VDOT contract C0000128013N01 bid tabulation
2026 plant mix - primary. Let by Virginia DOT on February 4, 2026, Fairfax, Northern Virginia. 5 bids received; low bid $3,418,409 by EUROVIA ATLANTIC COAST LLC dba VIRGINIA.
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 24
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | EUROVIA ATLANTIC COAST LLC dba VIRGINIA | $3,418,409 | Low |
| 2 | Superior Paving Corporation | $3,446,777 | +1.0% |
| 3 | Julius Branscome, Inc. | $3,687,409 | +8.0% |
| 4 | Allan Myers Va, Inc. | $3,831,777 | +12% |
| 5 | Chemung Contracting Corporation | $4,014,415 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. EUROVIA ATLANTIC COAST LLC dba VIRGINIA | 2. Superior Paving Corporation | 3. Julius Branscome, Inc. | 4. Allan Myers Va, Inc. | 5. Chemung Contracting Corporation |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Inlet protection type B (303SD20-0031) | EACH | 42 | $66.00 | $1.04 | $0.01 | $0.01 | $0.01 |
| 0001-0020 | Tack coat (310SD20-0001) | GAL | 22,975 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0001-0030 | Asph. conc. TY. SM-12.5E maint (315SD20-0036) | TON | 26,560.66 | $97.50 | $105.50 | $102.00 | $128.55 | $127.50 |
| 0001-0040 | Asph. conc. BMD P+VO SM- 9.5D (315SP20-0049) | TON | 1,186.70 | $97.00 | $103.00 | $115.00 | $105.00 | $119.00 |
| 0001-0050 | Surface preparation and restoration type II (323SD20-0041) | TON | 139 | $155.00 | $140.00 | $97.00 | $190.00 | $200.00 |
| 0001-0060 | Flagger service (512SD20-0027) | HR | 829 | $35.00 | $16.00 | $35.00 | $0.01 | $35.00 |
| 0001-0070 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 183,576 | $0.01 | $0.15 | $0.15 | $0.01 | $0.14 |
| 0001-0080 | Temp. PVMT MRKG TY. A, 8" (512SD20-0048) | LF | 1,448 | $0.01 | $0.22 | $0.21 | $0.21 | $0.21 |
| 0001-0090 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 918 | $0.01 | $2.60 | $2.55 | $2.50 | $2.50 |
| 0001-0100 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 4 | $54.75 | $56.87 | $55.85 | $54.75 | $54.75 |
| 0001-0110 | NS maintenance of traffic MOT (512SP20-0002) | LS | 1 | $110,000 | $63,978 | $75,000 | $9,520.60 | $95,000 |
| 0001-0120 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 12,908.07 | $1.95 | $0.20 | $3.50 | $0.05 | $0.05 |
| 0001-0130 | Flexible pavement planing above 2"-4" (515SD20-0014) | SY | 216,837.98 | $1.35 | $0.40 | $1.60 | $0.10 | $0.05 |
| 0001-0140 | 14/1 conductor cable enclosed (700SD20-0118) | LF | 2,985 | $1.00 | $1.04 | $1.28 | $1.00 | $1.00 |
| 0001-0150 | Conduit metal 1" (700SD20-0183) | LF | 25 | $5.00 | $5.19 | $5.10 | $5.00 | $5.00 |
| 0001-0160 | Loop saw cut 3/8" (703SD20-0042) | LF | 990 | $12.75 | $13.24 | $13.25 | $12.75 | $12.75 |
| 0001-0170 | Loop saw cut 5/8" (703SD20-0043) | LF | 225 | $35.00 | $36.35 | $36.25 | $35.00 | $35.00 |
| 0001-0180 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 91,788 | $1.10 | $1.47 | $1.45 | $1.10 | $1.42 |
| 0001-0190 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 6,471 | $1.70 | $2.35 | $2.31 | $1.70 | $2.26 |
| 0001-0200 | Type B class I PVMT line MRKG 12" (704SD20-0009) | LF | 1,700 | $2.50 | $3.42 | $3.36 | $2.47 | $3.29 |
| 0001-0210 | Type B class I PVMT line MRKG 24" (704SD20-0010) | LF | 2,119 | $12.50 | $17.12 | $16.81 | $12.39 | $16.48 |
| 0001-0220 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 1,423 | $40.75 | $56.63 | $55.34 | $40.64 | $54.52 |
| 0001-0230 | PVMT symb MRKG SGL turn arr. TY B CL I (704SD20-0047) | EACH | 16 | $192.25 | $272.14 | $267.25 | $192.06 | $262.01 |
| 0001-0240 | Symb MRKG lane reduction arr TY B CL I (704SD20-0059) | EACH | 3 | $905.50 | $1,316.79 | $1,293.12 | $905.49 | $1,267.79 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.