TxDOT contract A00213972 bid tabulation

CABLE BARRIER REPAIR, IH0040 (VARIOUS LOCATIONS ~ SEE PLAN SHEETS to VARIOUS LOCATIONS ~ SEE PLAN SHEETS). Let by Texas DOT on February 27, 2025, Potter, Amarillo District. 6 bids received; low bid $259,524 by BK Field Operations LLC, -29% against the engineer's estimate of $366,100.

Owner
Texas DOT
Letting
27 FEB 2025
Pay items
17
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1BK Field Operations LLC$259,524Low-29%
2Ross Sa Enterprise LLC$293,654+13%-20%
3HJC Farms, Inc.$331,366+28%-9.0%
4E.V.G. Enterprise$359,324+38%-2.0%
5Above All Contracting LLC$360,934+39%-1.0%
6Massana Construction Inc.$450,826+74%+23%
TxDOT contract A00213972: bids by rank

Engineer's estimate: $366,100.

Bid tabulation

LinePay itemUnitQuantityEstimate1. BK Field Operations LLC2. Ross Sa Enterprise LLC3. HJC Farms, Inc.4. E.V.G. Enterprise5. Above All Contracting LLC6. Massana Construction Inc.
1Mobilization (callout) (500-7002)EACH14$2,000.00$1.00$1.00$5.00$1.00$1.00$6,499.00
2TMA (stationary) (505-7001)DAY150$250.00$1.00$1.00$25.00$1.00$1.00$10.00
3Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH300$15.00$1.00$1.00$20.00$5.00$25.00$24.00
4Replace posts (TL-3)(gibraltar) (771-7001)EACH15$5.00$1.00$50.00$100.00$1.00$100.00$225.00
5Replace posts (TL-3)(trinity) (771-7003)EACH15$5.00$1.00$50.00$100.00$1.00$100.00$250.00
6Replace posts (TL-4)(gibraltar) (771-7005)EACH500$240.00$190.00$230.00$250.00$300.00$300.00$189.00
7Replace posts (TL-4)(trinity) (771-7007)EACH500$240.00$190.00$230.00$350.00$300.00$300.00$224.00
8Cable splice / turnbuckle (TL-3) (771-7009)EACH10$5.00$1.00$1.00$1.00$1.00$1.00$435.00
9Cable splice / turnbuckle (TL-4) (771-7010)EACH30$25.00$1.00$1.00$1.00$100.00$1.00$435.00
10Repair concrete foundation (TL-3) (771-7011)EACH10$5.00$1.00$1.00$50.00$1.00$1.00$586.00
11Repair concrete foundation (TL-4) (771-7012)EACH10$5.00$1.00$1.00$50.00$1.00$1.00$586.00
12Repair or replace cable barrier terminal sec(TL-3) (771-7013)EACH10$5.00$1.00$1.00$250.00$1,000.00$1.00$1,500.00
13Repair or replace cable barrier terminal sec(TL-4) (771-7014)EACH20$2,100.00$3,375.00$3,000.00$500.00$2,000.00$2,000.00$1,500.00
14Replace cable (TL-3) (771-7015)LF100$5.00$0.10$1.00$0.01$1.00$1.00$5.45
15Replace cable (TL-4) (771-7016)LF500$5.00$2.50$3.00$0.01$5.00$10.00$5.70
16Check / RE-tension cable (TL-3) (771-7017)EACH100$50.00$1.00$0.10$25.00$10.00$1.00$300.00
17Check / RE-tension cable (TL-4) (771-7018)EACH100$50.00$1.00$0.10$25.00$10.00$50.00$300.00
TxDOT contract A00213972: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy