6 conductor cable, VDOT 700SD20-0143

Low bidders on VDOT contracts carried a median of $5.04 per LF for this item, over the 24 months to 28 OCT 2026, across 14 low bids. Half of all 37 bids fell between $3.20 and $7.00.

Owner
Virginia DOT
Item
700SD20-0143
Unit
LF
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 55060 on lettings from 23 APR 2002 to 15 DEC 2021 (342 bids); 700SD20-0143 on lettings from 22 OCT 2025 to 23 SEP 2026 (37 bids). They are combined here into one trend.

$5.04Low bidder's median, per LF
$5.00Median of all bids, per LF
14Contracts in the window

By year of letting

6 conductor cable, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200266$0.6515$1.00
200322$1.406$0.97
200477$1.0015$1.00
200544$1.7010$1.59
200655$1.7011$1.70
200755$1.1012$1.32
200865$1.3615$1.40
200922$3.726$2.59
201077$1.2021$1.28
201198$1.5925$1.75
201266$1.5618$1.56
20131313$1.8134$1.86
20141111$1.4933$1.70
201599$1.6523$2.00
201676$2.4815$2.00
201777$2.2720$1.73
201844$1.1012$1.21
201988$3.0021$3.13
202044$3.4710$2.67
202167$2.0017$2.50
202577$5.5015$5.23
202677$3.0022$4.30

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Staunton3$7.008$4.52
Hampton Roads3$5.504$5.62
6 conductor cable, VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
50 to 3753$7.06
500 to 1,4304$3.52
2,220 to 3,6363$5.50
6,770 to 34,7004$5.04
6 conductor cable, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
B & B Signal Co., L.L.C.1611 (69%)
Midasco Va LLC (Use N Va By: Midasco, LLC)1511 (73%)
A & M Concrete Corp.157 (47%)
The Brothers Signal Company97 (78%)
Fort Myer Construction Corporation166 (38%)
General Excavation, Inc.96 (67%)
6 conductor cable, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
23 SEP 2026C0000128686N01Culpeper500$4.11$4.113Richardson-Wayland-Ferreira, LLCVDOT
22 JUL 2026C0000120611C01Salem50$7.90$7.901Branch Civil, Inc.VDOT
22 JUL 2026C0000122147C01CRichmond22,020$2.78$5.134Richardson-Wayland-Ferreira, LLCVDOT
24 JUN 2026C000121648C501BStaunton6,770$7.00$3.443Creative Design Concepts, Inc.VDOT
27 MAY 2026C000113172C01DFredericksburg2,220$2.00$3.854Ardent Company, LLCVDOT
04 FEB 2026C0000127373N01Northern Virginia1,430$3.00$3.904Creative Design Concepts, Inc.VDOT
04 FEB 2026C0000127476C01Northern Virginia1,095$3.00$6.153Creative Design Concepts, Inc.VDOT
17 DEC 2025C0000118871C01BCulpeper375$7.00$7.003S. L. Williamson Company, IncorporatedVDOT
17 DEC 2025C000113634M01BHampton Roads34,700$4.84$4.841BRANSCOME OPERATING, LLC dba BRANSCOMEVDOT
19 NOV 2025C0000115128N01Staunton950$4.04$5.003Richardson-Wayland-Ferreira, LLCVDOT
19 NOV 2025C0000127310N01Staunton150$7.06$5.032Richardson-Wayland-Ferreira, LLCVDOT
22 OCT 2025C0000118376C01Hampton Roads3,636$5.75$6.882VSL Electrical, Signing, Lighting LLCVDOT
22 OCT 2025C000117033M01DHampton Roads2,705$5.50$5.501Joseph B. Fay Co.VDOT
22 OCT 2025C0000120443M01Richmond9,517$5.23$4.253Richardson-Wayland-Ferreira, LLCVDOT
15 DEC 2021C0000118581C01Richmond2,755$7.00$7.001Shirley Contracting Company, LLCVDOT
Latest VDOT contracts carrying 6 conductor cable

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.