Asph. conc. TY. IM-19.0A maint, VDOT 315SD20-0040

Low bidders on VDOT contracts carried a median of $87.12 per TON for this item, over the 24 months to 28 OCT 2026, across 10 low bids. Half of all 45 bids fell between $86.50 and $100.00.

Owner
Virginia DOT
Item
315SD20-0040
Unit
TON
Data through
28 OCT 2026

VDOT prints this item as “ASPH. CONC. TY. IM-19.0A MAINT”.

VDOT has bid this work under more than one code: 16365 on lettings from 26 FEB 2002 to 25 AUG 2021 (751 bids); 315SD20-0040 on lettings from 19 NOV 2025 to 22 JUL 2026 (45 bids). They are combined here into one trend.

$87.12Low bidder's median, per TON
$90.00Median of all bids, per TON
10Contracts in the window

By year of letting

Asph. conc. TY. IM-19.0A maint, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20021111$32.1528$32.20
20031313$37.2532$37.05
200422$32.506$34.03
200599$42.0017$45.00
200666$48.0015$53.55
200777$55.0018$55.50
200888$66.3816$63.15
20091010$64.5025$68.00
20101111$100.0020$66.44
20111818$72.6030$72.05
20122525$75.7849$79.15
20131515$88.0030$92.12
20141010$78.6221$78.65
20151818$70.8049$75.00
20162828$63.6273$69.00
20171919$62.0051$66.00
20182626$67.5073$73.00
20192222$68.4665$71.83
20201616$65.8848$69.00
20212830$67.0085$70.00
202566$85.9227$88.50
202644$98.5018$97.62

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northern Virginia6$89.6231$93.00
Culpeper3$81.2511$86.50
Asph. conc. TY. IM-19.0A maint, VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

Who is lowest on this line

BidderLines bidLowest on the line
Superior Paving Corporation10946 (42%)
Virginia Paving Co., Div. of the Lane Constr. Corp.7939 (49%)
Eurovia Atlantic Coast LLC DBA Virginia Paving Company3820 (53%)
Julius Branscome, Inc.5417 (31%)
Allan Myers Va, Inc.3615 (42%)
Francis O. Day Co., Inc.4214 (33%)
Asph. conc. TY. IM-19.0A maint, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000128831P01Northern Virginia5,806.83$99.00$105.005Arthur Construction Co., Inc.VDOT
22 JUL 2026C0000128797P01Northern Virginia858.80$98.00$98.005Arthur Construction Co., Inc.VDOT
04 FEB 2026CM726PME127461Culpeper25,628.18$79.00$83.504Superior Paving CorporationVDOT
14 JAN 2026CM726PMD127450Culpeper1,862.08$100.00$93.534Chemung Contracting CorporationVDOT
17 DEC 2025CM726PMC127463Culpeper13,004.24$81.25$86.503Superior Paving CorporationVDOT
17 DEC 2025C0000128018P01Northern Virginia1,232.08$87.00$87.504Arthur Construction Co., Inc.VDOT
17 DEC 2025C0000127755P01Northern Virginia1,519.98$92.00$92.005Superior Paving CorporationVDOT
19 NOV 2025CM626PME127628Fredericksburg3,717.12$84.84$85.003Allan Myers Va, Inc.VDOT
19 NOV 2025C0000128015P01Northern Virginia3,527.93$84.00$90.506Julius Branscome, Inc.VDOT
19 NOV 2025C0000127753P01Northern Virginia2,123.95$87.25$90.006Julius Branscome, Inc.VDOT
25 AUG 2021C0000000118723Northern Virginia7,958.01$75.00$71.003Allan Myers Va, Inc.VDOT
23 JUN 2021C0000118719N01Northern Virginia444.36$75.00$73.003Arthur Construction Co., Inc.VDOT
28 APR 2021C0000109474C01Fredericksburg3,144$70.00$77.003Allan Myers Va, Inc.VDOT
28 APR 2021C0000109474C01Fredericksburg507$70.00$77.003Allan Myers Va, Inc.VDOT
28 APR 2021C0000109474C01Fredericksburg355$77.00$77.003Allan Myers Va, Inc.VDOT
Latest VDOT contracts carrying Asph. conc. TY. IM-19.0A maint

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy