TxDOT contract A00217878 bid tabulation
ILLUMINATION MAINTENANCE, US0082 (Various locations in to Paris District). Let by Texas DOT on November 20, 2025, Lamar, Paris District. 3 bids received; low bid $488,025 by Vaca Underground Utilities Inc, -1.9% against the engineer's estimate of $497,445.
- Owner
- Texas DOT
- Letting
- 20 NOV 2025
- Pay items
- 33
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Vaca Underground Utilities Inc | $488,025 | Low | -2.0% |
| 2 | American Lighting and Signalization, LLC | $551,715 | +13% | +11% |
| 3 | North Texas Traffic Systems Construction | $557,060 | +14% | +12% |
Engineer's estimate: $497,445.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Vaca Underground Utilities Inc | 2. American Lighting and Signalization, LLC | 3. North Texas Traffic Systems Construction |
|---|---|---|---|---|---|---|---|
| 1 | Riprap (concrete)(CL C) (432-7006) | CY | 10 | $1,000.00 | $2,000.00 | $800.00 | $600.00 |
| 2 | Mobilization (callout) (500-7002) | EACH | 10 | $3,000.00 | $7,500.00 | $4,250.00 | $5,150.00 |
| 3 | TMA (stationary) (505-7001) | DAY | 60 | $210.00 | $250.00 | $300.00 | $600.00 |
| 4 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 2 | $3,000.00 | $350.00 | $850.00 | $1,150.00 |
| 5 | Remove RD IL asm (trans-base) (610-7009) | EACH | 1 | $1,400.00 | $1,500.00 | $950.00 | $750.00 |
| 6 | Elc SRV type A 120/240 060(NS)AL(E)SP(O) (628-7004) | EACH | 2 | $7,000.00 | $5,500.00 | $9,000.00 | $2,500.00 |
| 7 | Install of duct cables (690-7012) | LF | 2,000 | $15.00 | $15.00 | $28.00 | $16.00 |
| 8 | Replace of electrical service (690-7019) | EACH | 2 | $5,500.00 | $1,500.00 | $3,000.00 | $2,500.00 |
| 9 | Replace above-ground conduit (690-7145) | LF | 25 | $30.00 | $15.00 | $25.00 | $20.00 |
| 10 | Install conductor (690-7149) | LF | 1,500 | $4.00 | $2.00 | $5.00 | $8.00 |
| 11 | Replace conductor (690-7151) | LF | 1,500 | $4.00 | $2.00 | $5.00 | $12.50 |
| 12 | Replace duct cable (690-7156) | LF | 4,000 | $15.00 | $15.00 | $28.00 | $18.00 |
| 13 | Install electrical splice (690-7157) | EACH | 2 | $60.00 | $50.00 | $100.00 | $200.00 |
| 14 | Road bore (690-7161) | LF | 1,000 | $25.00 | $25.00 | $38.00 | $40.00 |
| 15 | Install roadway illum assembly (LED) (690-7165) | EACH | 10 | $1,300.00 | $3,500.00 | $2,700.00 | $1,100.00 |
| 16 | Replace roadway illum assembly (LED) (690-7167) | EACH | 25 | $3,500.00 | $2,500.00 | $2,700.00 | $3,500.00 |
| 17 | Replace high mast luminaires (690-7182) | EACH | 5 | $1,000.00 | $750.00 | $550.00 | $450.00 |
| 18 | Schedule prev maintenance (high mast assembly) (690-7190) | EACH | 35 | $815.00 | $1,000.00 | $200.00 | $900.00 |
| 19 | Replace steel service pole (690-7192) | EACH | 1 | $2,900.00 | $1,500.00 | $2,550.00 | $750.00 |
| 20 | Install ground box W/apron (690-7194) | EACH | 2 | $1,000.00 | $1,000.00 | $2,100.00 | $750.00 |
| 21 | Install foundation (690-7195) | EACH | 20 | $2,500.00 | $2,500.00 | $2,800.00 | $2,200.00 |
| 22 | Replace transformer base (690-7197) | EACH | 5 | $1,000.00 | $500.00 | $1,250.00 | $900.00 |
| 23 | Replace transformer base cover (690-7198) | EACH | 3 | $150.00 | $50.00 | $30.00 | $20.00 |
| 24 | Replace fuse (690-7218) | EACH | 60 | $50.00 | $50.00 | $10.00 | $20.00 |
| 25 | Replace fuse holder (690-7219) | EACH | 30 | $225.00 | $50.00 | $35.00 | $175.00 |
| 26 | Replace photocell and bracket (690-7222) | EACH | 5 | $135.00 | $50.00 | $50.00 | $100.00 |
| 27 | Replace hand-off-auto switch (690-7229) | EACH | 5 | $200.00 | $50.00 | $50.00 | $150.00 |
| 28 | Replace contactor (690-7230) | EACH | 1 | $375.00 | $50.00 | $100.00 | $250.00 |
| 29 | Replace breaker panel (690-7233) | EACH | 1 | $800.00 | $250.00 | $1,750.00 | $750.00 |
| 30 | Install circuit breaker (690-7234) | EACH | 1 | $400.00 | $50.00 | $50.00 | $200.00 |
| 31 | Replace circuit breaker (690-7235) | EACH | 2 | $150.00 | $50.00 | $50.00 | $200.00 |
| 32 | Replace luminaires (690-7244) | EACH | 100 | $750.00 | $350.00 | $500.00 | $815.00 |
| 33 | Replace 3/8" wire rope (690-7280) | EACH | 1 | $1,900.00 | $7,500.00 | $7,250.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.