VDOT contract C0000128018P01 bid tabulation
2026 plant mix - secondary. Let by Virginia DOT on December 17, 2025, Loudoun, Northern Virginia. 4 bids received; low bid $2,389,551 by Arthur Construction Co., Inc..
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 30
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Arthur Construction Co., Inc. | $2,389,551 | Low |
| 2 | Superior Paving Corporation | $2,596,631 | +9.0% |
| 3 | Allan Myers Va, Inc. | $2,610,777 | +9.0% |
| 4 | EUROVIA ATLANTIC COAST LLC dba VIRGINIA | $3,022,812 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Arthur Construction Co., Inc. | 2. Superior Paving Corporation | 3. Allan Myers Va, Inc. | 4. EUROVIA ATLANTIC COAST LLC dba VIRGINIA |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Inlet protection type B (303SD20-0031) | EACH | 13 | $25.00 | $50.00 | $0.01 | $100.00 |
| 0001-0020 | Agr. base mat. TY.I or II no. 21A or 21B (305SP20-0003) | TON | 173 | $45.00 | $150.00 | $90.00 | $70.00 |
| 0001-0030 | Tack coat (310SD20-0001) | GAL | 14,175 | $0.01 | $3.25 | $2.31 | $0.01 |
| 0001-0040 | Asph. conc. TY. IM-19.0A maint (315SD20-0040) | TON | 1,232.08 | $87.00 | $88.00 | $82.25 | $107.38 |
| 0001-0050 | Pavement shoulder wedge prep. const (315SP20-0006) | LF | 4,850 | $1.00 | $0.01 | $0.01 | $0.01 |
| 0001-0060 | Asph. conc. BMD P+VO SM- 9.5A (315SP20-0048) | TON | 13,899.44 | $105.25 | $97.00 | $127.39 | $117.50 |
| 0001-0070 | Asph. conc. BMD P+VO SM- 9.5D (315SP20-0049) | TON | 3,857.52 | $105.25 | $89.00 | $85.67 | $112.00 |
| 0001-0080 | Asph. conc. TY. BM-25.0 T maint (321SD20-0003) | TON | 1,013.76 | $106.00 | $108.00 | $105.50 | $132.00 |
| 0001-0090 | Surface preparation and restoration type II (323SD20-0041) | TON | 592 | $85.00 | $125.00 | $65.00 | $185.00 |
| 0001-0100 | Flagger service (512SD20-0027) | HR | 1,338 | $25.00 | $35.00 | $56.00 | $37.00 |
| 0001-0110 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 41,009 | $0.05 | $0.50 | $0.32 | $0.35 |
| 0001-0120 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 377 | $4.00 | $0.01 | $4.00 | $4.40 |
| 0001-0130 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 5 | $90.00 | $0.01 | $80.00 | $87.50 |
| 0001-0140 | NS maintenance of traffic MOT (512SP20-0002) | LS | 1 | $62,246 | $61,750 | $9,951.81 | $128,500 |
| 0001-0150 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 178,909.51 | $0.01 | $1.50 | $0.01 | $1.30 |
| 0001-0160 | Flexible pavement planing above 2"-4" (515SD20-0014) | SY | 10,090.67 | $2.70 | $2.25 | $0.25 | $2.00 |
| 0001-0170 | 14/1 conductor cable enclosed (700SD20-0118) | LF | 2,388 | $3.15 | $2.99 | $2.99 | $3.25 |
| 0001-0180 | Conduit metal 1" (700SD20-0183) | LF | 20 | $5.25 | $5.00 | $5.00 | $5.50 |
| 0001-0190 | Loop saw cut 3/8" (703SD20-0042) | LF | 528 | $15.75 | $15.00 | $15.00 | $16.00 |
| 0001-0200 | Loop saw cut 5/8" (703SD20-0043) | LF | 120 | $57.75 | $55.00 | $55.00 | $60.00 |
| 0001-0210 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 41,009 | $1.25 | $1.55 | $1.22 | $1.35 |
| 0001-0220 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 4,930 | $2.20 | $1.60 | $2.13 | $2.35 |
| 0001-0230 | Type B class I PVMT line MRKG 24" (704SD20-0010) | LF | 1,285 | $12.25 | $13.33 | $12.00 | $13.15 |
| 0001-0240 | PVMT symb MRKG SGL turn arr. TY B CL I (704SD20-0047) | EACH | 15 | $200.00 | $178.97 | $192.00 | $210.00 |
| 0001-0250 | MRKG DBL turn arr. thru/LT or RT TY A (704SD20-0049) | EACH | 1 | $125.00 | $0.01 | $120.00 | $130.00 |
| 0001-0260 | DBL turn arr.thru/LT or RT TY B, CL I (704SD20-0050) | EACH | 1 | $325.00 | $239.25 | $292.00 | $320.00 |
| 0001-0270 | Symb MRKG bicycle thru arrow TY B CL I (704SD20-0095) | EACH | 15 | $370.00 | $106.77 | $355.00 | $390.00 |
| 0001-0280 | Symb MRKG helmeted bicyclist TY B CL I (704SD20-0101) | EACH | 15 | $200.00 | $294.82 | $192.00 | $210.00 |
| 0001-0290 | PVMT MSG. mark. “only” TY B, CL. I, 8’ (704SD20-0107) | EACH | 2 | $525.00 | $422.20 | $500.00 | $550.00 |
| 0002-0300 | NS select material alternate shoulder materials (305SX20-0006) | TON | 1 | $50.00 | $150.00 | $89.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.