANCE, IH0020 (VARIOUS LOCATIONS IN to Tarrant County). Let by Texas DOT on August 7, 2025, Tarrant, Fort Worth District. 1 bid received; low bid $1,229,020 by Vaca Underground Utilities Inc, +12% against the engineer's estimate of $1,101,800.

Owner
Texas DOT
Letting
07 AUG 2025
Pay items
76
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Vaca Underground Utilities Inc$1,229,020Low+12%
TxDOT contract A00212479: bids by rank

Engineer's estimate: $1,101,800.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Vaca Underground Utilities Inc
1Removing concrete (foundations) (104-7024)CY40$250.00$1,000.00
2Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF20$400.00$250.00
3Mobilization (callout) (500-7002)EACH20$2,500.00$5,000.00
4Mobilization (emergency) (500-7033)EACH20$2,500.00$1,500.00
5Portable changeable message sign (503-7001)DAY120$150.00$75.00
6TMA (stationary) (505-7001)DAY40$250.00$2,000.00
7Biodegradable erosion control logs (install) (18") (506-7045)LF200$10.00$0.25
8Biodegradable erosion control logs (remove) (506-7046)LF200$3.00$0.25
9Conduit (PVC) (schedule 40) (2") (618-7030)LF400$20.00$15.00
10Conduit (PVC) (schedule 40) (2") (bore) (618-7031)LF1,000$36.00$20.00
11Conduit (PVC) (schedule 80) (1 1/2") (618-7052)LF800$12.00$10.00
12Conduit (prepare) (618-7090)LF3,600$5.00$3.00
13Electrical conductor (no.10) insulated (620-7006)LF6,000$3.00$2.00
14Electrical conductor (no.8) bare (620-7007)LF1,000$2.50$2.10
15Electrical conductor (no.8) insulated (620-7008)LF1,000$2.50$2.25
16Electrical conductor (no.6) bare (620-7009)LF6,000$2.50$2.55
17Electrical conductor (no.6) insulated (620-7010)LF6,000$2.75$2.80
18Electrical conductor (no.4) bare (620-7011)LF1,000$3.50$3.00
19Electrical conductor (no.4) insulated (620-7012)LF1,000$3.50$3.25
20Remove ground box (624-7013)EACH16$450.00$800.00
21Remove electrical services (628-7002)EACH10$1,200.00$1,000.00
22Elc SRV type A 240/480 100(NS)AL(T)EX(O) (628-7073)EACH20$5,000.00$5,500.00
23Removal of cables (690-7009)LF2,000$3.00$2.00
24Install of cables (690-7011)LF20,000$4.00$2.75
25Replace of electrical service (690-7019)EACH20$8,800.00$3,800.00
26Replace luminaire pole (690-7126)EACH24$700.00$6,000.00
27Install above-ground conduit (690-7143)LF100$2.60$30.00
28Remove above-ground conduit (690-7144)LF100$2.75$5.00
29Replace above-ground conduit (690-7145)LF100$2.90$30.00
30Install underground conduit (690-7146)LF200$3.25$15.00
31Remove underground conduit (690-7147)LF100$2.25$8.00
32Replace underground conduit (690-7148)LF200$6.00$15.00
33Install electrical splice (690-7157)EACH100$65.00$150.00
34Road bore (690-7161)LF500$12.00$30.00
35Remove roadway illum assembly (HPS) (690-7163)EACH30$1,200.00$500.00
36Remove roadway illum assembly (LED) (690-7166)EACH20$1,200.00$1,200.00
37Replace roadway illum assembly (LED) (690-7167)EACH10$2,400.00$6,500.00
38Remove underpass luminaire (HPS) (690-7168)EACH10$100.00$150.00
39Remove underpass luminaire (LED) (690-7171)EACH10$300.00$150.00
40Replace underpass luminaire (LED) (690-7172)EACH10$330.00$600.00
41Replace luminaire fixture (HPS) (690-7178)EACH10$175.00$300.00
42Replace high mast luminaires (690-7182)EACH4$1,500.00$1,500.00
43Replace luminaire arms (690-7183)EACH20$500.00$1,200.00
44Maintain roadway illumination (690-7184)EACH20$155.00$600.00
45Maintain high mast illumination (690-7185)EACH10$500.00$1,900.00
46Maintain underpass fixture (690-7187)EACH20$500.00$150.00
47Schedule prev maintenance (roadway illum assembly) (690-7189)EACH10$750.00$150.00
48Schedule prev maintenance (high mast assembly) (690-7190)EACH10$750.00$1,300.00
49Replace timber service pole (690-7191)EACH10$200.00$500.00
50Replace steel service pole (690-7192)EACH10$2,750.00$500.00
51Install ground box W/apron (690-7194)EACH8$575.00$1,800.00
52Replace transformer base (690-7197)EACH6$350.00$1,500.00
53Replace transformer base cover (690-7198)EACH60$5.00$150.00
54Replace hand hole cover (690-7199)EACH60$55.00$150.00
55Replace ballast (690-7201)EACH30$100.00$60.00
56Replace ballast (high mast lighting) (690-7202)EACH30$250.00$100.00
57Replace fuse (690-7218)EACH100$30.00$100.00
58Replace fuse holder (690-7219)EACH100$30.00$50.00
59Replace breakaway fuse holder (690-7220)EACH60$30.00$250.00
60Replace photocell and bracket (690-7222)EACH80$30.00$79.00
61Replace control trans (high mast) (690-7223)EACH20$250.00$1,000.00
62Replace control trans (elect service) (690-7224)EACH10$70.00$400.00
63Replace control circuit (high mast) (690-7225)EACH10$125.00$350.00
64Replace aviation warning fixture (690-7227)EACH18$1,200.00$750.00
65Replace aviation warning lamp (690-7228)EACH40$1,300.00$100.00
66Replace hand-off-auto switch (690-7229)EACH20$60.00$100.00
67Replace contactor (690-7230)EACH16$150.00$500.00
68Replace meter base (690-7231)EACH20$75.00$500.00
69Replace circuit breaker (690-7235)EACH20$200.00$150.00
70Replace flex power cable or cord (690-7236)LF400$6.00$40.00
71RE-strap existing conduit (690-7240)EACH40$1,250.00$25.00
72Replace nuts, washers & other hardware (690-7241)EACH100$275.00$30.00
73Troubleshoot for repairs (690-7242)HR200$100.00$175.00
74Replace lamp for pole MNT fixture 150W (690-7271)EACH20$375.00$5.00
75Replace lamp for pole MNT fixture 250W (690-7272)EACH20$250.00$5.00
76Replace lamp for pole MNT fixture 400W (690-7273)EACH20$100.00$5.00
TxDOT contract A00212479: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy