VDOT contract C0000126013N01 bid tabulation
Shoulder improvements. Let by Virginia DOT on February 4, 2026, Nelson, Lynchburg. 4 bids received; low bid $7,674,027 by S. L. Williamson Company, Incorporated.
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 37
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | S. L. Williamson Company, Incorporated | $7,674,027 | Low |
| 2 | Adams Construction Company | $7,865,180 | +2.0% |
| 3 | Superior Paving Corporation | $7,990,534 | +4.0% |
| 4 | White'S Construction Company, Inc. | $8,884,180 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. S. L. Williamson Company, Incorporated | 2. Adams Construction Company | 3. Superior Paving Corporation | 4. White'S Construction Company, Inc. |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Utility test pit unpaved (303SX20-0012) | EACH | 500 | $125.00 | $125.00 | $140.00 | $137.50 |
| 0001-0020 | Agr. base mat. TY.I or II no. 21A or 21B (305SP20-0003) | TON | 14,000 | $62.00 | $57.07 | $60.70 | $45.37 |
| 0001-0030 | Machining shoulders (305SP20-0005) | LF | 205,850 | $0.15 | $1.06 | $1.15 | $1.00 |
| 0001-0040 | Manual shoulders restoration (305SP20-0006) | LF | 5,700 | $0.50 | $6.00 | $6.25 | $5.00 |
| 0001-0050 | Liquid asphalt (fog sealing) (312SD20-0004) | GAL | 1,980 | $1.00 | $9.31 | $8.00 | $12.00 |
| 0001-0060 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 6,780 | $112.85 | $142.21 | $127.00 | $130.50 |
| 0001-0070 | Liquid asphalt coating (rumble strip) (315SD20-0016) | SY | 17,900 | $0.60 | $0.56 | $0.60 | $0.62 |
| 0001-0080 | Rumble strip sinusoidal asphalt (315SD20-0052) | LF | 171,700 | $0.26 | $0.21 | $0.25 | $0.23 |
| 0001-0090 | Asph. conc. TY. BM-25.0 T maint (321SD20-0003) | TON | 27,850 | $125.00 | $127.05 | $116.75 | $123.06 |
| 0001-0100 | Remove EX. guardrail terminal (505SD20-0009) | EACH | 58 | $800.00 | $750.00 | $800.00 | $825.00 |
| 0001-0110 | Guardrail GR-MGS1 (505SD20-0011) | LF | 6,800 | $41.00 | $40.00 | $42.50 | $44.00 |
| 0001-0120 | Guardrail GR-MGS1, 9' post (505SD20-0013) | LF | 5,700 | $51.00 | $50.00 | $53.00 | $55.00 |
| 0001-0130 | Radial guardrail GR-MGS1 (505SD20-0014) | LF | 688 | $46.00 | $45.00 | $47.50 | $49.50 |
| 0001-0140 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 68 | $5,250.00 | $5,000.00 | $5,500.00 | $5,500.00 |
| 0001-0150 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 38 | $2,150.00 | $2,000.00 | $2,200.00 | $2,200.00 |
| 0001-0160 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 62 | $2,150.00 | $2,000.00 | $2,200.00 | $2,200.00 |
| 0001-0170 | Guardrail terminal GR-6 NCHRP 350 (505SD20-0027) | LF | 63 | $205.00 | $200.00 | $215.00 | $13,860 |
| 0001-0180 | Guardrail GR-2 (505SD20-0030) | LF | 1,363 | $41.00 | $40.00 | $45.00 | $44.00 |
| 0001-0190 | Alt.breakaway cable term. GR-9 (505SD20-0038) | EACH | 1 | $5,250.00 | $5,000.00 | $5,275.00 | $5,500.00 |
| 0001-0200 | Guardrail GR-10 (505SD20-0040) | LF | 1,500 | $46.00 | $45.00 | $47.50 | $49.50 |
| 0001-0210 | Remove existing guardrail (505SD20-0073) | LF | 16,250 | $10.00 | $10.00 | $10.50 | $11.00 |
| 0001-0220 | NS hand dig guardrail post locations specified by engineer (505SX20-0001) | EACH | 500 | $150.00 | $125.00 | $132.00 | $137.50 |
| 0001-0230 | NS guardrail guardrail terminal site preparation (6-FT moderate) (505SX20-0058) | EACH | 110 | $1,100.00 | $1,000.00 | $1,050.00 | $1,000.00 |
| 0001-0240 | Temporary sign (512SD20-0014) | SF | 545 | $15.00 | $19.51 | $40.00 | $23.10 |
| 0001-0250 | Truck mounted attenuator (512SD20-0023) | HR | 2,752 | $5.00 | $8.05 | $30.00 | $20.00 |
| 0001-0260 | Group 2 channelizing devices (512SD20-0024) | DAY | 14,000 | $0.75 | $0.01 | $1.65 | $1.50 |
| 0001-0270 | Port.changeable mess. sign (512SD20-0025) | HR | 2,690 | $5.00 | $4.39 | $15.00 | $20.00 |
| 0001-0280 | Electronic arrow board (512SD20-0026) | HR | 2,752 | $5.00 | $5.36 | $20.00 | $10.00 |
| 0001-0290 | Flagger service (512SD20-0027) | HR | 500 | $12.50 | $40.70 | $25.00 | $50.00 |
| 0001-0300 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 171,700 | $0.18 | $0.16 | $0.17 | $0.18 |
| 0001-0310 | Mobilization (513SD20-0001) | LS | 1 | $405,001 | $233,270 | $373,500 | $481,065 |
| 0001-0320 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 15 | $550.00 | $528.78 | $575.00 | $412.50 |
| 0001-0330 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 20 | $390.00 | $381.17 | $400.00 | $192.50 |
| 0001-0340 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 175 | $37.00 | $35.95 | $40.00 | $24.20 |
| 0001-0350 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 15 | $1,850.00 | $1,835.17 | $2,000.00 | $1,093.40 |
| 0001-0360 | Sign panel (701SD20-0001) | SF | 50 | $48.00 | $45.60 | $48.50 | $30.80 |
| 0001-0370 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 171,700 | $0.76 | $0.85 | $0.90 | $0.94 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.