NS pre. & spot coat EX. STR. various structures, VDOT 411SX20-0001
Low bidders on VDOT contracts carried a median of $150.00 per SF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 2 bids fell between $112.50 and $137.50.
- Owner
- Virginia DOT
- Item
- 411SX20-0001
- Unit
- SF
- Data through
- 28 OCT 2026
VDOT prints this item as “NS PRE. & SPOT COAT EX. STR. VARIOUS STRUCTURES”.
VDOT has bid this work under more than one code: 68455 on lettings from 11 MAR 2002 to 25 AUG 2021 (259 bids); 411SX20-0001 on lettings from 04 FEB 2026 to 04 FEB 2026 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 2 | 2 | $121.58 | 6 | $57.50 |
| 2003 | 4 | 9 | $5.18 | 20 | $11.94 |
| 2004 | 1 | 1 | $13.20 | 3 | $13.20 |
| 2005 | 5 | 11 | $11.22 | 26 | $11.00 |
| 2006 | 5 | 21 | $11.50 | 42 | $11.50 |
| 2007 | 12 | 14 | $15.75 | 40 | $15.60 |
| 2008 | 3 | 10 | $10.68 | 22 | $16.32 |
| 2009 | 1 | 1 | $24.53 | 3 | $30.00 |
| 2010 | 5 | 15 | $13.00 | 43 | $28.00 |
| 2011 | 3 | 5 | $11.50 | 15 | $11.50 |
| 2014 | 2 | 3 | $45.00 | 7 | $45.00 |
| 2015 | 2 | 2 | $142.50 | 6 | $67.50 |
| 2017 | 2 | 2 | $195.00 | 6 | $170.00 |
| 2018 | 1 | 1 | $200.00 | 2 | $162.50 |
| 2019 | 3 | 3 | $40.00 | 6 | $42.50 |
| 2020 | 2 | 2 | $47.25 | 6 | $48.14 |
| 2021 | 1 | 2 | $100.00 | 6 | $638.50 |
| 2026 | 1 | 1 | $150.00 | 2 | $125.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 45 | $11.00 | 105 | $12.65 |
| Salem | 34 | $11.50 | 86 | $13.20 |
| Northern Virginia | 12 | $30.00 | 32 | $40.00 |
| Richmond | 7 | $40.00 | 18 | $47.50 |
| Culpeper | 4 | $66.50 | 12 | $67.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SF) | Low bids | Low-bid median |
|---|---|---|
| 3 to 858 | 26 | $40.00 |
| 858 to 1,674 | 26 | $13.60 |
| 1,750 to 3,090 | 26 | $11.11 |
| 3,090 to 21,150 | 27 | $10.59 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Cleco Corporation | 39 | 22 (56%) |
| Lanford Brothers Company, Incorporated | 55 | 19 (35%) |
| Elk Knob, Inc. | 29 | 13 (45%) |
| DLB, Inc. | 13 | 11 (85%) |
| Ken Construction Co., Inc. | 8 | 8 (100%) |
| Klicos Painting Company, Inc. | 8 | 8 (100%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 500 | $150.00 | $125.00 | 2 | M. D. Miller Co., Inc. | VDOT |
| 25 AUG 2021 | C0000118517N01 | Culpeper | 80 | $100.00 | $837.00 | 3 | Saffo Contractors, Inc. | VDOT |
| 25 AUG 2021 | C0000118517N01 | Culpeper | 150 | $100.00 | $440.00 | 3 | Saffo Contractors, Inc. | VDOT |
| 21 OCT 2020 | C0000110624B15 | Salem | 1,516 | $44.50 | $44.50 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 22 APR 2020 | C0000111298B10 | Richmond | 1,000 | $50.00 | $115.50 | 3 | M. D. Miller Co., Inc. | VDOT |
| 25 SEP 2019 | C000114208B32 | Richmond | 147 | $87.00 | $77.47 | 2 | Freyssinet, Inc. | VDOT |
| 22 MAY 2019 | C000110784B20 | Richmond | 3,200 | $40.00 | $37.00 | 2 | Burleigh Construction Co., Inc. | VDOT |
| 22 MAY 2019 | C000110997B04 | Richmond | 2,400 | $32.00 | $38.50 | 2 | Allan Myers Va, Inc. | VDOT |
| 28 MAR 2018 | C0000110922N01 | Bristol | 50 | $200.00 | $162.50 | 2 | Elk Knob, Inc. | VDOT |
| 22 FEB 2017 | C0000110080B70 | Hampton Roads | 30 | $180.00 | $180.00 | 3 | PCL Civil Constructors, Inc. | VDOT |
| 22 FEB 2017 | C000101754B13 | Lynchburg | 52 | $210.00 | $160.00 | 3 | Orders Construction Company, Inc. | VDOT |
| 26 AUG 2015 | C00106951B69 | Northern Virginia | 2,800 | $35.00 | $30.00 | 3 | Martins Construction Corp. | VDOT |
| 25 MAR 2015 | C00106511N01 | Bristol | 50 | $250.00 | $250.00 | 3 | Elk Knob, Inc. | VDOT |
| 26 MAR 2014 | C000104565N01 | Bristol | 3 | $823.40 | $823.40 | 3 | Richardson-Wayland Electrical Co. LLC | VDOT |
| 26 MAR 2014 | C00103924C01 | Northern Virginia | 1,000 | $45.00 | $44.70 | 2 | Martins Construction Corp. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.