VDOT contract C0000123319B54 bid tabulation
Sgr - bridge superstructure replacement. Let by Virginia DOT on February 4, 2026, Wise, Bristol. 8 bids received; low bid $2,763,781 by Freyssinet, Inc..
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 66
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Freyssinet, Inc. | $2,763,781 | Low |
| 2 | Jones Road & Bridge, Inc. | $2,782,743 | +1.0% |
| 3 | King General Contractors, Inc. | $3,083,009 | +12% |
| 4 | Patrick Construction, Inc. | $3,110,163 | +13% |
| 5 | Elk Knob, Inc. | $3,240,823 | +17% |
| 6 | Glass Machinery and Excavation, Inc. | $3,795,993 | +37% |
| 7 | Caton Construction Group, Inc. | $3,842,122 | +39% |
| 8 | Brayman Construction Corporation | $4,855,159 | +76% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Freyssinet, Inc. | 2. Jones Road & Bridge, Inc. | 3. King General Contractors, Inc. | 4. Patrick Construction, Inc. | 5. Elk Knob, Inc. | 6. Glass Machinery and Excavation, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001-0010 | 18" pipe (302SD20-0028) | LF | 175 | $47.00 | $80.00 | $35.30 | $40.00 | $30.00 | $81.31 |
| 0001-0020 | 18" end section ES-1 or 2 (302SD20-0200) | EACH | 4 | $1,140.00 | $1,000.00 | $528.00 | $550.00 | $300.00 | $1,805.06 |
| 0001-0030 | Check dam rock TY. II (303SD20-0023) | EACH | 7 | $200.00 | $500.00 | $622.20 | $900.00 | $400.00 | $350.00 |
| 0001-0040 | Check dam sediment retention roll 20" (303SD20-0025) | EACH | 11 | $750.00 | $500.00 | $492.90 | $800.00 | $300.00 | $444.17 |
| 0001-0050 | Siltation control excavation (303SD20-0029) | CY | 77 | $20.00 | $0.03 | $9.10 | $1.00 | $1.00 | $20.00 |
| 0001-0060 | Temp. silt fence type A (303SD20-0034) | LF | 416 | $5.00 | $7.00 | $8.10 | $10.00 | $5.00 | $7.00 |
| 0001-0070 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 17 | $62.00 | $75.95 | $130.30 | $75.00 | $100.00 | $79.72 |
| 0001-0080 | Asphalt concrete TY. SM- 12.5A const (315SD20-0001) | TON | 181 | $460.00 | $360.10 | $294.10 | $350.00 | $345.09 | $241.69 |
| 0001-0090 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 9 | $825.00 | $646.27 | $286.20 | $620.00 | $619.34 | $236.35 |
| 0001-0100 | Structure excavation const. (401SD20-0001) | CY | 46 | $16.00 | $60.00 | $181.60 | $100.00 | $100.00 | $100.00 |
| 0001-0110 | Select backfill abutment zone (401SD20-0002) | TON | 60 | $63.00 | $65.64 | $79.70 | $50.00 | $40.00 | $74.52 |
| 0001-0120 | Geocomposite wall drain (401SD20-0004) | SY | 12 | $42.00 | $55.36 | $166.10 | $85.00 | $40.00 | $60.00 |
| 0001-0130 | Pipe underdrain 6" const. (401SD20-0005) | LF | 74 | $11.00 | $55.00 | $49.20 | $30.00 | $15.00 | $40.00 |
| 0001-0140 | Concrete class A3, substruct. const. (404SD20-0011) | CY | 3.20 | $1,350.00 | $3,750.20 | $3,481.50 | $6,000.00 | $9,850.00 | $2,773.78 |
| 0001-0150 | Shear keys (404SP20-0002) | CF | 49 | $515.00 | $675.00 | $456.40 | $325.00 | $425.00 | $800.00 |
| 0001-0160 | VA adjacent member conn. block-outs (404SP20-0003) | CF | 281 | $455.00 | $550.00 | $456.40 | $325.00 | $425.00 | $600.00 |
| 0001-0170 | Prest.conc.slab 3'X21"X(+35'-40') (405SD20-0012) | EACH | 6 | $60,600 | $29,534 | $40,958 | $28,000 | $38,250 | $52,194 |
| 0001-0180 | Prest.conc.slab 3'X21"X(+40'-45') (405SD20-0014) | EACH | 4 | $44,400 | $29,534 | $40,958 | $28,000 | $38,250 | $52,108 |
| 0001-0190 | Prest. conc. slab 4' X 21" X(+35'-40') (405SD20-0025) | EACH | 18 | $34,700 | $34,635 | $45,611 | $34,000 | $39,500 | $55,770 |
| 0001-0200 | Prest. conc. slab 4' X 21" X(+40'-45') (405SD20-0027) | EACH | 12 | $36,100 | $34,635 | $45,611 | $34,000 | $39,500 | $55,770 |
| 0001-0210 | CR reinf. steel CL. I SPR. struct. const. (406SD20-0003) | LB | 1,960 | $4.50 | $6.00 | $6.70 | $6.00 | $5.00 | $4.00 |
| 0001-0220 | CR reinf. steel CL. I substruct. const. (406SD20-0008) | LB | 810 | $4.50 | $6.00 | $6.20 | $6.00 | $5.00 | $4.00 |
| 0001-0230 | Railing kansas corral 32" W/out curb const. (410SD20-0010) | LF | 405 | $150.00 | $550.00 | $341.50 | $325.00 | $394.00 | $306.49 |
| 0001-0240 | Embedded galvanic anodes (412SD20-0017) | EACH | 272 | $42.00 | $60.00 | $23.30 | $65.00 | $40.00 | $40.00 |
| 0001-0250 | Reinf. STL. splicer #6 bar (412SD20-0022) | EACH | 14 | $85.00 | $150.00 | $55.60 | $125.00 | $125.00 | $70.00 |
| 0001-0260 | Concrete substruct. surface repair (412SD20-0061) | SY | 34 | $1,150.00 | $2,800.00 | $1,792.20 | $4,000.00 | $3,000.00 | $1,400.00 |
| 0001-0270 | NS rem. port.of EX.STR. VA. STR. no. 6005 (413SX20-0005) | LS | 1 | $152,000 | $112,000 | $25,333 | $500,000 | $395,000 | $366,182 |
| 0001-0280 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 10 | $195.00 | $100.00 | $211.90 | $75.00 | $75.00 | $61.23 |
| 0001-0290 | Waterproofing – epoxy resin type EP-3B/EP-3T (416SD20-0003) | SY | 342 | $155.00 | $60.00 | $83.50 | $100.00 | $60.00 | $70.00 |
| 0001-0300 | NS nbis access, under bridge STR. no. 6005 (430SX20-0001) | DAY | 2 | $1,190.00 | $1,300.00 | $4,480.50 | $2,000.00 | $100.00 | $2,500.00 |
| 0001-0310 | Guardrail GR-MGS1 (505SD20-0011) | LF | 50 | $92.00 | $60.00 | $66.60 | $70.00 | $57.50 | $63.25 |
| 0001-0320 | Radial guardrail GR-MGS1 (505SD20-0014) | LF | 50 | $105.00 | $66.00 | $72.70 | $75.00 | $63.25 | $69.58 |
| 0001-0330 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 2 | $8,420.00 | $5,400.00 | $5,449.20 | $6,500.00 | $5,175.00 | $5,692.50 |
| 0001-0340 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 2 | $3,830.00 | $2,400.00 | $2,421.90 | $3,500.00 | $2,300.00 | $2,530.00 |
| 0001-0350 | Guardrail ter.site preparation (505SD20-0039) | EACH | 2 | $2,300.00 | $1,440.00 | $1,453.10 | $1,500.00 | $1,500.00 | $1,518.00 |
| 0001-0360 | Fixed object attach. GR- foa-5 (505SD20-0055) | EACH | 4 | $9,190.00 | $5,400.00 | $5,449.20 | $6,500.00 | $5,175.00 | $5,692.50 |
| 0001-0370 | Remove existing guardrail (505SD20-0073) | LF | 220 | $13.00 | $12.00 | $11.40 | $10.00 | $5.00 | $12.65 |
| 0001-0380 | Traffic barrier service MB-11A (512SD20-0003) | LF | 410 | $165.00 | $80.00 | $62.10 | $75.00 | $48.00 | $84.90 |
| 0001-0390 | Temporary sign (512SD20-0014) | SF | 450 | $31.00 | $28.80 | $24.20 | $55.00 | $40.00 | $35.42 |
| 0001-0400 | Truck mounted attenuator (512SD20-0023) | HR | 40 | $690.00 | $18.58 | $74.50 | $15.00 | $50.00 | $20.00 |
| 0001-0410 | Group 2 channelizing devices (512SD20-0024) | DAY | 600 | $0.40 | $1.30 | $0.30 | $2.00 | $4.00 | $1.33 |
| 0001-0420 | Port.changeable mess. sign (512SD20-0025) | HR | 1,008 | $54.00 | $6.64 | $6.10 | $8.00 | $15.00 | $7.10 |
| 0001-0430 | Electronic arrow board (512SD20-0026) | HR | 40 | $38.00 | $5.31 | $22.04 | $10.00 | $10.00 | $5.83 |
| 0001-0440 | Flagger service (512SD20-0027) | HR | 250 | $84.00 | $35.00 | $32.00 | $40.00 | $30.00 | $50.00 |
| 0001-0450 | Warning light TY. B (512SD20-0029) | DAY | 960 | $1.50 | $0.62 | $1.21 | $2.50 | $4.00 | $2.52 |
| 0001-0460 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 300 | $130.00 | $65.00 | $75.00 | $70.00 | $40.00 | $63.60 |
| 0001-0470 | Portable temporary rumble strip array (512SP20-0001) | DAY | 40 | $92.00 | $200.00 | $72.66 | $400.00 | $250.00 | $219.88 |
| 0001-0480 | NS temporary traffic control signal STR. no. 6005 (512SX20-0025) | LS | 1 | $76,600 | $260,000 | $285,114 | $300,000 | $275,000 | $291,870 |
| 0001-0490 | Mobilization (513SD20-0001) | LS | 1 | $40,800 | $130,000 | $234,000 | $150,000 | $192,250 | $173,150 |
| 0001-0500 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 284 | $110.00 | $85.54 | $14.53 | $85.00 | $81.97 | $12.00 |
| 0001-0510 | Construction surveying constr. (517SD20-0001) | LS | 1 | $14,100 | $25,000 | $30,274 | $9,500.00 | $15,180 | $12,000 |
| 0001-0520 | Rolled erosion CTRL product EC-2 type 4 (606SD20-0004) | SY | 377 | $7.50 | $7.03 | $4.61 | $6.00 | $5.00 | $8.00 |
| 0001-0530 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 5 | $190.00 | $450.00 | $348.50 | $500.00 | $200.00 | $474.38 |
| 0001-0540 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 4 | $355.00 | $210.00 | $528.50 | $2,000.00 | $500.00 | $221.38 |
| 0001-0550 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 28 | $47.00 | $23.86 | $42.18 | $40.00 | $25.00 | $25.15 |
| 0001-0560 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 5 | $1,310.00 | $832.80 | $1,032.45 | $1,000.00 | $800.00 | $877.91 |
| 0001-0570 | Sign panel (701SD20-0001) | SF | 36 | $74.00 | $33.60 | $58.17 | $40.00 | $56.00 | $35.42 |
| 0001-0580 | NS hanger assembly SMD- 1 (703SX20-0004) | EACH | 2 | $77.00 | $2,728.43 | $700.00 | $1,000.00 | $100.00 | $506.00 |
| 0001-0590 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 75 | $36.00 | $27.89 | $46.31 | $26.00 | $35.00 | $37.95 |
| 0001-0600 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 13 | $670.00 | $523.15 | $527.92 | $460.00 | $172.50 | $189.75 |
| 0001-0610 | PVMT MSG. mark. R/R crossing TY. B, CL. II (704SD20-0042) | EACH | 1 | $2,140.00 | $1,677.50 | $1,692.80 | $1,000.00 | $2,070.00 | $2,277.00 |
| 0001-0620 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 1 | $830.00 | $649.45 | $655.38 | $700.00 | $977.50 | $1,075.25 |
| 0001-0630 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 1 | $1,030.00 | $809.11 | $1,627.82 | $1,000.00 | $1,092.50 | $1,201.75 |
| 0001-0640 | Removal of SRPM (704SP20-0001) | EACH | 8 | $670.00 | $525.00 | $529.79 | $600.00 | $250.00 | $25.30 |
| 0001-0650 | NS pavement marking type D class III, 6" (704SX20-0001) | LF | 2,800 | $5.00 | $4.10 | $4.63 | $5.00 | $4.60 | $5.06 |
| 0001-0660 | NS pavement marking type E, 6" (704SX20-0001) | LF | 4,500 | $6.00 | $4.82 | $5.21 | $5.00 | $5.75 | $6.33 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.