Reinforcing steel substruct. const., VDOT 406SD20-0006

Low bidders on VDOT contracts carried a median of $3.00 per LB for this item, over the 24 months to 28 OCT 2026, across 9 low bids. Half of all 50 bids fell between $2.62 and $5.00.

Owner
Virginia DOT
Item
406SD20-0006
Unit
LB
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 65200 on lettings from 26 FEB 2002 to 15 DEC 2021 (640 bids); 406SD20-0006 on lettings from 25 FEB 2026 to 22 JUL 2026 (50 bids). They are combined here into one trend.

$3.00Low bidder's median, per LB
$3.98Median of all bids, per LB
9Contracts in the window

By year of letting

Reinforcing steel substruct. const., VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20021212$0.7436$0.70
200388$0.8822$0.88
20041717$0.9046$0.90
200577$1.2020$0.98
200688$0.9524$0.94
200788$0.9523$1.00
200822$1.006$1.02
200988$0.7824$0.93
201066$0.9018$0.88
20111111$1.0033$1.00
201288$1.0624$1.08
20131818$1.0054$1.10
20141616$1.1041$1.10
20151719$1.3347$1.30
20162625$1.1072$1.20
201799$1.4027$1.42
20181010$1.3528$1.42
20191313$1.5039$1.60
20201111$1.4033$1.60
202177$1.8121$1.60
202699$3.0050$3.98

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Culpeper3$2.5020$3.67
Staunton3$3.0015$5.00
Reinforcing steel substruct. const., VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

Who is lowest on this line

BidderLines bidLowest on the line
Fairfield-Echols, LLC3716 (43%)
Burleigh Construction Co., Inc.4413 (30%)
Abernathy Construction Corporation2513 (52%)
Crossroads Bridge Inc2311 (48%)
English Construction Company, Incorporated2111 (52%)
DLB, Inc.2710 (37%)
Reinforcing steel substruct. const., VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000118431B20Culpeper8,130$2.50$3.066Freyssinet, Inc.VDOT
22 JUL 2026C0000121138B52Bristol6,590$2.00$3.105Elk Knob, Inc.VDOT
24 JUN 2026C0000112964B03Staunton1,900$2.52$5.005Hammond-Mitchell, Inc.VDOT
24 JUN 2026C0000117111B62Bristol11,540$4.58$4.583King General Contractors, Inc.VDOT
27 MAY 2026C0000118430B39Culpeper9,600$2.08$3.008Burleigh Construction Co., Inc.VDOT
22 APR 2026C0000124564B64Culpeper360$4.00$4.506WG Construction Co., Inc.VDOT
25 MAR 2026C0000121531B68Hampton Roads1,815$3.00$3.007Crofton Construction Services,VDOT
25 FEB 2026C0000117021B19Staunton9,953$3.00$3.005Freyssinet, Inc.VDOT
25 FEB 2026C0000115132M01Staunton1,026$5.00$5.005A & J Development and Excavation, Inc.VDOT
15 DEC 2021C0000111777C01Culpeper11,500$2.00$2.003Fairfield-Echols, LLCVDOT
25 AUG 2021C0000111282B24Lynchburg9,430$1.60$3.003Burleigh Construction Co., Inc.VDOT
26 MAY 2021C0000104005C01Northern Virginia10,330$1.40$1.403Shirley Contracting Company, LLCVDOT
28 APR 2021C0000071874B03Bristol6,750$2.25$2.253Estes Bros. Const., Inc.VDOT
24 MAR 2021C0000105490B43Richmond27,670$1.50$1.503Clearwater Construction, Inc.VDOT
24 MAR 2021C0000110433B43Northern Virginia36,930$2.68$1.253Clearwater Construction, Inc.VDOT
Latest VDOT contracts carrying Reinforcing steel substruct. const.

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy