TxDOT contract A00220226 bid tabulation

Surfacing/Roadway Restoration, SH 360 (Arkansas Ln to SH 180). Let by Texas DOT on September 3, 2026, Tarrant, Fort Worth District. 6 bids received; low bid $4,581,050 by Foutsco Paving Company, LLC, -12% against the engineer's estimate of $5,198,453.

Owner
Texas DOT
Letting
03 SEP 2026
Pay items
54
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Foutsco Paving Company, LLC$4,581,050Low-12%
2O. Trevino Construction, LLC$4,914,580+7.0%-5.0%
3Ed Bell Construction Company$5,075,030+11%-2.0%
4Silver Creek Construction, Inc.$5,120,757+12%-1.0%
5Select Maintenance, L.L.C.$5,772,348+26%+11%
6Emery Sapp & Son'S Inc.$7,727,534+69%+49%
TxDOT contract A00220226: bids by rank

Engineer's estimate: $5,198,453.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Foutsco Paving Company, LLC2. O. Trevino Construction, LLC3. Ed Bell Construction Company4. Silver Creek Construction, Inc.5. Select Maintenance, L.L.C.6. Emery Sapp & Son'S Inc.
1Lime (quicklime (dry)) (260-7002)TON120$360.00$250.00$330.00$365.00$375.00$320.00$385.00
2Lime TRT (existing material)(6") (260-7006)SY12,000$8.50$3.00$21.00$13.00$18.00$19.00$24.00
3Full - depth repair CRCP (8") (361-7049)SY12,000$200.00$175.00$157.00$185.00$197.54$180.00$200.00
4Cleaning and sealing existing joints (438-7001)LF124,250$2.45$2.00$2.50$3.25$2.90$3.25$4.50
5Mobilization (500-7001)LS1$502,050$400,000$490,000$500,000$512,000$560,000$1,067,132
6Barricades, signs and traffic handling (502-7001)MO17$12,250$44,000$18,250$31,500$6,000.00$42,000$15,700
7Portable changeable message sign (503-7002)EACH4$8,880.00$4,500.00$35,000$7,500.00$9,000.00$24,900$2,000.00
8TMA (stationary) (505-7001)DAY450$136.62$1.00$150.00$50.00$200.00$286.00$220.00
9TMA (mobile operation) (505-7003)DAY30$371.17$1.00$400.00$500.00$750.00$1,000.00$1,300.00
10Biodegradable erosion control logs (install) (12") (506-7044)LF1,040$5.50$1.00$5.25$10.00$6.00$12.00$8.00
11Biodegradable erosion control logs (remove) (506-7046)LF1,040$1.80$0.25$0.94$3.00$1.00$0.50$5.00
12Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF1,000$75.00$80.00$95.00$21.00$80.00$99.00$145.00
13Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF60$100.00$90.00$110.00$84.00$85.00$100.00$56.00
14Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF7,000$25.00$13.00$15.00$13.65$15.00$10.00$195.00
15Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF850$30.00$20.00$8.50$27.30$18.00$13.25$70.00
16Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF1,000$28.00$20.00$15.00$26.25$24.00$13.25$106.00
17Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF60$31.00$20.00$25.00$52.50$24.00$18.00$61.00
18Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH8,200$1.94$0.10$2.50$5.25$2.00$1.00$3.50
19Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,150$2.25$0.10$2.50$5.25$2.00$1.00$3.50
20Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF5,750$0.88$0.93$1.00$0.95$0.87$0.87$1.00
21Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF550$3.00$3.75$3.95$2.07$3.50$1.90$2.15
22Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,425$6.82$6.75$7.10$7.90$6.77$7.25$8.50
23Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH22$142.41$130.00$136.50$185.30$175.00$170.00$15.00
24Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045)EACH13$292.00$185.00$194.50$354.25$300.00$325.00$20.00
25Reflectorized pavement marking type I(W)(uturn arrow)(100MIL) (666-7051)EACH3$300.00$190.00$199.50$479.60$300.00$440.00$12.00
26Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH29$155.52$156.00$164.50$218.00$200.00$200.00$16.00
27Pavement sler 6" (666-7347)LF79,100$0.14$0.17$0.20$0.22$0.20$0.20$0.22
28Pavement sler 8" (666-7348)LF5,750$0.18$0.26$0.30$0.25$0.30$0.23$0.26
29Pavement sler 12" (666-7350)LF550$0.84$0.76$0.80$0.39$1.00$0.36$0.44
30Pavement sler 24" (666-7352)LF1,425$1.00$1.35$1.40$0.77$2.00$0.71$0.88
31Pavement sler (arrow) (666-7353)EACH22$9.85$26.00$27.50$14.17$50.00$13.00$12.00
32Pavement sler (word) (666-7354)EACH29$10.65$31.00$32.50$14.17$50.00$13.00$250.00
33Pavement sler (double arrow) (666-7356)EACH13$34.74$37.00$39.00$16.35$100.00$15.00$20.00
34Pavement sler (uturn arrow) (666-7358)EACH3$49.87$38.00$40.00$16.35$100.00$15.00$0.80
35Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF34,525$0.91$0.69$0.75$0.76$0.67$0.70$0.65
36Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF23,275$0.70$0.62$0.65$0.62$0.56$0.57$0.65
37Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF21,325$0.72$0.62$0.65$0.62$0.56$0.57$0.65
38Reflectorized pavement marker type II-C-R (672-7006)EACH135$4.44$4.05$4.25$4.36$5.00$4.00$4.60
39Eliminating existing PM & markers (6") (677-7002)LF79,100$0.85$0.35$0.40$0.49$0.25$0.45$0.51
40Eliminating existing PM & markers (8") (677-7004)LF5,750$1.55$0.69$0.75$0.65$0.25$0.60$0.70
41Eliminating existing PM & markers (12") (677-7006)LF550$1.85$1.60$1.70$1.09$1.00$1.00$1.20
42Eliminating existing PM & markers (24") (677-7008)LF1,425$3.10$2.70$2.85$2.73$2.00$2.50$2.90
43Pavement surface preparation for marking (6") (678-7002)LF79,100$0.14$0.02$0.02$0.05$0.05$0.05$0.06
44Pavement surface preparation for marking (8") (678-7004)LF5,750$0.30$0.07$0.07$0.05$0.05$0.05$0.06
45Pavement surface preparation for marking (12") (678-7006)LF550$0.55$0.27$0.30$0.05$0.50$0.05$0.06
46Pavement surface preparation for marking (24") (678-7008)LF1,425$1.11$0.48$0.50$0.23$1.00$0.21$0.25
47Pavement surface preparation for marking (arrow) (678-7009)EACH22$15.96$11.50$12.05$10.90$15.00$10.00$200.00
48Pavement surface preparation for marking (double arrow) (678-7010)EACH13$22.65$16.00$16.80$10.90$17.00$10.00$380.00
49Pavement surface preparation for marking (uturn arr) (678-7012)EACH3$38.00$16.00$16.80$10.90$25.00$10.00$525.00
50Pavement surface preparation for marking (word) (678-7016)EACH29$18.61$13.50$14.00$10.90$22.00$10.00$11.25
51Pavement surface preparation for marking (RPM) (678-7033)EACH135$0.30$0.66$0.70$0.55$2.00$0.50$0.56
52Fiber reinforced polymer patching materials (721-7001)LB5,000$10.00$7.50$5.00$15.00$4.75$10.00$7.00
53Continuous grinding-concrete pavement (3017-7001)SY113,400$5.75$3.10$4.80$3.40$5.00$4.85$5.00
54Continuous grooving-concrete pavement (3017-7005)SY113,400$2.50$2.25$3.75$2.50$3.35$3.85$4.00
TxDOT contract A00220226: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy