Asphalt concrete TY. SM-12.5E (76-22 or 64E), VDOT 315SD20-0003
Low bidders on VDOT contracts carried a median of $254.90 per TON for this item, over the 24 months to 28 OCT 2026, across 21 low bids. Half of all 67 bids fell between $194.75 and $321.00.
- Owner
- Virginia DOT
- Item
- 315SD20-0003
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “ASPHALT CONCRETE TY. SM- 12.5E CONST”.
VDOT has bid this work under more than one code: 10609 on lettings from 19 NOV 2002 to 15 DEC 2021 (148 bids); 315SD20-0003 on lettings from 19 NOV 2025 to 26 AUG 2026 (67 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 2 | 2 | $54.25 | 5 | $56.00 |
| 2006 | 1 | 1 | $85.00 | 1 | $85.00 |
| 2009 | 4 | 4 | $101.77 | 10 | $130.00 |
| 2010 | 1 | 1 | $200.00 | 3 | $200.00 |
| 2011 | 1 | 1 | $120.00 | 3 | $130.00 |
| 2012 | 2 | 2 | $122.09 | 6 | $139.50 |
| 2013 | 3 | 3 | $105.00 | 9 | $105.00 |
| 2014 | 1 | 1 | $210.00 | 2 | $223.75 |
| 2015 | 5 | 5 | $99.41 | 15 | $102.00 |
| 2016 | 3 | 3 | $110.00 | 8 | $109.52 |
| 2017 | 5 | 5 | $107.00 | 14 | $115.00 |
| 2018 | 4 | 4 | $220.00 | 8 | $245.00 |
| 2019 | 3 | 4 | $129.84 | 8 | $130.24 |
| 2020 | 8 | 8 | $127.82 | 20 | $130.64 |
| 2021 | 15 | 17 | $138.85 | 36 | $152.00 |
| 2025 | 4 | 4 | $271.99 | 11 | $200.00 |
| 2026 | 17 | 17 | $254.90 | 56 | $271.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Bristol | 9 | $254.90 | 28 | $227.67 |
| Richmond | 4 | $282.50 | 9 | $295.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 23 to 469 | 5 | $285.00 |
| 520 to 1,065 | 5 | $215.00 |
| 1,121 to 1,679 | 5 | $295.00 |
| 1,880 to 5,314 | 6 | $201.99 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| W-L Construction & Paving, Inc. | 20 | 18 (90%) |
| Allan Myers Va, Inc. | 7 | 5 (71%) |
| Curtis Contracting, Inc. | 8 | 4 (50%) |
| M. D. Miller Co., Inc. | 6 | 2 (33%) |
| Howard Brothers Contractor, Inc. | 5 | 2 (40%) |
| Shoosmith Construction, Inc. | 5 | 1 (20%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 26 AUG 2026 | C000119218C01B | Hampton Roads | 700 | $245.96 | $245.96 | 3 | BRANSCOME OPERATING, LLC dba BRANSCOME | VDOT |
| 26 AUG 2026 | C0000119687C01B | Richmond | 1,241 | $295.00 | $334.50 | 2 | Gray and Sons Construction, Inc. | VDOT |
| 26 AUG 2026 | C0000128603B82 | Bristol | 1,679 | $322.00 | $392.50 | 6 | M. D. Miller Co., Inc. | VDOT |
| 26 AUG 2026 | C0000129131C01B | Richmond | 5,314 | $236.25 | $210.12 | 2 | Caton Construction Group, Inc. | VDOT |
| 22 JUL 2026 | C0000119436C01 | Bristol | 1,288 | $267.20 | $191.00 | 4 | E. C. Pace Company, Inc. | VDOT |
| 22 JUL 2026 | C0000119114C01 | Northern Virginia | 469 | $275.00 | $297.50 | 2 | A & M Concrete Corp. | VDOT |
| 22 JUL 2026 | C0000126560B40 | Northern Virginia | 23 | $285.00 | $310.00 | 7 | Martins Construction Corp. | VDOT |
| 22 JUL 2026 | C0000120611C01 | Salem | 1,880 | $302.00 | $302.00 | 1 | Branch Civil, Inc. | VDOT |
| 22 JUL 2026 | C0000120748C01 | Culpeper | 3,408 | $125.00 | $167.50 | 4 | General Excavation, Inc. | VDOT |
| 22 JUL 2026 | C0000122360M01 | Fredericksburg | 3,430 | $225.00 | $251.00 | 6 | Martins Construction Corp. | VDOT |
| 22 JUL 2026 | C0000115403C01C | Richmond | 434 | $310.00 | $300.00 | 3 | MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | VDOT |
| 24 JUN 2026 | C0000115470C01 | Bristol | 2,351 | $176.80 | $185.65 | 2 | W-L Construction & Paving, Inc. | VDOT |
| 22 APR 2026 | C0000115529N01B | Hampton Roads | 557 | $215.00 | $329.26 | 3 | Allan Myers Va, Inc. | VDOT |
| 25 MAR 2026 | C0000122877C01 | Bristol | 826 | $180.38 | $181.00 | 3 | W-L Construction & Paving, Inc. | VDOT |
| 25 FEB 2026 | C0000119431C01B | Bristol | 435 | $254.90 | $277.45 | 2 | King General Contractors, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way