VDOT contract C0000126560B40 bid tabulation
Bridge rehabilitation. Let by Virginia DOT on July 22, 2026, Arlington, Northern Virginia. 7 bids received; low bid $4,620,121 by Martins Construction Corp..
- Owner
- Virginia DOT
- Letting
- 22 JUL 2026
- Pay items
- 84
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martins Construction Corp. | $4,620,121 | Low |
| 2 | Fort Myer Construction Corporation | $5,691,081 | +23% |
| 3 | Rba Engineering International, PLLC | $5,872,569 | +27% |
| 4 | Gemstone, LLC | $6,227,316 | +35% |
| 5 | Freyssinet, Inc. | $6,316,110 | +37% |
| 6 | Sagres Construction Corporation | $7,676,553 | +66% |
| 7 | Structural Technologies, LLC of Maryland | $8,273,920 | +79% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martins Construction Corp. | 2. Fort Myer Construction Corporation | 3. Rba Engineering International, PLLC | 4. Gemstone, LLC | 5. Freyssinet, Inc. | 6. Sagres Construction Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Baseline progress schedule (108SP20-0001) | LS | 1 | $35,000 | $8,625.00 | $2,889.00 | $6,000.00 | $9,630.00 | $15,000 |
| 0001-0020 | Progress schedule updates (108SP20-0002) | EACH | 24 | $300.00 | $747.50 | $310.00 | $600.00 | $860.00 | $1,000.00 |
| 0001-0030 | Regular excavation (303SD20-0001) | CY | 3 | $90.00 | $300.00 | $798.00 | $400.00 | $650.00 | $88.96 |
| 0001-0040 | Inlet protection type A (303SD20-0030) | EACH | 2 | $1,000.00 | $400.00 | $287.00 | $400.00 | $900.00 | $222.19 |
| 0001-0050 | Inlet protection type B (303SD20-0031) | EACH | 3 | $275.00 | $400.00 | $247.00 | $500.00 | $740.00 | $256.75 |
| 0001-0060 | Temp. silt fence type A (303SD20-0034) | LF | 285 | $13.00 | $12.00 | $7.00 | $10.00 | $7.00 | $5.57 |
| 0001-0070 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 93 | $95.00 | $110.00 | $124.00 | $110.00 | $105.00 | $86.00 |
| 0001-0080 | NS aggr. material no. 1 (308SX20-0002) | CY | 13 | $125.00 | $150.00 | $137.00 | $900.00 | $145.00 | $110.81 |
| 0001-0090 | Cover matl. aggr. no. 68 (311SD20-0002) | TON | 2 | $255.00 | $450.00 | $240.00 | $1,000.00 | $520.00 | $107.91 |
| 0001-0100 | Aggr. no. 78 (314SP20-0010) | SY | 20 | $120.00 | $125.00 | $28.00 | $250.00 | $44.00 | $110.00 |
| 0001-0110 | NS aggregate cement aggregate base material (314SX20-0005) | TON | 47 | $180.00 | $150.00 | $119.00 | $750.00 | $180.00 | $114.93 |
| 0001-0120 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 26 | $250.00 | $300.00 | $271.00 | $1,440.00 | $2,040.00 | $300.00 |
| 0001-0130 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 23 | $285.00 | $300.00 | $310.00 | $1,680.00 | $2,380.00 | $300.00 |
| 0001-0140 | Asphalt concrete TY. IM- 19.0A const (315SD20-0004) | TON | 31 | $190.00 | $250.00 | $258.00 | $810.00 | $1,150.00 | $275.00 |
| 0001-0150 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 135 | $145.00 | $200.00 | $284.00 | $570.00 | $810.00 | $245.00 |
| 0001-0160 | Saw-cut asphalt concrete (UP to 14") (315SD20-0104) | LF | 1,630 | $5.00 | $8.00 | $40.00 | $9.00 | $10.00 | $6.00 |
| 0001-0170 | Hydraulic cem. base course 9" (316SD20-0003) | SY | 280 | $150.00 | $185.00 | $139.00 | $230.00 | $120.00 | $250.00 |
| 0001-0180 | Bridge deck grooving maint. (404SD20-0020) | SY | 1,653 | $6.40 | $15.00 | $13.00 | $25.00 | $20.00 | $10.00 |
| 0001-0190 | Pier protection system 54", const (410SX20-0011) | LF | 245 | $630.00 | $752.60 | $701.00 | $800.00 | $360.00 | $870.50 |
| 0001-0200 | NS recoat EX. STR. (fed. STR. no. 301/VA STR. no. 2041) (411SX20-0004) | LS | 1 | $820,000 | $1,040,000 | $1,183,891 | $930,000 | $2,370,000 | $1,300,000 |
| 0001-0210 | NS disposal of material (fed. STR. no. 301/VA STR. no. 2041) (411SX20-0006) | LS | 1 | $10,260 | $61,000 | $13,155 | $20,000 | $107,000 | $50,000 |
| 0001-0220 | Crack repair type B (412SD20-0013) | LF | 10 | $125.00 | $126.00 | $164.00 | $210.00 | $70.00 | $350.00 |
| 0001-0230 | Embedded galvanic anodes (412SD20-0017) | EACH | 534 | $36.00 | $34.65 | $66.00 | $50.00 | $53.00 | $45.00 |
| 0001-0240 | Embedded galvanic anodes (412SD20-0017) | EACH | 346 | $36.00 | $34.65 | $67.00 | $50.00 | $53.00 | $45.00 |
| 0001-0250 | Patching type B (412SD20-0033) | SY | 10 | $850.00 | $735.00 | $785.00 | $1,500.00 | $995.00 | $1,250.00 |
| 0001-0260 | Patching type C (412SD20-0035) | SY | 2 | $1,350.00 | $1,522.50 | $1,394.00 | $4,500.00 | $2,570.00 | $2,500.00 |
| 0001-0270 | Back wall reconstruction hes (412SD20-0046) | LF | 133 | $300.00 | $630.00 | $426.00 | $960.00 | $265.00 | $900.00 |
| 0001-0280 | Jacking and blocking beam (412SD20-0048) | EACH | 36 | $8,000.00 | $11,550 | $10,962 | $8,500.00 | $8,180.00 | $14,307 |
| 0001-0290 | Conc. superstr. surface repair (412SD20-0049) | SY | 23 | $1,650.00 | $1,575.00 | $1,189.00 | $2,000.00 | $1,300.00 | $1,950.00 |
| 0001-0300 | Concrete substruct. surface repair (412SD20-0061) | SY | 56 | $1,700.00 | $1,470.00 | $1,099.00 | $2,000.00 | $1,320.00 | $1,820.00 |
| 0001-0310 | Reconstruct bridge seat type A (412SD20-0062) | EACH | 19 | $4,000.00 | $3,675.00 | $1,918.00 | $4,900.00 | $3,100.00 | $4,600.00 |
| 0001-0320 | NS BR.superstr. wid./repair replace bearing (412SX20-0009) | EACH | 36 | $8,500.00 | $13,598 | $6,450.00 | $8,200.00 | $10,500 | $17,559 |
| 0001-0330 | NS BR.superstr. wid./repair debris shield (412SX20-0013) | LS | 1 | $153,500 | $120,000 | $116,068 | $40,000 | $42,500 | $275,000 |
| 0001-0340 | NS BR.superstr. wid./repair modify dry standpipe arm and valve assembly (412SX20-0013) | LS | 1 | $1,600.00 | $10,000 | $154,757 | $45,000 | $8,510.00 | $35,000 |
| 0001-0350 | NS BR.superstr. wid./repair deck slab closure (412SX20-0015) | SY | 180 | $2,000.00 | $1,890.00 | $1,613.00 | $3,000.00 | $965.00 | $2,350.00 |
| 0001-0360 | NS BR.superstr. wid./repair waterproofing coating (412SX20-0015) | SY | 863 | $52.00 | $89.25 | $117.00 | $75.00 | $77.00 | $110.55 |
| 0001-0370 | NS BR. substr. wid./repair partial beam/girder replacement substructure (412SX20-0020) | LB | 500 | $40.00 | $47.25 | $14.00 | $80.00 | $63.00 | $70.00 |
| 0001-0380 | NS BR. substr. wid./repair slope protection repair (412SX20-0022) | LS | 1 | $20,000 | $90,000 | $186,998 | $30,000 | $7,700.00 | $50,000 |
| 0001-0390 | NS BR. substr. wid./repair waterproofing coating (412SX20-0024) | SY | 759 | $90.00 | $73.50 | $117.00 | $180.00 | $77.00 | $100.00 |
| 0001-0400 | NS env.& worker protect. (fed. STR. no. 301/VA STR. no. 2041) (413SX20-0003) | LS | 1 | $493,000 | $583,500 | $105,235 | $400,000 | $51,300 | $675,000 |
| 0001-0410 | Waterproofing – epoxy resin type EP-3B/EP-3T (416SD20-0003) | SY | 42 | $113.00 | $97.75 | $46.00 | $140.00 | $70.00 | $110.00 |
| 0001-0420 | Waterproofing – epoxy resin type EP-3B/EP-3T (416SD20-0003) | SY | 692 | $85.00 | $97.75 | $37.00 | $78.00 | $70.00 | $110.00 |
| 0001-0430 | Adhesive based JT. sealer CL. I, 1-1/2" maint. (420SD20-0019) | LF | 86 | $68.00 | $184.00 | $115.00 | $125.00 | $125.00 | $208.10 |
| 0001-0440 | Adhesive based JT. sealer CL. I, 2" maint. (420SD20-0020) | LF | 37 | $95.00 | $138.00 | $124.00 | $150.00 | $125.00 | $156.08 |
| 0001-0450 | Adhesive based JT. sealer CL. II, 2" maint. (420SD20-0023) | LF | 17 | $106.00 | $300.00 | $119.00 | $200.00 | $125.00 | $156.08 |
| 0001-0460 | Type A milling 1-3/4" (425SD20-0005) | SY | 1,653 | $37.00 | $22.00 | $35.00 | $43.00 | $43.00 | $50.00 |
| 0001-0470 | Furn.very erly mod.conc. 2-1/4"- 2-3/4" (425SD20-0013) | CY | 94 | $1,200.00 | $2,500.00 | $1,573.00 | $3,100.00 | $2,840.00 | $2,000.00 |
| 0001-0480 | Place very early mod.conc.overlay (425SD20-0015) | SY | 1,653 | $95.00 | $73.81 | $55.00 | $150.00 | $59.00 | $350.00 |
| 0001-0490 | Type A hydro-demolition 1/2" (425SD20-0022) | SY | 1,653 | $82.00 | $151.24 | $72.00 | $120.00 | $160.00 | $110.00 |
| 0001-0500 | Partial beam/girder replacement superstructure (426SD20-0009) | LB | 2,550 | $36.00 | $29.40 | $14.00 | $70.00 | $29.00 | $36.50 |
| 0001-0510 | NS nbis access, under bridge (fed. STR. no. 301/VA STR. no. 2041) (430SX20-0001) | DAY | 4 | $1,350.00 | $3,500.00 | $9,846.00 | $2,500.00 | $12,800 | $4,500.00 |
| 0001-0520 | Curb, radial CG-3 (502SD20-0015) | LF | 191 | $66.00 | $33.92 | $44.00 | $30.00 | $64.00 | $130.00 |
| 0001-0530 | Median barrier MB-7D (502SD20-0036) | LF | 166 | $402.00 | $233.20 | $194.00 | $120.00 | $160.00 | $300.00 |
| 0001-0540 | Median barrier MB-7F (502SD20-0038) | LF | 74 | $508.00 | $355.10 | $187.00 | $200.00 | $210.00 | $500.00 |
| 0001-0550 | Median strip MS-1 (502SD20-0053) | SY | 123 | $176.00 | $148.40 | $269.00 | $240.00 | $275.00 | $250.00 |
| 0001-0560 | NS median barrier 54" concrete barrier to MB- 7F transition (502SX20-0011) | LF | 10 | $607.00 | $969.90 | $634.00 | $750.00 | $390.00 | $1,400.00 |
| 0001-0570 | NS median barrier modified median barrier MB-7D (502SX20-0011) | LF | 7 | $458.00 | $625.40 | $682.00 | $850.00 | $2,880.00 | $1,000.00 |
| 0001-0580 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 6 | $124.00 | $79.50 | $181.00 | $800.00 | $1,030.00 | $150.00 |
| 0001-0590 | Geotextile drainage fabric (504SD20-0005) | SY | 105 | $8.15 | $6.00 | $9.00 | $18.00 | $16.00 | $6.00 |
| 0001-0600 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 3 | $2,462.00 | $2,760.00 | $2,069.00 | $2,040.00 | $4,250.00 | $2,942.53 |
| 0001-0610 | Fixed object attach. GR- foa-5 (505SD20-0055) | EACH | 3 | $6,565.00 | $7,360.00 | $4,745.00 | $4,680.00 | $8,510.00 | $7,846.75 |
| 0001-0620 | Remove existing guardrail (505SD20-0073) | LF | 706 | $14.00 | $15.53 | $4.00 | $3.60 | $34.00 | $16.00 |
| 0001-0630 | Impact atten. TY.1 TL-3, low maintenance (505SP20-0001) | EACH | 1 | $46,000 | $41,745 | $80,664 | $22,710 | $68,100 | $50,000 |
| 0001-0640 | CSB-3 type 1 (505SP20-0037) | LF | 56 | $650.00 | $816.20 | $1,044.00 | $750.00 | $395.00 | $945.75 |
| 0001-0650 | CSB-TW (505SP20-0038) | EACH | 1 | $10,000 | $12,190 | $22,023 | $15,000 | $12,100 | $15,000 |
| 0001-0660 | Demo. of PVMT. combination (508SD20-0002) | SY | 630 | $65.00 | $42.00 | $70.00 | $70.00 | $17.00 | $35.00 |
| 0001-0670 | NS modify exist. drop inlet (510SX20-0031) | EACH | 1 | $6,670.00 | $10,000 | $2,573.00 | $18,000 | $1,920.00 | $6,500.00 |
| 0001-0680 | NS remove exist. combination curb and gutter (510SX20-0039) | LF | 706 | $16.00 | $15.00 | $70.00 | $30.00 | $12.00 | $41.25 |
| 0001-0690 | Traffic barrier service MB-11A (512SD20-0003) | LF | 2,000 | $35.00 | $65.00 | $142.00 | $94.27 | $175.00 | $75.00 |
| 0001-0700 | Temporary sign (512SD20-0014) | SF | 1,012 | $23.00 | $18.00 | $35.00 | $32.40 | $43.00 | $45.00 |
| 0001-0710 | Truck mounted attenuator (512SD20-0023) | HR | 2,800 | $2.85 | $30.00 | $24.00 | $40.00 | $39.00 | $35.00 |
| 0001-0720 | Group 2 channelizing devices (512SD20-0024) | DAY | 7,900 | $1.70 | $3.00 | $12.00 | $0.30 | $0.40 | $1.17 |
| 0001-0730 | Electronic arrow board (512SD20-0026) | HR | 2,720 | $5.30 | $4.00 | $8.00 | $4.87 | $4.50 | $13.24 |
| 0001-0740 | Temp. PVMT MRKG TY. E, 6" (512SD20-0054) | LF | 1,210 | $7.00 | $4.89 | $6.00 | $11.09 | $16.00 | $5.95 |
| 0001-0750 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 410 | $5.00 | $3.05 | $12.00 | $9.97 | $14.00 | $5.82 |
| 0001-0760 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 800 | $5.25 | $5.75 | $7.00 | $11.57 | $16.00 | $9.62 |
| 0001-0770 | Impact attenuator IA-1 (512SD20-0069) | EACH | 2 | $8,700.00 | $10,000 | $11,575 | $32,400 | $15,300 | $23,203 |
| 0001-0780 | Mobilization (513SD20-0001) | LS | 1 | $260,000 | $210,000 | $837,195 | $427,000 | $77,600 | $413,000 |
| 0001-0790 | Construction surveying constr. (517SD20-0001) | LS | 1 | $6,160.00 | $38,875 | $32,242 | $15,000 | $12,800 | $175,000 |
| 0001-0800 | Permanent seed (603SD20-0001) | LB | 15 | $5.10 | $20.00 | $18.00 | $6.00 | $47.00 | $12.26 |
| 0001-0810 | Conduit PVC 3" (700SD20-0195) | LF | 3 | $165.00 | $150.00 | $185.00 | $48.00 | $165.00 | $61.30 |
| 0001-0820 | Illuminated traffic control sign (703SD20-0051) | EACH | 3 | $1,750.00 | $4,500.00 | $3,458.00 | $30,222 | $25,500 | $9,957.26 |
| 0001-0830 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 3,162 | $1.85 | $1.27 | $2.00 | $4.94 | $7.00 | $5.00 |
| 0001-0840 | Type B class I PVMT line MRKG 12" (704SD20-0009) | LF | 550 | $3.10 | $4.72 | $9.00 | $6.82 | $9.50 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of July 22, 2026. Compiled by Mirage Metrics.