TxDOT contract A00220226 bid tabulation
Surfacing/Roadway Restoration, SH 360 (Arkansas Ln to SH 180). Let by Texas DOT on September 3, 2026, Tarrant, Fort Worth District. 6 bids received; low bid $4,581,050 by Foutsco Paving Company, LLC, -12% against the engineer's estimate of $5,198,453.
- Owner
- Texas DOT
- Letting
- 03 SEP 2026
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foutsco Paving Company, LLC | $4,581,050 | Low | -12% |
| 2 | O. Trevino Construction, LLC | $4,914,580 | +7.0% | -5.0% |
| 3 | Ed Bell Construction Company | $5,075,030 | +11% | -2.0% |
| 4 | Silver Creek Construction, Inc. | $5,120,757 | +12% | -1.0% |
| 5 | Select Maintenance, L.L.C. | $5,772,348 | +26% | +11% |
| 6 | Emery Sapp & Son'S Inc. | $7,727,534 | +69% | +49% |
Engineer's estimate: $5,198,453.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foutsco Paving Company, LLC | 2. O. Trevino Construction, LLC | 3. Ed Bell Construction Company | 4. Silver Creek Construction, Inc. | 5. Select Maintenance, L.L.C. | 6. Emery Sapp & Son'S Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lime (quicklime (dry)) (260-7002) | TON | 120 | $360.00 | $250.00 | $330.00 | $365.00 | $375.00 | $320.00 | $385.00 |
| 2 | Lime TRT (existing material)(6") (260-7006) | SY | 12,000 | $8.50 | $3.00 | $21.00 | $13.00 | $18.00 | $19.00 | $24.00 |
| 3 | Full - depth repair CRCP (8") (361-7049) | SY | 12,000 | $200.00 | $175.00 | $157.00 | $185.00 | $197.54 | $180.00 | $200.00 |
| 4 | Cleaning and sealing existing joints (438-7001) | LF | 124,250 | $2.45 | $2.00 | $2.50 | $3.25 | $2.90 | $3.25 | $4.50 |
| 5 | Mobilization (500-7001) | LS | 1 | $502,050 | $400,000 | $490,000 | $500,000 | $512,000 | $560,000 | $1,067,132 |
| 6 | Barricades, signs and traffic handling (502-7001) | MO | 17 | $12,250 | $44,000 | $18,250 | $31,500 | $6,000.00 | $42,000 | $15,700 |
| 7 | Portable changeable message sign (503-7002) | EACH | 4 | $8,880.00 | $4,500.00 | $35,000 | $7,500.00 | $9,000.00 | $24,900 | $2,000.00 |
| 8 | TMA (stationary) (505-7001) | DAY | 450 | $136.62 | $1.00 | $150.00 | $50.00 | $200.00 | $286.00 | $220.00 |
| 9 | TMA (mobile operation) (505-7003) | DAY | 30 | $371.17 | $1.00 | $400.00 | $500.00 | $750.00 | $1,000.00 | $1,300.00 |
| 10 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,040 | $5.50 | $1.00 | $5.25 | $10.00 | $6.00 | $12.00 | $8.00 |
| 11 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,040 | $1.80 | $0.25 | $0.94 | $3.00 | $1.00 | $0.50 | $5.00 |
| 12 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 1,000 | $75.00 | $80.00 | $95.00 | $21.00 | $80.00 | $99.00 | $145.00 |
| 13 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 60 | $100.00 | $90.00 | $110.00 | $84.00 | $85.00 | $100.00 | $56.00 |
| 14 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 7,000 | $25.00 | $13.00 | $15.00 | $13.65 | $15.00 | $10.00 | $195.00 |
| 15 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 850 | $30.00 | $20.00 | $8.50 | $27.30 | $18.00 | $13.25 | $70.00 |
| 16 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 1,000 | $28.00 | $20.00 | $15.00 | $26.25 | $24.00 | $13.25 | $106.00 |
| 17 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 60 | $31.00 | $20.00 | $25.00 | $52.50 | $24.00 | $18.00 | $61.00 |
| 18 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 8,200 | $1.94 | $0.10 | $2.50 | $5.25 | $2.00 | $1.00 | $3.50 |
| 19 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,150 | $2.25 | $0.10 | $2.50 | $5.25 | $2.00 | $1.00 | $3.50 |
| 20 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,750 | $0.88 | $0.93 | $1.00 | $0.95 | $0.87 | $0.87 | $1.00 |
| 21 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 550 | $3.00 | $3.75 | $3.95 | $2.07 | $3.50 | $1.90 | $2.15 |
| 22 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,425 | $6.82 | $6.75 | $7.10 | $7.90 | $6.77 | $7.25 | $8.50 |
| 23 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 22 | $142.41 | $130.00 | $136.50 | $185.30 | $175.00 | $170.00 | $15.00 |
| 24 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 13 | $292.00 | $185.00 | $194.50 | $354.25 | $300.00 | $325.00 | $20.00 |
| 25 | Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051) | EACH | 3 | $300.00 | $190.00 | $199.50 | $479.60 | $300.00 | $440.00 | $12.00 |
| 26 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 29 | $155.52 | $156.00 | $164.50 | $218.00 | $200.00 | $200.00 | $16.00 |
| 27 | Pavement sler 6" (666-7347) | LF | 79,100 | $0.14 | $0.17 | $0.20 | $0.22 | $0.20 | $0.20 | $0.22 |
| 28 | Pavement sler 8" (666-7348) | LF | 5,750 | $0.18 | $0.26 | $0.30 | $0.25 | $0.30 | $0.23 | $0.26 |
| 29 | Pavement sler 12" (666-7350) | LF | 550 | $0.84 | $0.76 | $0.80 | $0.39 | $1.00 | $0.36 | $0.44 |
| 30 | Pavement sler 24" (666-7352) | LF | 1,425 | $1.00 | $1.35 | $1.40 | $0.77 | $2.00 | $0.71 | $0.88 |
| 31 | Pavement sler (arrow) (666-7353) | EACH | 22 | $9.85 | $26.00 | $27.50 | $14.17 | $50.00 | $13.00 | $12.00 |
| 32 | Pavement sler (word) (666-7354) | EACH | 29 | $10.65 | $31.00 | $32.50 | $14.17 | $50.00 | $13.00 | $250.00 |
| 33 | Pavement sler (double arrow) (666-7356) | EACH | 13 | $34.74 | $37.00 | $39.00 | $16.35 | $100.00 | $15.00 | $20.00 |
| 34 | Pavement sler (uturn arrow) (666-7358) | EACH | 3 | $49.87 | $38.00 | $40.00 | $16.35 | $100.00 | $15.00 | $0.80 |
| 35 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 34,525 | $0.91 | $0.69 | $0.75 | $0.76 | $0.67 | $0.70 | $0.65 |
| 36 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 23,275 | $0.70 | $0.62 | $0.65 | $0.62 | $0.56 | $0.57 | $0.65 |
| 37 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 21,325 | $0.72 | $0.62 | $0.65 | $0.62 | $0.56 | $0.57 | $0.65 |
| 38 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 135 | $4.44 | $4.05 | $4.25 | $4.36 | $5.00 | $4.00 | $4.60 |
| 39 | Eliminating existing PM & markers (6") (677-7002) | LF | 79,100 | $0.85 | $0.35 | $0.40 | $0.49 | $0.25 | $0.45 | $0.51 |
| 40 | Eliminating existing PM & markers (8") (677-7004) | LF | 5,750 | $1.55 | $0.69 | $0.75 | $0.65 | $0.25 | $0.60 | $0.70 |
| 41 | Eliminating existing PM & markers (12") (677-7006) | LF | 550 | $1.85 | $1.60 | $1.70 | $1.09 | $1.00 | $1.00 | $1.20 |
| 42 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,425 | $3.10 | $2.70 | $2.85 | $2.73 | $2.00 | $2.50 | $2.90 |
| 43 | Pavement surface preparation for marking (6") (678-7002) | LF | 79,100 | $0.14 | $0.02 | $0.02 | $0.05 | $0.05 | $0.05 | $0.06 |
| 44 | Pavement surface preparation for marking (8") (678-7004) | LF | 5,750 | $0.30 | $0.07 | $0.07 | $0.05 | $0.05 | $0.05 | $0.06 |
| 45 | Pavement surface preparation for marking (12") (678-7006) | LF | 550 | $0.55 | $0.27 | $0.30 | $0.05 | $0.50 | $0.05 | $0.06 |
| 46 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,425 | $1.11 | $0.48 | $0.50 | $0.23 | $1.00 | $0.21 | $0.25 |
| 47 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 22 | $15.96 | $11.50 | $12.05 | $10.90 | $15.00 | $10.00 | $200.00 |
| 48 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 13 | $22.65 | $16.00 | $16.80 | $10.90 | $17.00 | $10.00 | $380.00 |
| 49 | Pavement surface preparation for marking (uturn arr) (678-7012) | EACH | 3 | $38.00 | $16.00 | $16.80 | $10.90 | $25.00 | $10.00 | $525.00 |
| 50 | Pavement surface preparation for marking (word) (678-7016) | EACH | 29 | $18.61 | $13.50 | $14.00 | $10.90 | $22.00 | $10.00 | $11.25 |
| 51 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 135 | $0.30 | $0.66 | $0.70 | $0.55 | $2.00 | $0.50 | $0.56 |
| 52 | Fiber reinforced polymer patching materials (721-7001) | LB | 5,000 | $10.00 | $7.50 | $5.00 | $15.00 | $4.75 | $10.00 | $7.00 |
| 53 | Continuous grinding-concrete pavement (3017-7001) | SY | 113,400 | $5.75 | $3.10 | $4.80 | $3.40 | $5.00 | $4.85 | $5.00 |
| 54 | Continuous grooving-concrete pavement (3017-7005) | SY | 113,400 | $2.50 | $2.25 | $3.75 | $2.50 | $3.35 | $3.85 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.