VDOT contract C0000112964B03 bid tabulation
Sgr - bridge replacement. Let by Virginia DOT on June 24, 2026, Lexington, Staunton. 5 bids received; low bid $1,597,243 by Hammond-Mitchell, Inc..
- Owner
- Virginia DOT
- Letting
- 24 JUN 2026
- Pay items
- 81
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hammond-Mitchell, Inc. | $1,597,243 | Low |
| 2 | Stonewall Bridge, Inc. | $1,956,626 | +23% |
| 3 | Haymes Brothers, Inc. | $1,990,848 | +25% |
| 4 | Allegheny Construction Company, Inc. | $2,047,890 | +28% |
| 5 | Fairfield-Echols, LLC | $2,097,189 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hammond-Mitchell, Inc. | 2. Stonewall Bridge, Inc. | 3. Haymes Brothers, Inc. | 4. Allegheny Construction Company, Inc. | 5. Fairfield-Echols, LLC |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Endwall EW-12 (302SD20-0013) | EACH | 1 | $1,620.00 | $2,000.00 | $3,000.00 | $1,900.00 | $1,021.65 |
| 0001-0020 | 12" pipe (302SD20-0018) | LF | 36 | $222.00 | $225.00 | $225.00 | $260.00 | $314.63 |
| 0001-0030 | 15" pipe (302SD20-0023) | LF | 25 | $210.00 | $250.00 | $250.00 | $325.00 | $376.22 |
| 0001-0040 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 1 | $1,200.00 | $1,500.00 | $1,000.00 | $900.00 | $2,205.00 |
| 0001-0050 | Drop inlet DI-2A (302SD20-0239) | EACH | 2 | $8,580.00 | $10,000 | $6,500.00 | $10,000 | $5,181.75 |
| 0001-0060 | Manhole MH-1 or 2 (302SD20-0662) | LF | 11.60 | $1,200.00 | $1,500.00 | $2,800.00 | $1,600.00 | $1,389.90 |
| 0001-0070 | Frame & cover MH-1 (302SD20-0663) | EACH | 2 | $1,080.00 | $1,250.00 | $1,400.00 | $1,780.00 | $913.50 |
| 0001-0080 | Grading (303SD20-0004) | LS | 1 | $75,600 | $20,000 | $100,000 | $75,000 | $53,493 |
| 0001-0090 | Borrow excavation (303SD20-0007) | CY | 160 | $110.40 | $100.00 | $90.00 | $25.00 | $184.71 |
| 0001-0100 | Dewatering basin EC-8 (303SD20-0028) | EACH | 2 | $6,420.00 | $2,500.00 | $600.00 | $2,400.00 | $4,900.58 |
| 0001-0110 | Siltation control excavation (303SD20-0029) | CY | 52 | $1.00 | $1.00 | $25.00 | $20.00 | $20.60 |
| 0001-0120 | Inlet protection type B (303SD20-0031) | EACH | 4 | $336.00 | $500.00 | $450.00 | $800.00 | $213.15 |
| 0001-0130 | Temp. silt fence type B (303SD20-0033) | LF | 38 | $30.00 | $10.00 | $12.00 | $12.00 | $40.07 |
| 0001-0140 | Temp. silt fence type A (303SD20-0034) | LF | 150 | $22.80 | $8.00 | $12.00 | $8.00 | $13.26 |
| 0001-0150 | No. 10 screenings (303SP20-0002) | TON | 4 | $162.00 | $250.00 | $75.00 | $500.00 | $495.13 |
| 0001-0160 | Geotextile subgrade stab. (305SD20-0009) | SY | 392 | $15.00 | $5.00 | $9.50 | $10.00 | $7.09 |
| 0001-0170 | Aggr.base mat.TY. I no.21A or 21B (305SD20-0012) | TON | 174 | $71.00 | $80.00 | $72.00 | $80.00 | $71.76 |
| 0001-0180 | Select material type ogb (309SP20-0001) | TON | 174 | $85.00 | $80.00 | $72.00 | $85.00 | $80.58 |
| 0001-0190 | Asphalt concrete TY. SM- 9.5A const (315SD20-0007) | TON | 32 | $228.00 | $600.00 | $660.00 | $500.00 | $226.85 |
| 0001-0200 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 88 | $216.00 | $550.00 | $365.00 | $425.00 | $208.58 |
| 0001-0210 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 63 | $13.00 | $12.00 | $38.00 | $35.00 | $14.13 |
| 0001-0220 | Structure excavation const. (401SD20-0001) | CY | 182 | $108.00 | $80.00 | $165.00 | $165.00 | $276.83 |
| 0001-0230 | Select backfill abutment zone (401SD20-0002) | TON | 322 | $72.00 | $80.00 | $115.00 | $88.00 | $199.20 |
| 0001-0240 | Geocomposite wall drain (401SD20-0004) | SY | 49 | $47.00 | $100.00 | $18.00 | $50.00 | $62.55 |
| 0001-0250 | Pipe underdrain 6" const. (401SD20-0005) | LF | 110 | $12.60 | $15.00 | $25.00 | $45.00 | $102.00 |
| 0001-0260 | Cofferdam (401SD20-0007) | EACH | 3 | $19,104 | $5,000.00 | $22,000 | $25,000 | $21,532 |
| 0001-0270 | Conc. CL. A4 ltweight, SPR. struct. const. (404SD20-0006) | CY | 32.50 | $2,880.00 | $2,800.00 | $4,000.00 | $3,750.00 | $4,225.38 |
| 0001-0280 | Bridge deck grooving const. (404SD20-0009) | SY | 118 | $74.00 | $65.00 | $65.00 | $80.00 | $47.60 |
| 0001-0290 | Cover depth survey const. (404SD20-0010) | SY | 147 | $25.00 | $35.00 | $28.00 | $30.00 | $23.00 |
| 0001-0300 | Concrete class A3, substruct. const. (404SD20-0011) | CY | 58.20 | $1,860.00 | $1,800.00 | $3,250.00 | $3,500.00 | $2,453.82 |
| 0001-0310 | Shear keys (404SP20-0002) | CF | 13 | $614.00 | $700.00 | $850.00 | $615.00 | $404.99 |
| 0001-0320 | VA adjacent member conn. block-outs (404SP20-0003) | CF | 64 | $546.00 | $700.00 | $425.00 | $500.00 | $642.53 |
| 0001-0330 | NS concrete class A3 unreinforced (404SX20-0001) | CY | 16 | $762.00 | $1,500.00 | $600.00 | $1,650.00 | $802.49 |
| 0001-0340 | Prest.conc.slab 3'X18"X(+40'-45') (405SD20-0013) | EACH | 2 | $32,400 | $50,000 | $48,000 | $30,000 | $39,889 |
| 0001-0350 | Prest. conc. slab 4' X 18" X(+40'-45') (405SD20-0026) | EACH | 7 | $32,400 | $50,000 | $34,000 | $30,000 | $39,889 |
| 0001-0360 | CR reinf. steel CL. I SPR. struct. const. (406SD20-0003) | LB | 2,430 | $3.90 | $6.00 | $4.85 | $9.00 | $13.55 |
| 0001-0370 | Reinforcing steel substruct. const. (406SD20-0006) | LB | 1,900 | $2.52 | $5.00 | $2.50 | $14.00 | $8.12 |
| 0001-0380 | CR reinf. steel CL. I substruct. const. (406SD20-0008) | LB | 2,270 | $3.90 | $6.00 | $3.75 | $9.00 | $15.62 |
| 0001-0390 | Railing CPSR 2 rail const. (410SD20-0011) | LF | 83 | $1,126.00 | $495.00 | $515.00 | $1,000.00 | $1,377.05 |
| 0001-0400 | NS bridge incidentals temporary shoring (410SX20-0014) | LS | 1 | $73,200 | $320,000 | $275,000 | $155,000 | $108,377 |
| 0001-0410 | NS env.& worker protect. environmental protection structure no. 8002 (413SX20-0003) | LS | 1 | $7,200.00 | $20,000 | $8,400.00 | $7,000.00 | $6,300.00 |
| 0001-0420 | NS material disposal structure no. 8002 (413SX20-0004) | LS | 1 | $3,600.00 | $20,000 | $4,000.00 | $25,000 | $3,150.00 |
| 0001-0430 | NS rem. port.of EX.STR. structure no. 8002 (413SX20-0005) | LS | 1 | $106,200 | $150,000 | $150,000 | $210,000 | $296,895 |
| 0001-0440 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 9 | $108.00 | $150.00 | $125.00 | $500.00 | $85.28 |
| 0001-0450 | Underdrain UD-4 (501SD20-0004) | LF | 160 | $57.90 | $25.00 | $55.00 | $65.00 | $27.24 |
| 0001-0460 | Crossdrain CD-2 (501SD20-0007) | LF | 32 | $58.00 | $60.00 | $55.00 | $90.00 | $18.11 |
| 0001-0470 | Outlet pipe (501SD20-0009) | LF | 10 | $87.90 | $30.00 | $45.00 | $30.00 | $36.54 |
| 0001-0480 | Curb, STD. CG-2 (502SD20-0011) | LF | 173 | $61.00 | $90.00 | $86.00 | $80.00 | $50.28 |
| 0001-0490 | NS saw cut H.C.C. items saw cut full depth sidewalk (502SX20-0010) | LF | 4 | $60.00 | $35.00 | $85.00 | $30.00 | $78.23 |
| 0001-0500 | CG-12 detectable warning surface (504SD20-0002) | SY | 3 | $510.00 | $575.00 | $625.00 | $1,300.00 | $1,173.38 |
| 0001-0510 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 76 | $162.00 | $100.00 | $165.00 | $190.00 | $107.50 |
| 0001-0520 | Handrail HR-1 type II (504SD20-0014) | LF | 33 | $720.00 | $450.00 | $500.00 | $535.00 | $558.49 |
| 0001-0530 | Gate FE-CL 10' (507SD20-0012) | EACH | 2 | $2,880.00 | $2,500.00 | $2,500.00 | $2,500.00 | $1,680.00 |
| 0001-0540 | NS fence temporary chain link fence (507SX20-0013) | LF | 416 | $36.00 | $15.00 | $50.00 | $70.00 | $39.90 |
| 0001-0550 | Demo. of pavement flexible (508SD20-0004) | SY | 392 | $22.50 | $50.00 | $25.00 | $28.00 | $27.70 |
| 0001-0560 | Remove sidewalk and entrance (510SX20-0001) | SY | 30 | $64.80 | $150.00 | $100.00 | $65.00 | $86.10 |
| 0001-0570 | Type 3 barricade 8' (512SD20-0013) | EACH | 4 | $960.00 | $500.00 | $1,000.00 | $600.00 | $644.13 |
| 0001-0580 | Temporary sign (512SD20-0014) | SF | 297 | $28.00 | $25.00 | $22.00 | $28.00 | $32.90 |
| 0001-0590 | Group 2 longitudinal channelizing device (512SD20-0022) | LF | 810 | $138.00 | $118.00 | $130.00 | $100.00 | $134.48 |
| 0001-0600 | Group 2 channelizing devices (512SD20-0024) | DAY | 5,400 | $0.60 | $2.00 | $1.00 | $2.00 | $0.39 |
| 0001-0610 | Port.changeable mess. sign (512SD20-0025) | HR | 720 | $10.00 | $9.00 | $5.00 | $15.00 | $8.71 |
| 0001-0620 | Flagger service (512SD20-0027) | HR | 100 | $72.00 | $60.00 | $45.00 | $65.00 | $73.89 |
| 0001-0630 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 48 | $90.00 | $25.00 | $6.60 | $12.00 | $8.40 |
| 0001-0640 | Mobilization (513SD20-0001) | LS | 1 | $109,800 | $100,000 | $95,000 | $130,000 | $134,859 |
| 0001-0650 | Flexible pave.planing 0"-2" (515SD20-0013) | SY | 38 | $29.00 | $150.00 | $34.50 | $125.00 | $5.25 |
| 0001-0660 | Construction surveying constr. (517SD20-0001) | LS | 1 | $26,880 | $30,000 | $25,000 | $55,000 | $11,340 |
| 0001-0670 | Mailbox post, single (521SD20-0001) | EACH | 1 | $720.00 | $1,000.00 | $350.00 | $600.00 | $221.55 |
| 0001-0680 | Mailbox post, multiple (521SD20-0003) | EACH | 1 | $780.00 | $1,000.00 | $500.00 | $80.00 | $908.25 |
| 0001-0690 | Topsoil class B 3" (602SD20-0004) | CY | 4 | $1,356.00 | $1,000.00 | $500.00 | $250.00 | $294.00 |
| 0001-0700 | Temporary seed (603SD20-0002) | LB | 1 | $300.00 | $5.00 | $140.00 | $60.00 | $12.85 |
| 0001-0710 | Regular seed (603SD20-0003) | LB | 4 | $300.00 | $5.00 | $175.00 | $60.00 | $479.33 |
| 0001-0720 | Overseeding (603SD20-0004) | LB | 3 | $300.00 | $6.00 | $165.00 | $60.00 | $577.50 |
| 0001-0730 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 109 | $20.00 | $10.00 | $8.00 | $4.00 | $0.78 |
| 0001-0740 | Fertilizer nitrogen - N (603SD20-0014) | LB | 1 | $300.00 | $5.00 | $14.00 | $5.00 | $1.32 |
| 0001-0750 | Fertilizer phosphorous - P (603SD20-0015) | LB | 1 | $300.00 | $5.00 | $14.00 | $5.00 | $1.32 |
| 0001-0760 | Fertilizer potassium - K (603SD20-0016) | LB | 1 | $300.00 | $5.00 | $14.00 | $5.00 | $1.32 |
| 0001-0770 | Lime (603SD20-0017) | TON | 0.06 | $15,000 | $300.00 | $3,200.00 | $365.00 | $296.17 |
| 0001-0780 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 129 | $16.00 | $10.00 | $6.00 | $8.00 | $2.63 |
| 0001-0790 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 44 | $54.00 | $70.00 | $35.00 | $40.00 | $56.96 |
| 0001-0800 | Type B class II PVMT line MRKG 4" (704SD20-0011) | LF | 618 | $10.00 | $9.00 | $9.00 | $10.00 | $3.73 |
| 0001-0810 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 72 | $42.00 | $40.00 | $40.00 | $45.00 | $22.05 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of June 24, 2026. Compiled by Mirage Metrics.