Asph. conc. TY. BM-25.0 T maint, VDOT 321SD20-0003
Low bidders on VDOT contracts carried a median of $125.28 per TON for this item, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 23 bids fell between $109.31 and $150.00.
- Owner
- Virginia DOT
- Item
- 321SD20-0003
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “ASPH. CONC. TY. BM-25.0 T MAINT”.
VDOT has bid this work under more than one code: 16395 on lettings from 25 FEB 2009 to 28 APR 2021 (512 bids); 321SD20-0003 on lettings from 17 DEC 2025 to 22 JUL 2026 (23 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2009 | 21 | 21 | $66.00 | 46 | $68.00 |
| 2010 | 16 | 16 | $71.50 | 29 | $73.00 |
| 2011 | 22 | 22 | $79.00 | 34 | $84.94 |
| 2012 | 18 | 18 | $93.33 | 35 | $91.65 |
| 2013 | 10 | 10 | $79.63 | 21 | $83.26 |
| 2014 | 23 | 23 | $80.00 | 57 | $86.00 |
| 2015 | 19 | 19 | $84.00 | 49 | $95.00 |
| 2016 | 24 | 24 | $86.50 | 57 | $90.00 |
| 2017 | 14 | 14 | $87.60 | 34 | $85.00 |
| 2018 | 25 | 25 | $94.00 | 59 | $95.00 |
| 2019 | 15 | 15 | $90.00 | 39 | $95.00 |
| 2020 | 15 | 17 | $90.00 | 32 | $91.91 |
| 2021 | 7 | 7 | $167.00 | 19 | $150.00 |
| 2025 | 2 | 2 | $108.31 | 6 | $109.31 |
| 2026 | 6 | 6 | $135.78 | 17 | $127.05 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Superior Paving Corporation | 57 | 27 (47%) |
| Adams Construction Company | 49 | 23 (47%) |
| Virginia Paving Co., Div. of the Lane Constr. Corp. | 42 | 19 (45%) |
| Colony Construction, Inc. | 24 | 14 (58%) |
| W-L Construction & Paving, Inc. | 20 | 13 (65%) |
| S. L. Williamson Company, Incorporated | 28 | 12 (43%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | CM327PMG128967 | Lynchburg | 795.05 | $150.00 | $173.37 | 3 | Adams Construction Company | VDOT |
| 25 MAR 2026 | C0000126012N01 | Lynchburg | 12,810 | $125.57 | $137.78 | 2 | White'S Construction Company, Inc. | VDOT |
| 04 FEB 2026 | CM726PMH127455 | Culpeper | 3,390.20 | $90.00 | $99.50 | 4 | EUROVIA ATLANTIC COAST LLC dba VIRGINIA | VDOT |
| 04 FEB 2026 | C0000126013N01 | Lynchburg | 27,850 | $125.00 | $124.03 | 4 | S. L. Williamson Company, Incorporated | VDOT |
| 14 JAN 2026 | CM326PMC127078 | Lynchburg | 118.74 | $200.00 | $202.23 | 3 | Colony Construction, Inc. | VDOT |
| 14 JAN 2026 | CM826PMF127548 | Staunton | 1,936 | $146.00 | $146.00 | 1 | Adams Construction Company | VDOT |
| 17 DEC 2025 | CM326PMD127084 | Lynchburg | 1,383.60 | $110.61 | $127.81 | 2 | Adams Construction Company | VDOT |
| 17 DEC 2025 | C0000128018P01 | Northern Virginia | 1,013.76 | $106.00 | $107.00 | 4 | Arthur Construction Co., Inc. | VDOT |
| 28 APR 2021 | C000110888N01B | Salem | 2,336 | $167.00 | $187.12 | 2 | Boxley Materials Company | VDOT |
| 24 MAR 2021 | C00000118232N01 | Northern Virginia | 100 | $213.25 | $280.00 | 3 | Fort Myer Construction Corporation | VDOT |
| 24 MAR 2021 | C0000112292N01 | Bristol | 12,046 | $169.53 | $157.26 | 2 | W-L Construction & Paving, Inc. | VDOT |
| 24 MAR 2021 | C0000116749N01 | Lynchburg | 226 | $215.00 | $172.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 24 FEB 2021 | C0000117831N01 | Northern Virginia | 286.53 | $67.00 | $115.00 | 3 | Julius Branscome, Inc. | VDOT |
| 20 JAN 2021 | C0000114092N01 | Lynchburg | 13,299 | $75.00 | $85.75 | 3 | Colony Construction, Inc. | VDOT |
| 20 JAN 2021 | C0000117828N01 | Northern Virginia | 1,165.12 | $105.00 | $95.75 | 3 | Superior Paving Corporation | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.