TxDOT contract A00216188 bid tabulation
CLEANING AND SWEEPING HIGHWAYS, FM1764 (VARIOUS HWYS IN GALVESTON COUNTY to VARIOUS HWYS IN GALVESTON COUNTY). Let by Texas DOT on September 4, 2025, Galveston, Houston District. 3 bids received; low bid $997,155 by Sweeping Corporation of America, LLC, -18% against the engineer's estimate of $1,217,394.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 63
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sweeping Corporation of America, LLC | $997,155 | Low | -18% |
| 2 | T & M Lawn-Fence Service, LLC | $1,099,450 | +10% | -10% |
| 3 | Professional Traffic Control LLC | $1,297,200 | +30% | +7.0% |
Engineer's estimate: $1,217,394.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Sweeping Corporation of America, LLC | 2. T & M Lawn-Fence Service, LLC | 3. Professional Traffic Control LLC |
|---|---|---|---|---|---|---|---|
| 1 | Mobilization (callout) (500-7002) | EACH | 12 | $100.00 | $5,000.00 | $3,000.00 | $2,400.00 |
| 2 | Mobilization (emergency) (500-7033) | EACH | 2 | $461.60 | $500.00 | $500.00 | $1,000.00 |
| 3 | TMA (stationary) (505-7001) | DAY | 75 | $225.50 | $1.00 | $30.00 | $100.00 |
| 4 | TMA (mobile operation) (505-7003) | DAY | 250 | $346.05 | $1.00 | $100.00 | $700.00 |
| 5 | Debris removing-CNTR med/MN LNS/ramps (735-7002) | CYC | 24 | $5,850.00 | $500.00 | $2,000.00 | $2,000.00 |
| 6 | Debris removal (frontage roads) (735-7026) | CYC | 24 | $3,624.00 | $500.00 | $2,000.00 | $1,500.00 |
| 7 | Debris removal (entrance/exit ramps) (735-7038) | CYC | 24 | $3,634.00 | $500.00 | $2,000.00 | $1,500.00 |
| 8 | Cleaning / sweeping (center median) (738-7004) | CYC | 6 | $600.00 | $185.00 | $1,200.00 | $600.00 |
| 9 | Clean / sweep - center median - area(2) (738-7006) | CYC | 6 | $961.42 | $740.00 | $1,000.00 | $600.00 |
| 10 | Clean / sweep - center median - area(3) (738-7007) | CYC | 6 | $2,100.00 | $3,885.00 | $3,500.00 | $3,000.00 |
| 11 | Clean / sweep - center median - area(4) (738-7008) | CYC | 6 | $1,500.00 | $2,960.00 | $2,600.00 | $2,400.00 |
| 12 | Clean / sweep - center median - area(5) (738-7009) | CYC | 6 | $800.00 | $1,295.00 | $1,000.00 | $1,000.00 |
| 13 | Clean / sweep - center median - area(6) (738-7010) | CYC | 6 | $700.00 | $1,110.00 | $1,000.00 | $900.00 |
| 14 | Clean / sweep - center median - area(7) (738-7011) | CYC | 6 | $2,150.00 | $4,255.00 | $1,500.00 | $3,400.00 |
| 15 | Clean / sweep - center median - area(9) (738-7013) | CYC | 12 | $1,100.00 | $1,480.00 | $1,200.00 | $1,200.00 |
| 16 | Clean / sweep - center median-area (10) (738-7014) | CYC | 6 | $600.00 | $925.00 | $1,000.00 | $750.00 |
| 17 | Clean / sweep - center median-area (11) (738-7015) | CYC | 6 | $1,000.00 | $1,480.00 | $1,200.00 | $1,200.00 |
| 18 | Clean / sweep - center median-area (12) (738-7016) | CYC | 6 | $1,000.00 | $2,590.00 | $2,200.00 | $2,100.00 |
| 19 | Clean / sweep - center median-area (13) (738-7017) | CYC | 6 | $600.00 | $925.00 | $1,000.00 | $750.00 |
| 20 | Clean / sweep - center median-area (14) (738-7018) | CYC | 6 | $600.00 | $555.00 | $1,000.00 | $450.00 |
| 21 | Clean / sweep - center median-area (15) (738-7019) | CYC | 6 | $2,000.00 | $4,070.00 | $3,800.00 | $3,300.00 |
| 22 | Clean / sweep - center median-area (17) (738-7021) | CYC | 6 | $683.33 | $740.00 | $1,000.00 | $1,350.00 |
| 23 | Clean / sweep - center median-area (19) (738-7023) | CYC | 12 | $1,500.00 | $3,145.00 | $3,000.00 | $2,500.00 |
| 24 | Clean / sweep - center median-area (20) (738-7024) | CYC | 12 | $1,500.00 | $3,330.00 | $3,000.00 | $2,700.00 |
| 25 | Clean / sweep-outside main lane-area(2) (738-7030) | CYC | 6 | $904.28 | $740.00 | $1,000.00 | $600.00 |
| 26 | Clean / sweep-outside main lane-area(3) (738-7031) | CYC | 6 | $1,000.00 | $3,885.00 | $3,400.00 | $3,150.00 |
| 27 | Clean / sweep-outside main lane-area(4) (738-7032) | CYC | 6 | $1,000.00 | $2,960.00 | $2,600.00 | $2,400.00 |
| 28 | Clean / sweep-outside main lane-area(5) (738-7033) | CYC | 6 | $1,000.00 | $1,295.00 | $1,000.00 | $1,050.00 |
| 29 | Clean / sweep-outside main lane-area(6) (738-7034) | CYC | 6 | $1,000.00 | $1,110.00 | $1,000.00 | $900.00 |
| 30 | Clean / sweep-outside main lane-area(7) (738-7035) | CYC | 6 | $12,000 | $4,255.00 | $1,500.00 | $3,450.00 |
| 31 | Clean / sweep-outside main lane-area(9) (738-7037) | CYC | 12 | $1,100.00 | $1,480.00 | $1,200.00 | $1,200.00 |
| 32 | Clean /sweep-outside main lane-area(10) (738-7038) | CYC | 6 | $700.00 | $925.00 | $1,000.00 | $750.00 |
| 33 | Clean /sweep-outside main lane-area(11) (738-7039) | CYC | 6 | $1,000.00 | $1,480.00 | $1,200.00 | $1,200.00 |
| 34 | Clean /sweep-outside main lane-area(12) (738-7040) | CYC | 6 | $1,000.00 | $2,590.00 | $2,200.00 | $2,100.00 |
| 35 | Clean /sweep-outside main lane-area(13) (738-7041) | CYC | 6 | $700.00 | $925.00 | $1,000.00 | $750.00 |
| 36 | Clean /sweep-outside main lane-area(14) (738-7042) | CYC | 6 | $1,000.00 | $555.00 | $1,000.00 | $450.00 |
| 37 | Clean /sweep-outside main lane-area(15) (738-7043) | CYC | 6 | $600.00 | $4,070.00 | $3,800.00 | $3,300.00 |
| 38 | Clean /sweep-outside main lane-area(17) (738-7045) | CYC | 4 | $500.00 | $740.00 | $1,000.00 | $600.00 |
| 39 | Clean /sweep-outside main lane-area(18) (738-7046) | CYC | 6 | $950.00 | $1,665.00 | $1,200.00 | $1,350.00 |
| 40 | Clean /sweep-outside main lane-area(19) (738-7047) | CYC | 12 | $1,200.00 | $3,145.00 | $3,000.00 | $2,550.00 |
| 41 | Clean /sweep-outside main lane-area(20) (738-7048) | CYC | 12 | $1,200.00 | $3,330.00 | $3,000.00 | $2,700.00 |
| 42 | Clean / sweep - frontage road - area(9) (738-7059) | CYC | 12 | $1,000.00 | $1,480.00 | $1,000.00 | $1,200.00 |
| 43 | Clean / sweep - (entr /ext RMP)(area 9) (738-7080) | CYC | 12 | $1,000.00 | $1,480.00 | $1,000.00 | $1,200.00 |
| 44 | Cleaning / sweeping (spot) (738-7104) | MI | 40 | $23.00 | $125.00 | $50.00 | $200.00 |
| 45 | Handwork - drain slots, barrier slots (738-7111) | SY | 1,000 | $0.14 | $0.75 | $4.00 | $10.00 |
| 46 | Clean/sweep-center median-area 28 (738-7112) | CYC | 12 | $1,000.00 | $370.00 | $1,000.00 | $300.00 |
| 47 | Clean/sweep-center median-area 29 (738-7113) | CYC | 24 | $5,850.00 | $1,200.00 | $2,000.00 | $4,000.00 |
| 48 | Clean/sweep-outside main lane-area 21 (738-7114) | CYC | 4 | $1,000.00 | $6,475.00 | $5,500.00 | $5,250.00 |
| 49 | Clean/sweep-outside main lane-area 22 (738-7115) | CYC | 6 | $950.00 | $1,295.00 | $1,200.00 | $1,000.00 |
| 50 | Clean/sweep-outside main lane-area 23 (738-7116) | CYC | 4 | $750.00 | $740.00 | $1,000.00 | $600.00 |
| 51 | Clean/sweep-outside main lane-area 24 (738-7117) | CYC | 12 | $1,000.00 | $2,960.00 | $2,700.00 | $2,400.00 |
| 52 | Clean/sweep-outside main lane-area 26 (738-7119) | CYC | 12 | $1,000.00 | $1,295.00 | $1,200.00 | $1,000.00 |
| 53 | Clean/sweep-outside main lane-area 27 (738-7120) | CYC | 4 | $350.00 | $185.00 | $1,000.00 | $150.00 |
| 54 | Clean/sweep-outside main lane-area 28 (738-7121) | CYC | 12 | $1,100.00 | $370.00 | $1,000.00 | $300.00 |
| 55 | Clean/sweep-outside main lane-area 29 (738-7122) | CYC | 24 | $5,850.00 | $1,200.00 | $2,000.00 | $4,000.00 |
| 56 | Clean / sweep-center median - area(21) (738-7125) | CYC | 4 | $1,000.00 | $6,475.00 | $5,500.00 | $5,250.00 |
| 57 | Clean / sweep-center median - area(22) (738-7126) | CYC | 6 | $1,000.00 | $1,295.00 | $1,200.00 | $1,000.00 |
| 58 | Clean / sweep-center median - area(24) (738-7127) | CYC | 12 | $1,000.00 | $2,960.00 | $2,700.00 | $2,400.00 |
| 59 | Clean/sweep-center median - area (26) (738-7131) | CYC | 24 | $1,000.00 | $1,295.00 | $1,200.00 | $1,000.00 |
| 60 | Clean/sweep-frontage road - area (24) (738-7132) | CYC | 12 | $1,500.00 | $2,960.00 | $2,700.00 | $2,400.00 |
| 61 | Clean/sweep-frontage road - area (29) (738-7133) | CYC | 12 | $1,000.00 | $1,200.00 | $2,000.00 | $4,000.00 |
| 62 | Clean/sweep - (entr/ext RMP) (AREA24) (738-7134) | CYC | 6 | $1,000.00 | $2,960.00 | $2,700.00 | $2,400.00 |
| 63 | Clean/sweep - (entr/ext RMP) (area 29) (738-7135) | CYC | 24 | $1,000.00 | $1,200.00 | $2,000.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.