VDOT contract C0000118871C01B bid tabulation
Smart scale - shared use path. Let by Virginia DOT on December 17, 2025, Albemarle, Culpeper. 3 bids received; low bid $1,910,504 by S. L. Williamson Company, Incorporated.
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 94
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | S. L. Williamson Company, Incorporated | $1,910,504 | Low |
| 2 | Arthur Construction Co., Inc. | $2,299,551 | +20% |
| 3 | Richardson-Wayland-Ferreira, LLC | $2,723,986 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. S. L. Williamson Company, Incorporated | 2. Arthur Construction Co., Inc. | 3. Richardson-Wayland-Ferreira, LLC |
|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $90,000 | $150,000 | $25,585 |
| 0001-0020 | NS pipe clean existing pipe (302SX20-0013) | LF | 2,846 | $12.00 | $5.00 | $76.75 |
| 0001-0030 | NS drainage clean existing inlet (302SX20-0022) | EACH | 12 | $1,500.00 | $1,500.00 | $1,918.86 |
| 0001-0040 | Regular excavation (303SD20-0001) | CY | 4,105 | $115.00 | $125.00 | $153.51 |
| 0001-0050 | Siltation control excavation (303SD20-0029) | CY | 236 | $1.00 | $25.00 | $153.51 |
| 0001-0060 | Inlet protection type B (303SD20-0031) | EACH | 14 | $300.00 | $350.00 | $191.89 |
| 0001-0070 | Temp. silt fence type A (303SD20-0034) | LF | 1,384 | $10.00 | $10.00 | $12.79 |
| 0001-0080 | Borrow excavation (305SD20-0001) | CY | 248 | $180.00 | $150.00 | $191.89 |
| 0001-0090 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 1,196 | $85.00 | $50.00 | $76.75 |
| 0001-0100 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 93 | $300.00 | $175.00 | $383.77 |
| 0001-0110 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 7 | $500.00 | $175.00 | $383.77 |
| 0001-0120 | Asphalt concrete TY. SM- 9.5A const (315SD20-0007) | TON | 316 | $220.00 | $250.00 | $383.77 |
| 0001-0130 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 108 | $300.00 | $175.00 | $383.77 |
| 0001-0140 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 520 | $2.00 | $5.00 | $6.40 |
| 0001-0150 | NS saw-cut hydr.cem.conc.pave. full depth (316SX20-0010) | LF | 2,440 | $2.00 | $5.00 | $6.40 |
| 0001-0160 | Curb, STD. CG-2 (502SD20-0011) | LF | 20 | $30.00 | $75.00 | $63.96 |
| 0001-0170 | Curb, radial CG-2 (502SD20-0012) | LF | 6 | $30.00 | $75.00 | $63.96 |
| 0001-0180 | Curb, STD. CG-3 (502SD20-0014) | LF | 514 | $30.00 | $100.00 | $63.96 |
| 0001-0190 | Curb, asphalt MC-3 (502SD20-0018) | LF | 28 | $385.00 | $100.00 | $63.96 |
| 0001-0200 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 473 | $45.00 | $125.00 | $83.16 |
| 0001-0210 | CG-12 detectable warning surface (504SD20-0002) | SY | 36 | $475.00 | $750.00 | $639.62 |
| 0001-0220 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 292 | $70.00 | $135.00 | $159.91 |
| 0001-0230 | High visibility fence, 4 feet (507SD20-0027) | LF | 2,370 | $11.00 | $8.00 | $19.19 |
| 0001-0240 | Demo. of pavement flexible (508SD20-0004) | SY | 367 | $40.00 | $45.00 | $44.78 |
| 0001-0250 | Temporary sign (512SD20-0014) | SF | 286 | $40.00 | $50.00 | $31.99 |
| 0001-0260 | Truck mounted attenuator (512SD20-0023) | HR | 1,628 | $10.00 | $5.00 | $76.75 |
| 0001-0270 | Group 2 channelizing devices (512SD20-0024) | DAY | 15,046 | $2.00 | $1.00 | $1.92 |
| 0001-0280 | Electronic arrow board (512SD20-0026) | HR | 1,628 | $10.00 | $25.00 | $19.19 |
| 0001-0290 | Flagger service (512SD20-0027) | HR | 232 | $70.00 | $30.00 | $51.17 |
| 0001-0300 | NS police patrol uniformed flaggers (512SX20-0040) | HR | 32 | $500.00 | $225.00 | $261.44 |
| 0001-0310 | Mobilization (513SD20-0001) | LS | 1 | $130,000 | $336,922 | $220,000 |
| 0001-0320 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 839 | $30.00 | $20.00 | $31.99 |
| 0001-0330 | Construction surveying constr. (517SD20-0001) | LS | 1 | $100,000 | $50,000 | $63,962 |
| 0001-0340 | Mailbox post, single (521SD20-0001) | EACH | 1 | $1,250.00 | $750.00 | $383.77 |
| 0001-0350 | Topsoil class A 2" (602SD20-0001) | ACRE | 1.35 | $82,000 | $45,000 | $38,377 |
| 0001-0360 | Temporary seed (603SD20-0002) | LB | 135 | $12.50 | $10.00 | $25.58 |
| 0001-0370 | Regular seed (603SD20-0003) | LB | 270 | $13.50 | $15.00 | $25.58 |
| 0001-0380 | Overseeding (603SD20-0004) | LB | 216 | $8.05 | $15.00 | $20.47 |
| 0001-0390 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 2,473 | $4.30 | $3.00 | $3.20 |
| 0001-0400 | Fertilizer nitrogen - N (603SD20-0014) | LB | 89 | $2.00 | $4.00 | $12.79 |
| 0001-0410 | Fertilizer phosphorous - P (603SD20-0015) | LB | 177 | $2.00 | $4.00 | $7.68 |
| 0001-0420 | Fertilizer potassium - K (603SD20-0016) | LB | 89 | $2.00 | $4.00 | $12.79 |
| 0001-0430 | Lime (603SD20-0017) | TON | 4.73 | $300.00 | $650.00 | $639.62 |
| 0001-0440 | NS landscape permanent vegetative cover (605SX20-0013) | LS | 1 | $30,000 | $25,000 | $25,585 |
| 0001-0450 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 2,473 | $4.50 | $9.00 | $10.23 |
| 0001-0460 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 1 | $775.00 | $250.00 | $492.09 |
| 0001-0470 | Remove existing 1 post sign panel (700SD20-0007) | EACH | 1 | $300.00 | $250.00 | $328.05 |
| 0001-0480 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 10 | $375.00 | $450.00 | $492.06 |
| 0001-0490 | Relocate EX. 2 post GRND mount SGN panel (700SD20-0013) | EACH | 2 | $525.00 | $500.00 | $656.10 |
| 0001-0500 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 75 | $50.00 | $30.00 | $38.38 |
| 0001-0510 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 96 | $45.00 | $30.00 | $44.78 |
| 0001-0520 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 13 | $80.00 | $40.00 | $40.94 |
| 0001-0530 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 9 | $1,200.00 | $650.00 | $575.66 |
| 0001-0540 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 8 | $1,300.00 | $750.00 | $831.51 |
| 0001-0550 | Pedestal pole PF-2, 10' (700SD20-0066) | EACH | 2 | $1,500.00 | $2,350.00 | $4,622.50 |
| 0001-0560 | Pedestal pole PF-2, 12' (700SD20-0067) | EACH | 1 | $1,600.00 | $2,350.00 | $6,436.55 |
| 0001-0570 | Conc. found. PF-8 (700SD20-0068) | CY | 15 | $2,200.00 | $5,400.00 | $6,035.56 |
| 0001-0580 | Conc. found. PF-2 (700SD20-0069) | EACH | 3 | $1,300.00 | $3,000.00 | $5,106.86 |
| 0001-0590 | Signal mast arm pole MP- 3, TY. B1 (700SD20-0091) | EACH | 2 | $25,750 | $37,800 | $33,765 |
| 0001-0600 | Mast arm 60' (700SD20-0101) | EACH | 1 | $12,650 | $23,500 | $16,668 |
| 0001-0610 | Mast arm 75', case 2 loading (700SD20-0105) | EACH | 1 | $19,200 | $37,800 | $23,475 |
| 0001-0620 | 14/2 conductor cable (700SD20-0110) | LF | 750 | $5.50 | $5.00 | $8.78 |
| 0001-0630 | 14/4 conductor cable (700SD20-0112) | LF | 750 | $6.00 | $5.00 | $13.29 |
| 0001-0640 | 14/7 conductor cable (700SD20-0114) | LF | 2,850 | $7.00 | $5.00 | $10.50 |
| 0001-0650 | 14/1 conductor cable enclosed (700SD20-0118) | LF | 500 | $6.75 | $4.00 | $22.86 |
| 0001-0660 | 14/2 conductor cable shielded (700SD20-0120) | LF | 625 | $7.00 | $4.00 | $10.12 |
| 0001-0670 | 6 conductor cable (700SD20-0143) | LF | 375 | $7.00 | $5.00 | $8.15 |
| 0001-0680 | Junction box JB-S1 (700SD20-0177) | EACH | 1 | $2,150.00 | $3,000.00 | $3,918.27 |
| 0001-0690 | Junction box JB-S2 (700SD20-0178) | EACH | 1 | $2,400.00 | $3,500.00 | $5,504.25 |
| 0001-0700 | Conduit metal 1-1/4" (700SD20-0185) | LF | 25 | $635.00 | $72.00 | $338.69 |
| 0001-0710 | Bored conduit 4" (700SD20-0193) | LF | 100 | $65.00 | $300.00 | $139.20 |
| 0001-0720 | Conduit PVC 3" (700SD20-0195) | LF | 175 | $9.00 | $45.00 | $10.68 |
| 0001-0730 | Trench excavation eci-1 (700SD20-0197) | LF | 175 | $10.00 | $55.00 | $48.93 |
| 0001-0740 | Test bore (700SD20-0199) | EACH | 2 | $6,750.00 | $15,000 | $4,477.34 |
| 0001-0750 | NS traffic signalization accessible pedestrian pushbutton station (700SX20-0010) | EACH | 2 | $1,560.00 | $9,000.00 | $3,983.80 |
| 0001-0760 | Sign panel (701SD20-0001) | SF | 112.13 | $50.00 | $100.00 | $97.70 |
| 0001-0770 | Traf. sig. head sect. 12" HVS backplate (703SD20-0007) | EACH | 36 | $475.00 | $900.00 | $833.32 |
| 0001-0780 | Evp detection system 1- way (703SD20-0020) | EACH | 1 | $6,200.00 | $15,000 | $3,402.70 |
| 0001-0790 | Evp detector cable (703SD20-0024) | LF | 450 | $5.00 | $4.50 | $18.88 |
| 0001-0800 | Hanger assembly SM-3, one way (703SD20-0034) | EACH | 11 | $650.00 | $650.00 | $1,651.29 |
| 0001-0810 | Hanger assembly SMB-3, one way (703SD20-0039) | EACH | 1 | $500.00 | $425.00 | $649.19 |
| 0001-0820 | Loop saw cut 3/8" (703SD20-0042) | LF | 25 | $40.00 | $60.00 | $94.27 |
| 0001-0830 | Loop saw cut 5/8" (703SD20-0043) | LF | 150 | $48.00 | $90.00 | $112.42 |
| 0001-0840 | Remove existing pole (703SD20-0044) | EACH | 4 | $2,400.00 | $2,000.00 | $3,026.12 |
| 0001-0850 | Remove existing foundation (703SD20-0045) | EACH | 4 | $1,900.00 | $2,400.00 | $6,279.06 |
| 0001-0860 | Remove existing signal head (703SD20-0046) | EACH | 10 | $215.00 | $305.00 | $1,049.69 |
| 0001-0870 | Pedestrian signal head SP-8 (703SD20-0060) | EACH | 2 | $1,100.00 | $1,500.00 | $1,455.63 |
| 0001-0880 | NS hanger assembly SMD- 1 (703SX20-0004) | EACH | 3 | $615.00 | $550.00 | $988.21 |
| 0001-0890 | NS hanger assembly SMD- 2 (703SX20-0004) | EACH | 3 | $525.00 | $600.00 | $1,018.25 |
| 0001-0900 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 166 | $18.00 | $3.25 | $22.95 |
| 0001-0910 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 232 | $18.25 | $6.25 | $23.23 |
| 0001-0920 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 141 | $27.00 | $50.00 | $33.26 |
| 0001-0930 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 1 | $750.00 | $450.00 | $947.14 |
| 0001-0940 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 1 | $880.00 | $650.00 | $1,122.57 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.