TxDOT contract A00217549 bid tabulation
TRAFFIC SIGNAL MAINTENANCE, IH0035 (VARIOUS LOCATIONS to IN THE SAN ANTONIO DISTRICT). Let by Texas DOT on September 17, 2025, Bexar, San Antonio District. 2 bids received; low bid $399,960 by E-Z Bel Construction, LLC, +8.2% against the engineer's estimate of $369,806.
- Owner
- Texas DOT
- Letting
- 17 SEP 2025
- Pay items
- 71
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E-Z Bel Construction, LLC | $399,960 | Low | +8.0% |
| 2 | Elecnor Belco Electric, Inc. | $574,841 | +44% | +55% |
Engineer's estimate: $369,806.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E-Z Bel Construction, LLC | 2. Elecnor Belco Electric, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete (miscellaneous) (104-7047) | CY | 5 | $42.35 | $30.00 | $415.00 |
| 2 | Drilled shaft (non - reinforced) (12 in) (416-7024) | LF | 10 | $90.75 | $100.00 | $1,058.00 |
| 3 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 10 | $199.65 | $240.00 | $342.00 |
| 4 | Mobilization (callout) (500-7002) | EACH | 8 | $4,114.00 | $3,900.00 | $7,300.00 |
| 5 | Mobilization (emergency) (500-7033) | EACH | 8 | $7,500.00 | $3,900.00 | $7,300.00 |
| 6 | TMA (stationary) (505-7001) | DAY | 10 | $242.00 | $550.00 | $225.00 |
| 7 | Concrete directional island (536-7004) | SY | 50 | $78.65 | $100.00 | $552.00 |
| 8 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 750 | $3.63 | $7.00 | $4.00 |
| 9 | Install of conduit by trenching (690-7002) | LF | 100 | $30.25 | $60.00 | $36.00 |
| 10 | Install of conduit by boring (690-7004) | LF | 200 | $60.50 | $60.00 | $43.00 |
| 11 | Removal of ground boxes (690-7006) | EACH | 2 | $60.50 | $150.00 | $250.00 |
| 12 | Replace of cables (690-7010) | LF | 500 | $24.20 | $14.00 | $9.00 |
| 13 | Install of cables (690-7011) | LF | 7,000 | $9.08 | $14.00 | $7.00 |
| 14 | Removal of span cable assembly (690-7016) | LF | 800 | $2.20 | $2.00 | $2.00 |
| 15 | Replace of span cable assembly (690-7017) | LF | 800 | $4.84 | $5.00 | $6.00 |
| 16 | Install of span cable assembly (690-7018) | LF | 800 | $4.84 | $5.00 | $4.00 |
| 17 | Replace of electrical service (690-7019) | EACH | 2 | $4,235.00 | $5,500.00 | $7,550.00 |
| 18 | Install of electrical service (690-7020) | EACH | 2 | $4,840.00 | $5,500.00 | $6,622.00 |
| 19 | Removal of timber poles (690-7021) | EACH | 2 | $272.25 | $500.00 | $1,100.00 |
| 20 | Replace of timber poles (690-7022) | EACH | 2 | $1,815.00 | $1,500.00 | $5,500.00 |
| 21 | Install of timber poles (690-7023) | EACH | 2 | $1,815.00 | $1,500.00 | $4,500.00 |
| 22 | Replace of signal head assembly (690-7025) | EACH | 20 | $996.44 | $1,700.00 | $1,205.00 |
| 23 | Install of signal head assembly (690-7026) | EACH | 8 | $968.00 | $1,700.00 | $993.00 |
| 24 | Replace of signal related signs (690-7028) | EACH | 10 | $272.25 | $650.00 | $240.00 |
| 25 | Install of signal related signs (690-7029) | EACH | 10 | $271.65 | $650.00 | $180.00 |
| 26 | Replace of pedestrian push buttons (690-7031) | EACH | 10 | $484.00 | $600.00 | $1,362.00 |
| 27 | Install of pedestrian push buttons (690-7032) | EACH | 4 | $484.00 | $600.00 | $1,258.00 |
| 28 | Removal of traffic signal pole FND (690-7033) | LF | 8 | $60.50 | $120.00 | $1,500.00 |
| 29 | Install of FND for ground MNT cabinets (690-7036) | EACH | 2 | $3,025.00 | $2,250.00 | $1,500.00 |
| 30 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 2 | $907.50 | $1,000.00 | $500.00 |
| 31 | Install of control cabinet(GRND MNT) (690-7040) | EACH | 2 | $2,420.00 | $2,500.00 | $2,700.00 |
| 32 | Removal of flasher cabinet (690-7044) | EACH | 2 | $60.50 | $100.00 | $500.00 |
| 33 | Replace of flasher cabinet (690-7045) | EACH | 2 | $181.50 | $250.00 | $2,600.00 |
| 34 | Install of flasher cabinet (690-7046) | EACH | 2 | $181.50 | $250.00 | $2,100.00 |
| 35 | Install of FND for RDSD FLSH bea assembly (690-7047) | EACH | 4 | $1,103.52 | $650.00 | $1,500.00 |
| 36 | Removal of RDSD FLSH beacon assembly (690-7048) | EACH | 2 | $121.00 | $100.00 | $1,600.00 |
| 37 | Replace of RDSD FLSH beacon assembly (690-7049) | EACH | 2 | $605.00 | $550.00 | $4,000.00 |
| 38 | Install of RDSD FLSH beacon assembly (690-7050) | EACH | 4 | $605.00 | $550.00 | $3,500.00 |
| 39 | Replace of signal pole assembly (690-7052) | EACH | 4 | $1,573.00 | $2,500.00 | $3,800.00 |
| 40 | Install of signal pole assembly (690-7053) | EACH | 1 | $1,573.00 | $2,500.00 | $2,200.00 |
| 41 | Removal of curbs (690-7054) | LF | 25 | $3.63 | $10.00 | $114.00 |
| 42 | Replace of curbs (690-7055) | LF | 50 | $12.10 | $25.00 | $78.00 |
| 43 | Install of curbs (690-7056) | LF | 50 | $12.10 | $25.00 | $78.00 |
| 44 | Removal of pedestrian ramps (690-7057) | EACH | 1 | $1,512.50 | $895.00 | $2,845.00 |
| 45 | Install of pedestrian ramps (690-7059) | EACH | 1 | $1,512.50 | $2,000.00 | $5,519.00 |
| 46 | Removal of sidewalks (690-7060) | SF | 50 | $10.89 | $15.00 | $57.00 |
| 47 | Install of sidewalks (690-7062) | SF | 20 | $10.89 | $30.00 | $325.00 |
| 48 | Removal of concrete foundations (690-7063) | EACH | 2 | $121.00 | $250.00 | $6,372.00 |
| 49 | Replace of luminaire head (690-7065) | EACH | 2 | $181.50 | $150.00 | $310.00 |
| 50 | Install of luminaire head (690-7066) | EACH | 3 | $181.50 | $150.00 | $210.00 |
| 51 | Replace of luminaire mast arms (690-7068) | EACH | 3 | $181.50 | $150.00 | $1,000.00 |
| 52 | Install of luminaire mast arms (690-7069) | EACH | 3 | $181.50 | $150.00 | $800.00 |
| 53 | Ins of traffic signal PL FND (24" dril SHFT) (690-7070) | LF | 10 | $193.60 | $150.00 | $310.00 |
| 54 | Ins of traffic signal PL FND (30" dril SHFT) (690-7071) | LF | 12 | $302.50 | $385.00 | $342.00 |
| 55 | Ins of traffic signal PL FND (36" dril SHFT) (690-7072) | LF | 15 | $332.75 | $385.00 | $386.00 |
| 56 | Ins of traffic signal PL FND (42" dril SHFT) (690-7073) | LF | 12 | $302.50 | $150.00 | $431.00 |
| 57 | Ins of traffic signal PL FND (48" dril SHFT) (690-7074) | LF | 12 | $423.50 | $385.00 | $521.00 |
| 58 | Install down guy and anchor W/guard (690-7081) | EACH | 1 | $484.00 | $720.00 | $4,800.00 |
| 59 | Replace down guy and anchor W/guard (690-7082) | EACH | 1 | $484.00 | $720.00 | $5,800.00 |
| 60 | Install vid image vehicle det sys (VIVDS) (690-7084) | EACH | 10 | $363.00 | $400.00 | $1,100.00 |
| 61 | Replace vid image vehicle det sys (VIVDS) (690-7085) | EACH | 4 | $6,121.50 | $400.00 | $1,500.00 |
| 62 | Install pedestrian pole assembly (690-7087) | EACH | 2 | $302.50 | $300.00 | $2,000.00 |
| 63 | Replace pedestrian pole assembly (690-7088) | EACH | 2 | $302.50 | $300.00 | $3,000.00 |
| 64 | Remove traffic signal (690-7100) | EACH | 1 | $1,996.50 | $3,000.00 | $2,500.00 |
| 65 | Replace luminaire pole (690-7126) | EACH | 2 | $605.00 | $1,300.00 | $2,900.00 |
| 66 | Install radar vehicle detection system (690-7134) | EACH | 10 | $363.00 | $550.00 | $1,100.00 |
| 67 | Replace radar vehicle detection system (690-7135) | EACH | 4 | $363.00 | $550.00 | $2,000.00 |
| 68 | Remove radar vehicle detection system (690-7136) | EACH | 1 | $242.00 | $200.00 | $500.00 |
| 69 | VIVDS cable (install) (690-7137) | LF | 500 | $2.42 | $7.00 | $3.00 |
| 70 | Install ground box W/apron (690-7194) | EACH | 2 | $605.00 | $1,000.00 | $1,700.00 |
| 71 | Remove foundation (690-7196) | EACH | 2 | $211.75 | $200.00 | $2,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.