NS hanger assembly SMD- 1, VDOT 703SX20-0004
Low bidders on VDOT contracts carried a median of $566.06 per EACH for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 13 bids fell between $525.00 and $1,000.00.
- Owner
- Virginia DOT
- Item
- 703SX20-0004
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT prints this item as “NS HANGER ASSEMBLY SMD- 1”.
VDOT has bid this work under more than one code: 51840 on lettings from 24 SEP 2002 to 27 OCT 2021 (746 bids); 703SX20-0004 on lettings from 19 NOV 2025 to 04 FEB 2026 (13 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 7 | 30 | $147.00 | 83 | $162.00 |
| 2004 | 6 | 27 | $124.00 | 54 | $165.00 |
| 2005 | 3 | 4 | $192.50 | 6 | $225.00 |
| 2006 | 3 | 8 | $222.00 | 19 | $154.81 |
| 2007 | 9 | 28 | $205.00 | 59 | $210.00 |
| 2008 | 3 | 13 | $205.00 | 38 | $215.00 |
| 2010 | 7 | 16 | $215.00 | 44 | $211.50 |
| 2011 | 10 | 27 | $204.75 | 75 | $204.75 |
| 2012 | 5 | 11 | $190.00 | 33 | $203.02 |
| 2013 | 3 | 13 | $205.61 | 24 | $208.81 |
| 2014 | 4 | 9 | $300.00 | 26 | $215.00 |
| 2015 | 4 | 10 | $300.00 | 24 | $337.50 |
| 2016 | 12 | 24 | $287.60 | 61 | $335.00 |
| 2017 | 9 | 15 | $275.00 | 39 | $355.00 |
| 2018 | 4 | 7 | $373.75 | 20 | $395.00 |
| 2019 | 6 | 14 | $327.50 | 40 | $356.27 |
| 2020 | 6 | 20 | $259.60 | 52 | $280.00 |
| 2021 | 4 | 10 | $282.50 | 26 | $389.19 |
| 2025 | 2 | 2 | $590.53 | 5 | $566.06 |
| 2026 | 1 | 1 | $77.00 | 8 | $850.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 91 | $200.00 | 239 | $224.00 |
| Fredericksburg | 45 | $248.53 | 123 | $250.00 |
| Hampton Roads | 33 | $200.00 | 94 | $209.50 |
| Staunton | 31 | $260.00 | 84 | $291.50 |
| Salem | 41 | $193.00 | 78 | $189.50 |
| Richmond | 26 | $319.65 | 62 | $350.65 |
| Culpeper | 18 | $240.00 | 43 | $260.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 5 | 72 | $267.80 |
| 5 to 15 | 72 | $230.03 |
| 15 to 50 | 72 | $206.50 |
| 50 to 900 | 73 | $200.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| B & B Signal Co., L.L.C. | 75 | 43 (57%) |
| Richardson-Wayland Electrical Co. LLC | 108 | 33 (31%) |
| The Brothers Signal Company | 39 | 26 (67%) |
| Elite Contracting Group, Inc. | 31 | 16 (52%) |
| General Excavation, Inc. | 21 | 12 (57%) |
| Phillip C. Clarke Electrical Contractor, Inc. | 39 | 11 (28%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 FEB 2026 | C0000123319B54 | Bristol | 2 | $77.00 | $850.00 | 8 | Freyssinet, Inc. | VDOT |
| 17 DEC 2025 | C0000118871C01B | Culpeper | 3 | $615.00 | $615.00 | 3 | S. L. Williamson Company, Incorporated | VDOT |
| 19 NOV 2025 | C0000127310N01 | Staunton | 2 | $566.06 | $545.53 | 2 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 8 | $375.00 | $485.74 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 20 | $275.00 | $321.47 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 8 | $190.00 | $214.66 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 1 | $190.00 | $294.39 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 4 | $290.00 | $458.84 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 1 | $250.00 | $293.01 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 8 | $250.00 | $294.14 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 25 AUG 2021 | C0000111047T01 | Staunton | 10 | $300.00 | $300.00 | 1 | Ces Consulting, LLC | VDOT |
| 23 JUN 2021 | C0000110793C01 | Bristol | 2 | $1,000.00 | $1,000.00 | 1 | Ramirez Contracting, L.L.C. | VDOT |
| 24 FEB 2021 | C0000107036M01 | Richmond | 4 | $403.39 | $430.00 | 3 | M & F Concrete, Inc. | VDOT |
| 16 DEC 2020 | C0000117400N01 | Hampton Roads | 5 | $227.00 | $255.00 | 3 | Bryant-Ritter Electric Corporation | VDOT |
| 16 DEC 2020 | C0000117400N01 | Hampton Roads | 2 | $415.00 | $440.00 | 3 | Bryant-Ritter Electric Corporation | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.