VDOT contract C000121648C501B bid tabulation
Safety improvements - interchange lighting. Let by Virginia DOT on June 24, 2026, Augusta, Staunton. 3 bids received; low bid $2,263,907 by Creative Design Concepts, Inc..
- Owner
- Virginia DOT
- Letting
- 24 JUN 2026
- Pay items
- 37
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Creative Design Concepts, Inc. | $2,263,907 | Low |
| 2 | Lumin8 Transportation Technologies, LLC | $2,761,113 | +22% |
| 3 | Richardson-Wayland-Ferreira, LLC | $2,895,386 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Creative Design Concepts, Inc. | 2. Lumin8 Transportation Technologies, LLC | 3. Richardson-Wayland-Ferreira, LLC |
|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $42,598 | $32,904 | $7,529.10 |
| 0001-0020 | Temp. silt fence type A (303SD20-0034) | LF | 2,500 | $15.00 | $7.20 | $4.28 |
| 0001-0030 | Rock excavation (303SX20-0005) | CY | 100 | $2,241.00 | $556.00 | $2,000.00 |
| 0001-0040 | Salvage EX. guardrail (505SD20-0001) | LF | 125 | $115.00 | $86.00 | $26.25 |
| 0001-0050 | Install salv. guardrail (505SD20-0004) | LF | 125 | $145.00 | $165.00 | $52.50 |
| 0001-0060 | NS modify exist. transformer connection (510SX20-0031) | EACH | 1 | $9,082.00 | $2,142.00 | $6,242.88 |
| 0001-0070 | NS install vdot furnished field ethernet switch (510SX20-0070) | EACH | 1 | $2,765.00 | $325.00 | $1,264.10 |
| 0001-0080 | NS install vdot furnished field router (510SX20-0070) | EACH | 1 | $2,980.00 | $650.00 | $1,264.10 |
| 0001-0090 | NS install vdot furnished inclement weather lighting programable logic controller (510SX20-0070) | EACH | 1 | $8,864.00 | $1,319.00 | $2,528.17 |
| 0001-0100 | NS install vdot furnished SFP module (510SX20-0070) | EACH | 2 | $2,248.00 | $56.00 | $1,264.09 |
| 0001-0110 | Maintenance of traffic lighting at exit 99 (512SP20-0002) | LS | 1 | $95,678 | $360,881 | $330,000 |
| 0001-0120 | Mobilization (513SD20-0001) | LS | 1 | $65,939 | $246,341 | $320,000 |
| 0001-0130 | Construction surveying constr. (517SD20-0001) | LS | 1 | $45,500 | $21,936 | $26,250 |
| 0001-0140 | NS asbestos removal management of naturally-ocurring asbestos (522SX20-0004) | LS | 1 | $185,980 | $209,763 | $516,414 |
| 0001-0150 | 1 conductor cable (700SD20-0140) | LF | 45 | $15.00 | $10.30 | $39.74 |
| 0001-0160 | 4 conductor cable (700SD20-0142) | LF | 8,745 | $8.00 | $4.40 | $4.98 |
| 0001-0170 | 6 conductor cable (700SD20-0143) | LF | 6,770 | $7.00 | $3.10 | $3.44 |
| 0001-0180 | 10 conductor cable (700SD20-0145) | LF | 3,985 | $5.00 | $1.50 | $3.23 |
| 0001-0190 | 8 conductor cable egc (700SD20-0148) | LF | 1,115 | $6.00 | $3.90 | $3.52 |
| 0001-0200 | Conc. found. LF-1, TY. A (700SD20-0149) | EACH | 35 | $5,580.00 | $4,000.00 | $10,009 |
| 0001-0210 | Lighting pole LP-2 type C (700SD20-0155) | EACH | 6 | $7,098.00 | $5,884.00 | $6,190.57 |
| 0001-0220 | Lighting pole LP-2 type D (700SD20-0156) | EACH | 3 | $7,455.00 | $6,314.00 | $6,507.89 |
| 0001-0230 | Electrical service work pad (700SD20-0174) | EACH | 1 | $2,852.00 | $812.00 | $1,602.38 |
| 0001-0240 | Junction box JB-S2 (700SD20-0178) | EACH | 38 | $2,788.00 | $1,424.00 | $4,083.54 |
| 0001-0250 | Elect. ser. GRD. electrode 10' (700SD20-0181) | EACH | 6 | $225.00 | $140.00 | $296.71 |
| 0001-0260 | Bored conduit 2" (700SD20-0191) | LF | 11,120 | $55.00 | $102.00 | $35.00 |
| 0001-0270 | Conduit PVC 2" (700SD20-0194) | LF | 670 | $20.00 | $11.20 | $5.58 |
| 0001-0280 | Conduit PVC 3" (700SD20-0195) | LF | 15 | $26.00 | $25.40 | $8.97 |
| 0001-0290 | Trench excavation eci-1 (700SD20-0197) | LF | 685 | $45.00 | $28.90 | $18.90 |
| 0001-0300 | Lighting pole LP-1 25' MNTG HT (700SD20-0217) | EACH | 26 | $6,990.00 | $4,830.00 | $6,088.64 |
| 0001-0310 | Luminaire arm 18' (700SD20-0225) | EACH | 26 | $2,432.00 | $2,550.00 | $4,150.10 |
| 0001-0320 | NS concrete foundation lighting control center foundation (700SX20-0023) | CY | 2 | $4,988.00 | $7,954.00 | $6,032.40 |
| 0001-0330 | NS luminaire type 4, 119 watt (705SX20-0001) | EACH | 36 | $1,188.00 | $1,092.00 | $1,831.14 |
| 0001-0340 | NS lighting control center (705SX20-0002) | EACH | 1 | $25,990 | $46,273 | $51,821 |
| 0001-0350 | Fiber optic cable 24 strand (808SD20-0001) | LF | 120 | $20.00 | $9.20 | $14.30 |
| 0001-0360 | Pre-terminated fiber patch panel (808SD20-0005) | EACH | 1 | $4,323.00 | $1,143.00 | $2,265.41 |
| 0001-0370 | Underground splice enclosure (808SD20-0006) | EACH | 1 | $4,242.00 | $1,959.00 | $3,853.31 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of June 24, 2026. Compiled by Mirage Metrics.