TxDOT contract A00214256 bid tabulation
TRAFFIC SIGNAL MAINTENANCE, IH0030 (Various Roadways in the to Dallas District). Let by Texas DOT on June 5, 2025, Dallas, Dallas District. 3 bids received; low bid $1,602,621 by Yunex LLC, +11% against the engineer's estimate of $1,440,680.
- Owner
- Texas DOT
- Letting
- 05 JUN 2025
- Pay items
- 143
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Yunex LLC | $1,602,621 | Low | +11% |
| 2 | Durable Specialties, Inc. | $1,750,820 | +9.0% | +22% |
| 3 | WG Engineering & Construction, LLC | $1,773,789 | +11% | +23% |
Engineer's estimate: $1,440,680.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Yunex LLC | 2. Durable Specialties, Inc. | 3. WG Engineering & Construction, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (foundations) (104-7024) | CY | 10 | $350.00 | $525.20 | $150.00 | $109.40 |
| 2 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 30 | $550.00 | $447.90 | $790.00 | $310.00 |
| 3 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 54 | $325.00 | $314.70 | $620.00 | $300.00 |
| 4 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 33 | $625.00 | $486.50 | $810.00 | $350.00 |
| 5 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 26 | $700.00 | $502.90 | $915.00 | $425.00 |
| 6 | Drilled shaft (traffic signal pole) (42 in) (416-7045) | LF | 34 | $700.00 | $504.40 | $1,050.00 | $450.00 |
| 7 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 22 | $825.00 | $846.30 | $1,105.00 | $700.00 |
| 8 | Mobilization (callout) (500-7002) | EACH | 60 | $1,500.00 | $1,234.90 | $2,200.00 | $4,000.00 |
| 9 | Mobilization (emergency) (500-7033) | EACH | 10 | $1,750.00 | $2,469.70 | $3,300.00 | $6,000.00 |
| 10 | Portable changeable message sign (503-7001) | DAY | 20 | $100.00 | $136.30 | $85.00 | $100.00 |
| 11 | TMA (stationary) (505-7001) | DAY | 30 | $400.00 | $284.00 | $750.00 | $340.00 |
| 12 | TMA (mobile operation) (505-7003) | DAY | 100 | $400.00 | $284.00 | $750.00 | $340.00 |
| 13 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 50 | $5.00 | $24.80 | $2.00 | $2.00 |
| 14 | Biodegradable erosion control logs (remove) (506-7046) | LF | 50 | $5.00 | $2.10 | $1.00 | $2.00 |
| 15 | Concrete sidewalks (4") (531-7001) | SY | 40 | $150.00 | $108.00 | $185.00 | $75.00 |
| 16 | Conduit (PVC) (schedule 40) (1") (618-7021) | LF | 300 | $15.00 | $10.51 | $27.00 | $12.00 |
| 17 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 750 | $20.00 | $21.01 | $28.00 | $20.00 |
| 18 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 650 | $30.00 | $37.55 | $63.00 | $28.00 |
| 19 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 400 | $35.00 | $20.20 | $30.00 | $22.00 |
| 20 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 600 | $40.00 | $54.27 | $67.00 | $30.00 |
| 21 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 350 | $40.00 | $25.45 | $33.00 | $25.00 |
| 22 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 600 | $50.00 | $51.29 | $69.00 | $33.00 |
| 23 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 100 | $25.00 | $23.28 | $29.00 | $22.00 |
| 24 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 50 | $35.00 | $39.83 | $64.00 | $28.00 |
| 25 | Conduit (RM) (1") (618-7072) | LF | 150 | $20.00 | $36.56 | $32.00 | $8.00 |
| 26 | Conduit (RM) (1 1/2") (618-7076) | LF | 150 | $25.00 | $37.09 | $33.00 | $12.00 |
| 27 | Conduit (RM) (2") (618-7078) | LF | 150 | $35.00 | $39.93 | $35.00 | $23.00 |
| 28 | Conduit (RM) (3") (618-7082) | LF | 150 | $40.00 | $56.70 | $125.00 | $35.00 |
| 29 | Conduit (RM) (4") (618-7086) | LF | 100 | $45.00 | $84.86 | $130.00 | $40.00 |
| 30 | Conduit (prepare) (618-7090) | LF | 500 | $4.00 | $5.28 | $2.00 | $7.00 |
| 31 | Electrical conductor (no.12) bare (620-7003) | LF | 100 | $2.00 | $2.73 | $2.00 | $1.00 |
| 32 | Electrical conductor (no.12) insulated (620-7004) | LF | 200 | $2.50 | $2.87 | $2.00 | $3.00 |
| 33 | Electrical conductor (no.10) bare (620-7005) | LF | 100 | $2.50 | $2.98 | $2.00 | $2.00 |
| 34 | Electrical conductor (no.10) insulated (620-7006) | LF | 200 | $2.75 | $2.95 | $2.00 | $3.00 |
| 35 | Electrical conductor (no.8) bare (620-7007) | LF | 1,000 | $2.25 | $3.18 | $4.00 | $4.00 |
| 36 | Electrical conductor (no.8) insulated (620-7008) | LF | 2,100 | $2.50 | $3.36 | $4.00 | $4.00 |
| 37 | Electrical conductor (no.6) bare (620-7009) | LF | 500 | $3.00 | $3.55 | $5.00 | $5.00 |
| 38 | Electrical conductor (no.6) insulated (620-7010) | LF | 800 | $3.25 | $3.86 | $5.00 | $5.00 |
| 39 | Electrical conductor (no.4) bare (620-7011) | LF | 100 | $4.00 | $4.00 | $6.00 | $5.00 |
| 40 | Electrical conductor (no.4) insulated (620-7012) | LF | 200 | $4.25 | $4.53 | $6.00 | $5.00 |
| 41 | Electrical conductor (no.2) bare (620-7015) | LF | 50 | $5.00 | $5.00 | $7.00 | $5.00 |
| 42 | Electrical conductor (no.2) insulated (620-7016) | LF | 100 | $5.00 | $5.70 | $7.00 | $5.00 |
| 43 | Tray cable (3 conductor) (12 AWG) (621-7002) | LF | 100 | $3.50 | $3.60 | $4.00 | $5.00 |
| 44 | Tray cable (3 conductor) (8 AWG) (621-7004) | LF | 200 | $3.00 | $4.60 | $4.00 | $6.00 |
| 45 | Ground box type A (122311)W/apron (624-7002) | EACH | 3 | $1,900.00 | $2,008.60 | $2,155.00 | $1,600.00 |
| 46 | Ground box type C (162911)W/apron (624-7006) | EACH | 3 | $2,500.00 | $2,694.20 | $2,250.00 | $2,000.00 |
| 47 | Ground box type D (162922)W/apron (624-7008) | EACH | 3 | $2,500.00 | $3,179.60 | $2,315.00 | $2,000.00 |
| 48 | Remove ground box (624-7013) | EACH | 5 | $400.00 | $617.50 | $350.00 | $350.00 |
| 49 | Zinc-coat steel wire strand (3/16") (625-7001) | LF | 3,000 | $5.00 | $6.87 | $6.00 | $6.00 |
| 50 | Zinc-coat steel wire strand (1/4") (625-7002) | LF | 3,000 | $5.00 | $6.91 | $6.00 | $6.00 |
| 51 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 3,000 | $5.00 | $7.16 | $6.00 | $6.00 |
| 52 | Zinc-coat steel wire strand (3/8") (625-7004) | LF | 3,000 | $5.00 | $7.36 | $6.00 | $8.00 |
| 53 | Remove electrical services (628-7002) | EACH | 5 | $800.00 | $1,234.90 | $750.00 | $1,000.00 |
| 54 | Elc SRV type D 120/240 070(NS)SS(E)GC(O) (628-7188) | EACH | 2 | $12,000 | $7,094.50 | $13,400 | $9,500.00 |
| 55 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 2 | $12,000 | $7,210.40 | $10,400 | $12,000 |
| 56 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 800 | $3.50 | $3.44 | $3.00 | $4.00 |
| 57 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 1,500 | $4.00 | $3.76 | $3.00 | $4.00 |
| 58 | Traffic signal CBL (type A)(14 AWG)(9 conductor) (684-7035) | LF | 2,500 | $4.50 | $4.27 | $5.00 | $4.00 |
| 59 | Traffic signal CBL (type A)(14 AWG)(12 conductor) (684-7038) | LF | 500 | $6.25 | $4.72 | $6.00 | $4.00 |
| 60 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 2,500 | $8.00 | $5.77 | $6.00 | $5.00 |
| 61 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 500 | $9.00 | $8.01 | $8.00 | $7.00 |
| 62 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 800 | $3.50 | $3.35 | $3.00 | $3.00 |
| 63 | Traffic signal CBL (type C)(14 AWG)(2 conductor) (684-7080) | LF | 2,000 | $3.00 | $2.97 | $3.00 | $3.00 |
| 64 | Vehicle LP detect (sawcut) (688-7004) | LF | 300 | $20.00 | $26.87 | $16.00 | $18.00 |
| 65 | Removal of conduit (690-7001) | LF | 100 | $9.00 | $24.70 | $1.00 | $5.00 |
| 66 | Removal of cables (690-7009) | LF | 400 | $2.00 | $2.06 | $1.00 | $8.50 |
| 67 | Replace of cables (690-7010) | LF | 400 | $3.00 | $6.18 | $4.00 | $8.50 |
| 68 | Install of cables (690-7011) | LF | 2,000 | $3.25 | $6.18 | $3.00 | $8.50 |
| 69 | Removal of cables by messenger cable (690-7013) | LF | 400 | $2.50 | $6.18 | $1.00 | $6.00 |
| 70 | Replace of cables by messenger cable (690-7014) | LF | 900 | $4.00 | $8.24 | $4.00 | $6.00 |
| 71 | Install of cables by messenger cable (690-7015) | LF | 900 | $3.50 | $8.24 | $3.00 | $6.00 |
| 72 | Removal of span cable assembly (690-7016) | LF | 1,200 | $2.50 | $3.09 | $1.00 | $2.00 |
| 73 | Replace of span cable assembly (690-7017) | LF | 1,000 | $2.75 | $7.21 | $8.00 | $5.00 |
| 74 | Replace of electrical service (690-7019) | EACH | 2 | $4,500.00 | $6,956.00 | $11,350 | $11,000 |
| 75 | Install of electrical service (690-7020) | EACH | 2 | $4,000.00 | $6,956.00 | $10,400 | $11,000 |
| 76 | Removal of timber poles (690-7021) | EACH | 3 | $725.00 | $1,647.00 | $1,200.00 | $500.00 |
| 77 | Replace of timber poles (690-7022) | EACH | 3 | $1,300.00 | $4,656.00 | $3,600.00 | $1,200.00 |
| 78 | Install of timber poles (690-7023) | EACH | 5 | $1,300.00 | $3,010.00 | $2,400.00 | $1,500.00 |
| 79 | Removal of signal head assembly (690-7024) | EACH | 12 | $175.00 | $206.00 | $150.00 | $50.00 |
| 80 | Replace of signal head assembly (690-7025) | EACH | 12 | $500.00 | $515.00 | $900.00 | $500.00 |
| 81 | Install of signal head assembly (690-7026) | EACH | 10 | $500.00 | $309.00 | $750.00 | $300.00 |
| 82 | Removal of signal related signs (690-7027) | EACH | 10 | $75.00 | $258.00 | $100.00 | $75.00 |
| 83 | Replace of signal related signs (690-7028) | EACH | 10 | $350.00 | $515.00 | $150.00 | $400.00 |
| 84 | Install of signal related signs (690-7029) | EACH | 10 | $375.00 | $361.00 | $125.00 | $400.00 |
| 85 | Removal of pedestrian push buttons (690-7030) | EACH | 7 | $90.00 | $52.00 | $50.00 | $10.00 |
| 86 | Replace of pedestrian push buttons (690-7031) | EACH | 7 | $400.00 | $591.00 | $150.00 | $700.00 |
| 87 | Install of pedestrian push buttons (690-7032) | EACH | 7 | $400.00 | $591.00 | $175.00 | $300.00 |
| 88 | Install of FND for ground MNT cabinets (690-7036) | EACH | 2 | $3,000.00 | $3,379.00 | $7,800.00 | $3,000.00 |
| 89 | Install of FND for pole MNT cabinets (690-7037) | EACH | 2 | $2,000.00 | $3,379.00 | $6,600.00 | $2,500.00 |
| 90 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 2 | $650.00 | $1,030.00 | $1,350.00 | $1,000.00 |
| 91 | Replace of control cabinet(GRND MNT) (690-7039) | EACH | 2 | $3,500.00 | $5,714.00 | $9,000.00 | $5,100.00 |
| 92 | Install of control cabinet(GRND MNT) (690-7040) | EACH | 2 | $2,500.00 | $3,656.00 | $9,000.00 | $4,000.00 |
| 93 | Removal of control cabinet(pole MNT) (690-7041) | EACH | 2 | $1,000.00 | $1,235.00 | $1,200.00 | $900.00 |
| 94 | Replace of control cabinet(pole MNT) (690-7042) | EACH | 2 | $1,750.00 | $3,634.00 | $10,000 | $3,000.00 |
| 95 | Install of control cabinet(pole MNT) (690-7043) | EACH | 2 | $2,000.00 | $2,811.00 | $10,000 | $2,800.00 |
| 96 | Removal of flasher cabinet (690-7044) | EACH | 2 | $350.00 | $464.00 | $500.00 | $300.00 |
| 97 | Replace of flasher cabinet (690-7045) | EACH | 2 | $800.00 | $2,811.00 | $2,500.00 | $1,700.00 |
| 98 | Install of flasher cabinet (690-7046) | EACH | 2 | $700.00 | $2,811.00 | $1,700.00 | $2,200.00 |
| 99 | Removal of RDSD FLSH beacon assembly (690-7048) | EACH | 2 | $350.00 | $1,235.00 | $1,500.00 | $1,000.00 |
| 100 | Replace of RDSD FLSH beacon assembly (690-7049) | EACH | 2 | $3,500.00 | $5,252.00 | $4,500.00 | $7,000.00 |
| 101 | Install of RDSD FLSH beacon assembly (690-7050) | EACH | 2 | $3,500.00 | $5,252.00 | $3,000.00 | $8,000.00 |
| 102 | Removal of signal pole assembly (690-7051) | EACH | 2 | $1,400.00 | $2,470.00 | $2,500.00 | $2,000.00 |
| 103 | Replace of signal pole assembly (690-7052) | EACH | 2 | $4,500.00 | $4,685.00 | $8,050.00 | $7,000.00 |
| 104 | Install of signal pole assembly (690-7053) | EACH | 2 | $2,500.00 | $3,861.00 | $7,000.00 | $5,000.00 |
| 105 | Removal of luminaire head (690-7064) | EACH | 5 | $200.00 | $155.00 | $175.00 | $50.00 |
| 106 | Replace of luminaire head (690-7065) | EACH | 5 | $550.00 | $309.00 | $520.00 | $575.00 |
| 107 | Install of luminaire head (690-7066) | EACH | 5 | $400.00 | $155.00 | $350.00 | $450.00 |
| 108 | Removal of luminaire mast arms (690-7067) | EACH | 5 | $200.00 | $824.00 | $175.00 | $50.00 |
| 109 | Replace of luminaire mast arms (690-7068) | EACH | 5 | $500.00 | $1,235.00 | $700.00 | $100.00 |
| 110 | Install of luminaire mast arms (690-7069) | EACH | 5 | $500.00 | $824.00 | $520.00 | $100.00 |
| 111 | Install down guy W/guard (690-7078) | EACH | 6 | $300.00 | $464.00 | $520.00 | $250.00 |
| 112 | Replace down guy W/guard (690-7079) | EACH | 6 | $375.00 | $515.00 | $700.00 | $250.00 |
| 113 | Install down guy and anchor W/guard (690-7081) | EACH | 8 | $250.00 | $618.00 | $700.00 | $250.00 |
| 114 | Replace down guy and anchor W/guard (690-7082) | EACH | 8 | $350.00 | $618.00 | $900.00 | $400.00 |
| 115 | Install vid image vehicle det sys (VIVDS) (690-7084) | EACH | 5 | $800.00 | $4,940.00 | $950.00 | $500.00 |
| 116 | Replace vid image vehicle det sys (VIVDS) (690-7085) | EACH | 5 | $1,000.00 | $5,565.00 | $1,100.00 | $500.00 |
| 117 | Remove vid image vehicle det sys (VIVDS) (690-7086) | EACH | 5 | $450.00 | $3,293.00 | $200.00 | $1,200.00 |
| 118 | Install pedestrian pole assembly (690-7087) | EACH | 2 | $1,500.00 | $1,803.00 | $1,500.00 | $1,100.00 |
| 119 | Replace pedestrian pole assembly (690-7088) | EACH | 2 | $1,000.00 | $1,803.00 | $2,000.00 | $2,000.00 |
| 120 | Remove pedestrian pole assembly (690-7089) | EACH | 2 | $500.00 | $824.00 | $500.00 | $500.00 |
| 121 | Replace LED traffic signal lamp unit (690-7090) | EACH | 120 | $175.00 | $206.00 | $145.00 | $250.00 |
| 122 | Replace pedestrian signal LED traffic signal lamp unit (690-7093) | EACH | 30 | $125.00 | $258.00 | $200.00 | $225.00 |
| 123 | Install pedestrian sign LED traffic signal amp unit (690-7095) | EACH | 15 | $100.00 | $206.00 | $115.00 | $225.00 |
| 124 | Salvage traffic signal (690-7099) | EACH | 3 | $2,000.00 | $1,441.00 | $4,000.00 | $2,000.00 |
| 125 | Relocate of pedestrian push button (690-7123) | EACH | 9 | $225.00 | $412.00 | $270.00 | $75.00 |
| 126 | Install luminaire pole (690-7125) | EACH | 3 | $2,000.00 | $1,576.00 | $2,500.00 | $900.00 |
| 127 | Replace luminaire pole (690-7126) | EACH | 2 | $1,400.00 | $1,988.00 | $3,000.00 | $900.00 |
| 128 | Remove luminaire pole (690-7127) | EACH | 3 | $1,250.00 | $927.00 | $500.00 | $900.00 |
| 129 | Install screw-in FND (690-7128) | EACH | 6 | $850.00 | $2,279.00 | $900.00 | $2,000.00 |
| 130 | Remove screw-in FND (690-7129) | EACH | 3 | $350.00 | $464.00 | $300.00 | $700.00 |
| 131 | Replace controller breakaway base (690-7130) | EACH | 3 | $1,000.00 | $3,861.00 | $1,200.00 | $900.00 |
| 132 | Install bbu system (690-7131) | EACH | 3 | $5,000.00 | $2,754.00 | $950.00 | $500.00 |
| 133 | Replace bbu system (690-7133) | EACH | 3 | $5,000.00 | $4,401.00 | $1,100.00 | $1,000.00 |
| 134 | Install radar vehicle detection system (690-7134) | EACH | 5 | $3,500.00 | $3,095.00 | $1,250.00 | $2,200.00 |
| 135 | Replace radar vehicle detection system (690-7135) | EACH | 5 | $1,650.00 | $4,741.00 | $1,500.00 | $1,500.00 |
| 136 | Remove radar vehicle detection system (690-7136) | EACH | 5 | $650.00 | $1,647.00 | $250.00 | $250.00 |
| 137 | Repl vehicle signal tunnel visor (12") (690-7139) | EACH | 5 | $250.00 | $155.00 | $105.00 | $30.00 |
| 138 | VIVDS cabling (6006-7007) | LF | 3,000 | $5.00 | $6.00 | $3.00 | $4.00 |
| 139 | RVDS (presence detection only) (6008-7001) | EACH | 3 | $12,000 | $11,302 | $12,000 | $12,000 |
| 140 | RVDS (advance detection only) (6008-7002) | EACH | 3 | $13,000 | $11,302 | $12,000 | $12,000 |
| 141 | RVDS (presence and advance detection) (6008-7003) | EACH | 3 | $14,000 | $12,948 | $12,000 | $20,500 |
| 142 | Ground box (prepare) (6013-7006) | EACH | 15 | $500.00 | $217.00 | $205.00 | $400.00 |
| 143 | Preventive maintenance (6029-7001) | EACH | 175 | $2,000.00 | $1,900.00 | $1,750.00 | $2,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.