TxDOT contract A00213305 bid tabulation
TRAFFIC SIGNAL MAINTENANCE, US0377 (DISTRICT-WIDE to DISTRICT-WIDE). Let by Texas DOT on March 20, 2025, Brown, Brownwood District. 1 bid received; low bid $653,617 by WG Engineering & Construction, LLC, +24% against the engineer's estimate of $525,106.
- Owner
- Texas DOT
- Letting
- 20 MAR 2025
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | WG Engineering & Construction, LLC | $653,617 | Low | +24% |
Engineer's estimate: $525,106.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. WG Engineering & Construction, LLC |
|---|---|---|---|---|---|
| 1 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 30 | $234.51 | $507.50 |
| 2 | Class C concrete (miscellaneous) (420-7067) | CY | 5 | $2,056.41 | $1,204.50 |
| 3 | Mobilization (callout) (500-7002) | EACH | 8 | $2,914.04 | $21,299 |
| 4 | TMA (stationary) (505-7001) | DAY | 30 | $254.25 | $506.60 |
| 5 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 250 | $30.65 | $25.40 |
| 6 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 250 | $20.00 | $48.20 |
| 7 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 250 | $34.30 | $55.80 |
| 8 | Electrical conductor (no.10) insulated (620-7006) | LF | 250 | $2.17 | $4.20 |
| 9 | Electrical conductor (no.6) bare (620-7009) | LF | 250 | $6.47 | $4.50 |
| 10 | Electrical conductor (no.6) insulated (620-7010) | LF | 500 | $6.50 | $4.80 |
| 11 | Relocate lrsa (647-7002) | EACH | 5 | $3,590.57 | $5,554.30 |
| 12 | Vehicle signal section (12")LED(housing only) (682-7016) | EACH | 2 | $318.00 | $190.50 |
| 13 | Install RDSD flash beacon assembly (685-7001) | EACH | 10 | $10,000 | $3,265.90 |
| 14 | Remove RDSD flash beacon assembly (685-7003) | EACH | 2 | $1,000.00 | $1,523.40 |
| 15 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 10 | $12,428 | $4,122.80 |
| 16 | Ins traffic signal PL AM (stran)(install only) (686-7293) | EACH | 2 | $1,636.20 | $4,060.80 |
| 17 | Removal of ground boxes (690-7006) | EACH | 2 | $261.72 | $571.30 |
| 18 | Replace of ground boxes (690-7007) | EACH | 2 | $1,699.16 | $2,189.00 |
| 19 | Install of ground boxes (690-7008) | EACH | 5 | $2,570.00 | $2,189.00 |
| 20 | Replace of cables (690-7010) | LF | 300 | $12.41 | $17.20 |
| 21 | Removal of span cable assembly (690-7016) | LF | 300 | $4.61 | $5.10 |
| 22 | Replace of electrical service (690-7019) | EACH | 2 | $8,519.03 | $10,902 |
| 23 | Install of electrical service (690-7020) | EACH | 2 | $5,814.90 | $10,902 |
| 24 | Replace of signal head assembly (690-7025) | EACH | 10 | $504.54 | $586.80 |
| 25 | Install of signal head assembly (690-7026) | EACH | 2 | $814.38 | $586.80 |
| 26 | Replace of signal related signs (690-7028) | EACH | 15 | $383.62 | $665.60 |
| 27 | Install of FND for ground MNT cabinets (690-7036) | EACH | 2 | $4,329.02 | $4,817.90 |
| 28 | Replace of control cabinet(GRND MNT) (690-7039) | EACH | 2 | $5,867.53 | $9,835.40 |
| 29 | Replace of control cabinet(pole MNT) (690-7042) | EACH | 2 | $1,751.50 | $5,836.60 |
| 30 | Replace of flasher cabinet (690-7045) | EACH | 2 | $2,397.88 | $2,789.80 |
| 31 | Replace of signal pole assembly (690-7052) | EACH | 2 | $6,411.90 | $5,836.60 |
| 32 | Removal of concrete foundations (690-7063) | EACH | 2 | $500.00 | $1,904.30 |
| 33 | Replace of luminaire head (690-7065) | EACH | 40 | $565.67 | $602.50 |
| 34 | Install of luminaire head (690-7066) | EACH | 2 | $820.64 | $507.30 |
| 35 | Replace pedestrian pole assembly (690-7088) | EACH | 2 | $2,215.30 | $2,537.50 |
| 36 | Replace LED traffic signal lamp unit (690-7090) | EACH | 50 | $402.60 | $285.70 |
| 37 | Install screw-in FND (690-7128) | EACH | 10 | $805.20 | $1,904.30 |
| 38 | VIVDS cable (install) (690-7137) | LF | 250 | $1.95 | $7.40 |
| 39 | VIVDS camera (install) (690-7138) | EACH | 5 | $1,118.00 | $1,356.60 |
| 40 | Repl vehicle signal tunnel visor (12") (690-7139) | EACH | 30 | $174.98 | $95.30 |
| 41 | Wrap signal cable (690-7140) | LF | 10 | $2.70 | $10.80 |
| 42 | Install electrical splice (690-7157) | EACH | 5 | $99.06 | $163.40 |
| 43 | Install roadway illum assembly (LED) (690-7165) | EACH | 10 | $921.00 | $3,299.60 |
| 44 | Replace high mast luminaires (690-7182) | EACH | 10 | $229.75 | $618.90 |
| 45 | Install foundation (690-7195) | EACH | 3 | $2,000.53 | $5,513.10 |
| 46 | Remove foundation (690-7196) | EACH | 3 | $944.06 | $1,904.30 |
| 47 | Replace fuse (690-7218) | EACH | 20 | $65.98 | $102.90 |
| 48 | Replace fuse holder (690-7219) | EACH | 20 | $100.42 | $259.90 |
| 49 | Raise and lower ring (high mast light) (690-7239) | EACH | 10 | $389.41 | $571.30 |
| 50 | Replace lamp for pole MNT fixture (690-7270) | EACH | 5 | $55.44 | $95.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.