Patching type B, VDOT 412SD20-0033
Low bidders on VDOT contracts carried a median of $850.00 per SY for this item, over the 24 months to 28 OCT 2026, across 3 low bids. Half of all 15 bids fell between $760.00 and $2,371.50.
- Owner
- Virginia DOT
- Item
- 412SD20-0033
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT prints this item as “PATCHING TYPE B”.
VDOT has bid this work under more than one code: 68320 on lettings from 26 MAR 2002 to 24 FEB 2021 (429 bids); 412SD20-0033 on lettings from 24 JUN 2026 to 26 AUG 2026 (15 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 13 | 13 | $160.00 | 37 | $160.00 |
| 2003 | 13 | 13 | $175.00 | 33 | $200.00 |
| 2004 | 9 | 9 | $168.00 | 24 | $164.81 |
| 2005 | 21 | 21 | $165.00 | 56 | $200.00 |
| 2006 | 14 | 14 | $237.50 | 37 | $225.00 |
| 2007 | 27 | 27 | $225.00 | 69 | $250.00 |
| 2008 | 14 | 14 | $250.00 | 38 | $250.00 |
| 2009 | 16 | 16 | $250.00 | 46 | $250.00 |
| 2010 | 9 | 9 | $225.00 | 25 | $275.00 |
| 2011 | 7 | 6 | $350.00 | 18 | $307.50 |
| 2012 | 3 | 3 | $390.00 | 7 | $390.00 |
| 2013 | 5 | 5 | $400.00 | 15 | $370.00 |
| 2014 | 2 | 2 | $500.00 | 6 | $387.50 |
| 2015 | 1 | 1 | $400.00 | 3 | $400.00 |
| 2018 | 1 | 1 | $400.00 | 2 | $400.00 |
| 2019 | 1 | 1 | $654.20 | 3 | $750.00 |
| 2020 | 2 | 2 | $750.00 | 6 | $817.50 |
| 2021 | 1 | 1 | $600.00 | 3 | $600.00 |
| 2026 | 3 | 3 | $850.00 | 15 | $1,250.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 59 | $215.00 | 146 | $247.75 |
| Bristol | 36 | $221.50 | 105 | $250.00 |
| Lynchburg | 35 | $225.00 | 99 | $250.00 |
| Richmond | 11 | $250.00 | 30 | $275.00 |
| Northern Virginia | 5 | $577.00 | 21 | $785.00 |
| Staunton | 7 | $200.00 | 18 | $220.62 |
| Culpeper | 5 | $225.00 | 13 | $250.00 |
| Hampton Roads | 3 | $625.00 | 9 | $654.20 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 20 | 40 | $250.00 |
| 20 to 58 | 40 | $213.12 |
| 58 to 120 | 40 | $225.00 |
| 124 to 1,000 | 41 | $200.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Cleco Corporation | 102 | 55 (54%) |
| Lanford Brothers Company, Incorporated | 120 | 50 (42%) |
| Burleigh Construction Co., Inc. | 48 | 31 (65%) |
| Elk Knob, Inc. | 39 | 13 (33%) |
| Corman Construction, Inc. | 18 | 6 (33%) |
| Ken Construction Co., Inc. | 20 | 5 (25%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 AUG 2026 | C0000129131C01B | Richmond | 5.11 | $10,247 | $17,623 | 2 | Caton Construction Group, Inc. | VDOT |
| 22 JUL 2026 | C0000126560B40 | Northern Virginia | 10 | $850.00 | $995.00 | 7 | Martins Construction Corp. | VDOT |
| 24 JUN 2026 | C0000126561B48 | Northern Virginia | 23 | $577.00 | $1,100.00 | 6 | Rba Engineering International, PLLC | VDOT |
| 24 FEB 2021 | C0000117348B63 | Bristol | 20 | $600.00 | $600.00 | 3 | Elk Knob, Inc. | VDOT |
| 24 JUN 2020 | C000101246M01B | Richmond | 20 | $500.00 | $785.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 27 MAY 2020 | C000115006B61 | Salem | 19 | $1,000.00 | $850.00 | 3 | M. D. Miller Co., Inc. | VDOT |
| 27 FEB 2019 | C00113392B010 | Hampton Roads | 35 | $654.20 | $750.00 | 3 | Curtis Contracting, Inc. | VDOT |
| 28 MAR 2018 | C0000110922N01 | Bristol | 50 | $400.00 | $400.00 | 2 | Elk Knob, Inc. | VDOT |
| 25 MAR 2015 | C00106511N01 | Bristol | 75 | $400.00 | $400.00 | 3 | Elk Knob, Inc. | VDOT |
| 28 MAY 2014 | C00105336B77 | Salem | 20 | $400.00 | $375.00 | 3 | English Construction Company, Incorporated | VDOT |
| 22 JAN 2014 | C00098137B09 | Richmond | 300 | $600.00 | $550.00 | 3 | PCL Civil Constructors, Inc. | VDOT |
| 24 JUL 2013 | C00103105B15 | Bristol | 75 | $400.00 | $400.00 | 3 | Lanford Brothers Company, Incorporated | VDOT |
| 22 MAY 2013 | C00098265B41 | Bristol | 10 | $400.00 | $350.00 | 3 | Elk Knob, Inc. | VDOT |
| 22 MAY 2013 | C00098271B29 | Bristol | 30 | $350.00 | $292.07 | 3 | Ken Construction Co., Inc. | VDOT |
| 22 MAY 2013 | C00103909N01 | Northern Virginia | 382 | $300.00 | $347.71 | 3 | Fort Myer Construction Corporation | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.