Structure excavation const., VDOT 401SD20-0001
Low bidders on VDOT contracts carried a median of $93.14 per CY for this item, over the 24 months to 28 OCT 2026, across 16 low bids. Half of all 87 bids fell between $77.47 and $165.00.
- Owner
- Virginia DOT
- Item
- 401SD20-0001
- Unit
- CY
- Data through
- 28 OCT 2026
VDOT has bid this work under more than one code: 64011 on lettings from 26 FEB 2002 to 15 DEC 2021 (829 bids); 401SD20-0001 on lettings from 22 OCT 2025 to 22 JUL 2026 (87 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 20 | 20 | $25.00 | 60 | $26.00 |
| 2003 | 10 | 10 | $25.00 | 29 | $30.00 |
| 2004 | 15 | 15 | $40.00 | 40 | $39.00 |
| 2005 | 10 | 10 | $27.50 | 28 | $35.00 |
| 2006 | 13 | 13 | $25.00 | 39 | $30.00 |
| 2007 | 8 | 8 | $30.00 | 23 | $45.00 |
| 2008 | 2 | 2 | $62.50 | 6 | $62.50 |
| 2009 | 10 | 10 | $26.00 | 30 | $30.00 |
| 2010 | 10 | 10 | $24.12 | 29 | $30.00 |
| 2011 | 11 | 11 | $34.00 | 33 | $37.00 |
| 2012 | 10 | 10 | $38.25 | 30 | $40.00 |
| 2013 | 23 | 23 | $36.00 | 69 | $32.00 |
| 2014 | 20 | 20 | $31.50 | 54 | $40.00 |
| 2015 | 22 | 24 | $37.50 | 62 | $49.50 |
| 2016 | 28 | 27 | $33.00 | 78 | $35.00 |
| 2017 | 11 | 11 | $49.00 | 33 | $45.00 |
| 2018 | 10 | 10 | $25.00 | 30 | $34.00 |
| 2019 | 24 | 24 | $45.00 | 65 | $46.00 |
| 2020 | 16 | 16 | $47.50 | 46 | $50.00 |
| 2021 | 15 | 15 | $45.80 | 45 | $50.00 |
| 2025 | 2 | 2 | $80.00 | 7 | $110.00 |
| 2026 | 14 | 14 | $93.14 | 80 | $100.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Culpeper | 3 | $107.95 | 20 | $141.00 |
| Bristol | 4 | $62.50 | 19 | $87.43 |
| Staunton | 3 | $84.78 | 17 | $84.78 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 19 to 34 | 4 | $196.00 |
| 46 to 304 | 4 | $96.39 |
| 320 to 792 | 4 | $51.00 |
| 796 to 2,508 | 4 | $88.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Crossroads Bridge Inc | 38 | 20 (53%) |
| Patrick Construction, Inc. | 33 | 20 (61%) |
| DLB, Inc. | 31 | 19 (61%) |
| Elk Knob, Inc. | 45 | 16 (36%) |
| Abernathy Construction Corporation | 33 | 13 (39%) |
| Ken Construction Co., Inc. | 41 | 12 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000118431B20 | Culpeper | 792 | $52.00 | $101.47 | 6 | Freyssinet, Inc. | VDOT |
| 22 JUL 2026 | C0000121138B52 | Bristol | 796 | $75.00 | $80.00 | 5 | Elk Knob, Inc. | VDOT |
| 24 JUN 2026 | C0000112964B03 | Staunton | 182 | $108.00 | $165.00 | 5 | Hammond-Mitchell, Inc. | VDOT |
| 24 JUN 2026 | C0000117111B62 | Bristol | 570 | $76.68 | $100.00 | 3 | King General Contractors, Inc. | VDOT |
| 24 JUN 2026 | C0000121544B01 | Richmond | 34 | $362.28 | $222.00 | 5 | Freyssinet, Inc. | VDOT |
| 27 MAY 2026 | C0000121826C01 | Northern Virginia | 154 | $250.00 | $188.32 | 4 | Fort Myer Construction Corporation | VDOT |
| 27 MAY 2026 | C0000118430B39 | Culpeper | 921 | $107.95 | $132.50 | 8 | Burleigh Construction Co., Inc. | VDOT |
| 22 APR 2026 | C0000117024B05 | Staunton | 304 | $84.78 | $84.78 | 7 | Fairfield-Echols, LLC | VDOT |
| 22 APR 2026 | C0000124564B64 | Culpeper | 19 | $142.00 | $342.50 | 6 | WG Construction Co., Inc. | VDOT |
| 25 MAR 2026 | C0000121531B68 | Hampton Roads | 560 | $41.00 | $100.00 | 7 | Crofton Construction Services, | VDOT |
| 25 FEB 2026 | C0000117021B19 | Staunton | 1,063 | $73.00 | $71.64 | 5 | Freyssinet, Inc. | VDOT |
| 04 FEB 2026 | C0000126720N01 | Fredericksburg | 20 | $250.00 | $250.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 04 FEB 2026 | C0000123319B54 | Bristol | 46 | $16.00 | $100.00 | 8 | Freyssinet, Inc. | VDOT |
| 04 FEB 2026 | C0000113851B01 | Fredericksburg | 2,508 | $101.50 | $81.98 | 8 | WG Construction Co., Inc. | VDOT |
| 19 NOV 2025 | C0000116160B01 | Bristol | 320 | $50.00 | $50.00 | 3 | Caton Construction Group, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.