TxDOT letting results, July 21, 2022
5 contracts let by Texas DOT on July 21, 2022, $1,667,750 in low bids, a median of 4 bidders per contract. On the 5 with an engineer's estimate, the low bid came in under it 0 times; median low bid +30% against the estimate.
- Owner
- Texas DOT
- Contracts
- 5
- Low bids, total
- $1,667,750
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07221511 | IH0035 Aggregate from VARIOUS LOCATIONS THROUGHT to COMAL MAINTENANCE SECTIONS | San Antonio District | 3 | Colorado Materials, LTD. | $365,000 | $397,778 | +9.0% | +46% | TxDOT |
| 07221512 | IH0010 Aggregate from VARIOUS LOCATIONS THROUGHOUT to KERR AREA OFFICE | San Antonio District | 4 | Vulcan Construction Materials, LLC | $356,801 | $433,602 | +22% | +30% | TxDOT |
| 07221513 | IH0035 Aggregate from VARIOUS LOCATIONS THROUGHOUT to HONDO AREA OFFICE | San Antonio District | 4 | Vulcan Construction Materials, LLC | $339,965 | $432,381 | +27% | +33% | TxDOT |
| 07221514 | IH0035 Hot mix from VARIOUS LOCATIONS THROUGHOUT to HONDO AO | San Antonio District | 3 | Texas Materials Group, Inc. | $324,150 | $353,645 | +9.0% | +14% | TxDOT |
| 07221510 | IH0035 Hot-mix cold-laid from VARIOUS LOCATIONS THROUGHOUT to SAN ANTONIO DISTRICT | San Antonio District | 6 | Vulcan Construction Materials, LLC | $281,834 | $315,400 | +12% | +3.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way