NS bridge superstructure transportation and placement of precast bridge approach slab units, VDOT 410SX20-0006
Low bidders on VDOT contracts carried a median of $6,500.00 per EACH for this item, from 26 MAR 2002 to 22 OCT 2025, across 50 low bids. Half of all 149 bids fell between $2,000.00 and $16,000.
- Owner
- Virginia DOT
- Item
- 410SX20-0006
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT prints this item as “NS BRIDGE SUPERSTRUCTURE TRANSPORTATION AND PLACEMENT OF PRECAST BRIDGE APPROACH SLAB UNITS”.
VDOT has bid this work under more than one code: 62535 on lettings from 26 MAR 2002 to 23 JUN 2021 (177 bids); 410SX20-0006 on lettings from 22 OCT 2025 to 22 OCT 2025 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 3 | 3 | $4,900.00 | 9 | $5,000.00 |
| 2003 | 4 | 4 | $4,434.92 | 12 | $5,000.00 |
| 2004 | 2 | 2 | $8,000.00 | 5 | $8,000.00 |
| 2005 | 2 | 2 | $1,500.00 | 7 | $840.00 |
| 2006 | 1 | 2 | $6,833.33 | 6 | $6,416.66 |
| 2007 | 3 | 3 | $9,500.00 | 9 | $9,700.00 |
| 2008 | 1 | 2 | $6,500.00 | 6 | $9,750.00 |
| 2009 | 3 | 4 | $7,582.24 | 16 | $7,500.00 |
| 2010 | 4 | 5 | $3,000.00 | 15 | $3,000.00 |
| 2011 | 1 | 1 | $18,600 | 3 | $19,229 |
| 2012 | 3 | 3 | $728.00 | 9 | $1,275.00 |
| 2015 | 4 | 9 | $2,000.00 | 25 | $2,157.61 |
| 2016 | 2 | 3 | $22,000 | 7 | $22,000 |
| 2019 | 1 | 2 | $45,000 | 6 | $45,000 |
| 2020 | 1 | 2 | $51,250 | 6 | $51,250 |
| 2021 | 3 | 3 | $21,100 | 7 | $20,000 |
| 2025 | 1 | 0 | n/a | 1 | $705.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 14 | $6,666.66 | 42 | $7,600.00 |
| Richmond | 15 | $21,100 | 41 | $21,100 |
| Fredericksburg | 5 | $3,000.00 | 15 | $1,500.00 |
| Culpeper | 5 | $5,000.00 | 15 | $5,000.00 |
| Staunton | 4 | $6,000.00 | 11 | $7,105.00 |
| Hampton Roads | 4 | $8,914.49 | 10 | $10,100 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 12 | $7,748.91 |
| 2 to 6 | 13 | $8,203.00 |
| 6 to 8 | 12 | $7,416.66 |
| 9 to 828 | 13 | $2,000.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| DLB, Inc. | 11 | 6 (55%) |
| Corman Construction, Inc. | 11 | 3 (27%) |
| Cleco Corporation | 6 | 3 (50%) |
| General Excavation, Inc. | 5 | 3 (60%) |
| D. A. Brown, Inc. | 9 | 2 (22%) |
| Technopref Industries Inc. | 6 | 2 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 OCT 2025 | C0000118393X01 | Northern Virginia | 71 | n/a | $705.00 | 1 | Martins Construction Corp. | VDOT |
| 23 JUN 2021 | C0000118108B74 | Hampton Roads | 348 | $750.00 | $750.00 | 1 | Wunna Contracting Corporation | VDOT |
| 26 MAY 2021 | C0000117389N60B | Hampton Roads | 5 | $25,800 | $20,000 | 3 | Coastal Gunite Construction Company | VDOT |
| 20 JAN 2021 | C0000109988C01 | Richmond | 8 | $21,100 | $21,100 | 3 | Abernathy Construction Corporation | VDOT |
| 21 OCT 2020 | C0000101238B22 | Richmond | 2 | $55,000 | $55,000 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 21 OCT 2020 | C0000101238B22 | Richmond | 4 | $47,500 | $47,500 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 24 JUL 2019 | C0000101241B41 | Richmond | 2 | $45,000 | $45,000 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 24 JUL 2019 | C0000101241B41 | Richmond | 3 | $45,000 | $45,000 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 21 DEC 2016 | C0000103553B61 | Bristol | 6 | $20,800 | $21,500 | 3 | Crossroads Bridge Inc | VDOT |
| 26 OCT 2016 | C0000107867C01 | Richmond | 14 | $22,000 | $21,550 | 2 | Wagman Heavy Civil, Inc. | VDOT |
| 26 OCT 2016 | C0000107867C01 | Richmond | 2 | $65,000 | $47,500 | 2 | Wagman Heavy Civil, Inc. | VDOT |
| 16 DEC 2015 | C0000101243C01 | Richmond | 9 | $28,150 | $28,150 | 3 | Fielder'S Choice Enterprises, Inc. | VDOT |
| 18 NOV 2015 | C0000098132B01 | Richmond | 96 | $2,000.00 | $2,000.00 | 3 | Cleco Corporation | VDOT |
| 18 NOV 2015 | C0000098132B01 | Richmond | 132 | $750.00 | $551.54 | 3 | Cleco Corporation | VDOT |
| 18 NOV 2015 | C0000098132B01 | Richmond | 8 | $1,200.00 | $2,123.00 | 3 | Cleco Corporation | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.