VDOT contract C0000119436C01 bid tabulation
Smart scale - turn lane improvements. Let by Virginia DOT on July 22, 2026, Wythe, Bristol. 4 bids received; low bid $2,673,541 by E. C. Pace Company, Inc..
- Owner
- Virginia DOT
- Letting
- 22 JUL 2026
- Pay items
- 102
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E. C. Pace Company, Inc. | $2,673,541 | Low |
| 2 | Jones Road & Bridge, Inc. | $2,799,579 | +5.0% |
| 3 | Ramirez Contracting, L.L.C. | $2,900,042 | +8.0% |
| 4 | W-L Construction & Paving, Inc. | $2,942,062 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E. C. Pace Company, Inc. | 2. Jones Road & Bridge, Inc. | 3. Ramirez Contracting, L.L.C. | 4. W-L Construction & Paving, Inc. |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Const rec docs SWM facility construction record documents for permanent rock check dams (105SP20-0002) | LS | 1 | $5,932.71 | $20,000 | $10,000 | $32,268 |
| 0001-0020 | Clearing and grubbing (301SD20-0001) | LS | 1 | $7,505.70 | $30,000 | $50,000 | $25,979 |
| 0001-0030 | Bedding matl. aggr. no. 57 (302SD20-0002) | TON | 1,809 | $57.40 | $65.00 | $65.00 | $104.55 |
| 0001-0040 | 15" conc. pipe (302SD20-0025) | LF | 8 | $198.23 | $250.00 | $350.00 | $1,106.91 |
| 0001-0050 | 18" conc. pipe (302SD20-0030) | LF | 417 | $231.00 | $275.00 | $285.00 | $437.10 |
| 0001-0060 | 18" storm sewer pipe (302SD20-0032) | LF | 470 | $178.10 | $210.00 | $250.00 | $216.33 |
| 0001-0070 | 18" end section ES-1 (302SD20-0201) | EACH | 1 | $2,594.79 | $2,000.00 | $2,500.00 | $2,004.74 |
| 0001-0080 | Drop inlet DI-3B,L=4' (302SD20-0311) | EACH | 2 | $7,443.92 | $9,000.00 | $7,000.00 | $8,136.55 |
| 0001-0090 | Drop inlet DI-3B,L=6' (302SD20-0312) | EACH | 3 | $8,085.24 | $9,000.00 | $7,000.00 | $8,581.32 |
| 0001-0100 | Drop inlet DI-3B,L=8' (302SD20-0313) | EACH | 4 | $9,067.60 | $10,000 | $7,000.00 | $9,571.54 |
| 0001-0110 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 1 | $9,614.65 | $11,000 | $8,000.00 | $9,729.21 |
| 0001-0120 | Drop inlet DI-5 (302SD20-0446) | EACH | 1 | $7,917.68 | $10,000 | $8,000.00 | $8,422.36 |
| 0001-0130 | Drop inlet DI-12C,L=6' (302SD20-0650) | EACH | 6 | $8,806.79 | $6,000.00 | $9,000.00 | $8,973.31 |
| 0001-0140 | Manhole MH-1 or 2 (302SD20-0662) | LF | 3.56 | $1,162.07 | $1,200.00 | $1,000.00 | $2,265.84 |
| 0001-0150 | Frame & cover IC-2 (302SD20-0664) | EACH | 1 | $767.40 | $1,500.00 | $2,500.00 | $851.78 |
| 0001-0160 | NS drainage low permeability liner geotextile (302SX20-0020) | SY | 1,587 | $11.83 | $30.00 | $40.00 | $11.45 |
| 0001-0170 | Regular excavation (303SD20-0001) | CY | 1,634 | $55.62 | $80.00 | $55.00 | $141.96 |
| 0001-0180 | Slope drain (303SD20-0018) | EACH | 1 | $2,069.37 | $3,000.00 | $1,000.00 | $3,762.11 |
| 0001-0190 | Temporary diversion dike (303SD20-0021) | LF | 208 | $13.28 | $5.00 | $6.00 | $15.34 |
| 0001-0200 | Check dam rock TY. I (303SD20-0022) | EACH | 8 | $324.18 | $1,000.00 | $600.00 | $634.54 |
| 0001-0210 | Check dam rock TY. II (303SD20-0023) | EACH | 23 | $223.54 | $900.00 | $650.00 | $478.87 |
| 0001-0220 | Check dam sediment retention roll 20" (303SD20-0025) | EACH | 84 | $140.21 | $350.00 | $25.00 | $471.67 |
| 0001-0230 | Siltation control excavation (303SD20-0029) | CY | 311 | $1.00 | $0.01 | $1.00 | $5.41 |
| 0001-0240 | Inlet protection type A (303SD20-0030) | EACH | 10 | $212.19 | $1,000.00 | $600.00 | $609.44 |
| 0001-0250 | Inlet protection type B (303SD20-0031) | EACH | 10 | $190.99 | $800.00 | $800.00 | $609.44 |
| 0001-0260 | Geotextile fabric (303SD20-0032) | SY | 3,560 | $3.51 | $5.00 | $9.00 | $8.91 |
| 0001-0270 | Temp. silt fence type A (303SD20-0034) | LF | 453 | $3.46 | $5.00 | $8.00 | $10.52 |
| 0001-0280 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 2,009 | $87.36 | $60.00 | $65.00 | $61.89 |
| 0001-0290 | Tack coat (310SD20-0001) | GAL | 937 | $8.90 | $7.00 | $7.00 | $6.00 |
| 0001-0300 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 1,288 | $267.20 | $200.00 | $182.00 | $180.15 |
| 0001-0310 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 1,092 | $235.61 | $190.00 | $160.00 | $158.85 |
| 0001-0320 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 2,072 | $2.74 | $6.00 | $5.00 | $6.39 |
| 0001-0330 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 20 | $224.07 | $100.00 | $90.00 | $109.25 |
| 0001-0340 | Paved ditch PG-2A (502SD20-0003) | SY | 311 | $143.75 | $220.00 | $225.00 | $201.60 |
| 0001-0350 | Curb, radial CG-2 (502SD20-0012) | LF | 57 | $81.27 | $100.00 | $105.00 | $166.88 |
| 0001-0360 | Median strip MS-1A (502SD20-0056) | SY | 298 | $368.08 | $225.00 | $225.00 | $205.55 |
| 0001-0370 | Concrete class A3 misc. (504SD20-0001) | CY | 11.13 | $1,728.03 | $2,500.00 | $3,000.00 | $2,270.28 |
| 0001-0380 | Guardrail GR-MGS1, 9' post (505SD20-0013) | LF | 37.50 | $111.23 | $88.00 | $87.00 | $84.75 |
| 0001-0390 | Radial guardrail GR- MGS1, 9' post (505SD20-0016) | LF | 37.50 | $118.66 | $96.00 | $95.00 | $90.40 |
| 0001-0400 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 2 | $3,707.95 | $3,000.00 | $3,500.00 | $2,938.00 |
| 0001-0410 | Guardrail GR-10 (505SD20-0040) | LF | 25 | $70.38 | $93.00 | $85.00 | $45.20 |
| 0001-0420 | Fence FE-W1 (507SD20-0001) | LF | 462 | $37.07 | $30.00 | $45.00 | $28.25 |
| 0001-0430 | Line brace unit FE-W1 or FE-W2 (507SD20-0003) | EACH | 4 | $2,224.77 | $2,000.00 | $1,900.00 | $1,695.00 |
| 0001-0440 | Corner brace unit FE-W1 or FE-W2 (507SD20-0004) | EACH | 6 | $2,224.77 | $2,000.00 | $1,900.00 | $1,695.00 |
| 0001-0450 | Gate FE-G 16' (507SD20-0023) | EACH | 2 | $2,669.72 | $2,000.00 | $2,200.00 | $2,034.00 |
| 0001-0460 | Obscuring roadway (508SD20-0001) | UNIT | 8 | $232.53 | $3,000.00 | $3,000.00 | $2,630.71 |
| 0001-0470 | Demo. of pavement flexible (508SD20-0004) | SY | 1,227 | $13.77 | $30.00 | $16.00 | $18.84 |
| 0001-0480 | Flowable backfill (509SD20-0001) | CY | 6 | $279.96 | $400.00 | $650.00 | $450.00 |
| 0001-0490 | Adjust exist. valve & box (510SD20-0038) | EACH | 1 | $895.04 | $2,000.00 | $1,000.00 | $927.43 |
| 0001-0500 | Adjust exist frame & cover (510SD20-0050) | EACH | 2 | $935.65 | $2,000.00 | $1,000.00 | $927.43 |
| 0001-0510 | Connect to exist. A/C pipe (510SX20-0009) | EACH | 2 | $6,334.55 | $3,500.00 | $5,000.00 | $5,650.00 |
| 0001-0520 | Remove exist. A/C pipe (510SX20-0010) | LF | 77 | $123.09 | $120.00 | $150.00 | $169.50 |
| 0001-0530 | NS remove exist. fence removal of existing fence (510SX20-0016) | LF | 376 | $4.19 | $12.00 | $10.00 | $8.24 |
| 0001-0540 | NS remove exist. 15" conc. pipe (510SX20-0039) | LF | 194 | $38.14 | $100.00 | $45.00 | $72.73 |
| 0001-0550 | NS remove exist. 24" conc. pipe (510SX20-0039) | LF | 151 | $39.43 | $100.00 | $45.00 | $88.98 |
| 0001-0560 | NS remove exist. drop inlet (510SX20-0040) | EACH | 1 | $3,434.68 | $2,000.00 | $1,800.00 | $2,597.89 |
| 0001-0570 | NS remove exist. end section (510SX20-0040) | EACH | 2 | $1,751.27 | $1,000.00 | $1,800.00 | $618.35 |
| 0001-0580 | NS remove exist. endwall (510SX20-0040) | EACH | 1 | $3,081.69 | $2,000.00 | $1,800.00 | $1,392.33 |
| 0001-0590 | Allaying dust (511SD20-0001) | HR | 60 | $1.00 | $20.00 | $28.00 | $28.78 |
| 0001-0600 | Aggregate material no. 25 or 26 (512SD20-0015) | TON | 106 | $73.26 | $60.00 | $70.00 | $70.08 |
| 0001-0610 | Port.changeable mess. sign (512SD20-0025) | HR | 6,720 | $8.15 | $8.00 | $3.00 | $14.33 |
| 0001-0620 | Maintenance of traffic (route 52, project wide) (512SP20-0002) | LS | 1 | $140,444 | $200,000 | $400,000 | $126,491 |
| 0001-0630 | Mobilization (513SD20-0001) | LS | 1 | $100,710 | $80,000 | $220,000 | $139,401 |
| 0001-0640 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 8,713 | $10.97 | $9.00 | $9.00 | $7.40 |
| 0001-0650 | Construction surveying constr. (517SD20-0001) | LS | 1 | $92,328 | $50,000 | $90,000 | $135,297 |
| 0001-0660 | 3/4" water service line (520SD20-0002) | LF | 111 | $37.54 | $120.00 | $50.00 | $56.50 |
| 0001-0670 | 6" DI water main (520SD20-0014) | LF | 13 | $329.34 | $500.00 | $400.00 | $452.00 |
| 0001-0680 | 8" DI water main (520SD20-0016) | LF | 76 | $408.13 | $500.00 | $400.00 | $452.00 |
| 0001-0690 | 12" DI water main (520SD20-0020) | LF | 442 | $457.11 | $500.00 | $365.00 | $412.45 |
| 0001-0700 | 6" gate valve & box (520SD20-0089) | EACH | 1 | $3,457.42 | $7,500.00 | $5,600.00 | $6,328.00 |
| 0001-0710 | 8" gate valve & box (520SD20-0090) | EACH | 1 | $7,233.24 | $9,000.00 | $7,000.00 | $7,910.00 |
| 0001-0720 | 12" gate valve & box (520SD20-0092) | EACH | 1 | $7,936.32 | $15,000 | $8,000.00 | $9,040.00 |
| 0001-0730 | Fire hydrant (520SD20-0162) | EACH | 1 | $7,537.14 | $10,000 | $8,000.00 | $9,040.00 |
| 0001-0740 | Topsoil class A (602SD20-0002) | CY | 226 | $73.42 | $90.00 | $60.00 | $127.50 |
| 0001-0750 | Topsoil class B (602SD20-0004) | CY | 226 | $158.19 | $135.00 | $60.00 | $143.07 |
| 0001-0760 | Temporary seed (603SD20-0002) | LB | 208 | $17.80 | $14.00 | $10.00 | $13.56 |
| 0001-0770 | Regular seed (603SD20-0003) | LB | 442 | $17.80 | $14.00 | $10.00 | $13.56 |
| 0001-0780 | Overseeding (603SD20-0004) | LB | 354 | $17.80 | $14.00 | $10.00 | $13.56 |
| 0001-0790 | Legume seed (603SD20-0005) | LB | 8 | $26.70 | $22.00 | $10.00 | $20.34 |
| 0001-0800 | Legume overseeding (603SD20-0006) | LB | 6 | $26.70 | $22.00 | $10.00 | $20.34 |
| 0001-0810 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 8,833 | $0.89 | $1.00 | $1.25 | $0.68 |
| 0001-0820 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 13,818 | $1.11 | $0.90 | $1.50 | $0.85 |
| 0001-0830 | Fertilizer nitrogen - N (603SD20-0014) | LB | 208 | $3.34 | $4.00 | $20.00 | $2.54 |
| 0001-0840 | Fertilizer phosphorous - P (603SD20-0015) | LB | 146 | $3.34 | $4.00 | $20.00 | $2.54 |
| 0001-0850 | Fertilizer potassium - K (603SD20-0016) | LB | 146 | $3.34 | $4.00 | $20.00 | $2.54 |
| 0001-0860 | Lime (603SD20-0017) | TON | 11.44 | $207.64 | $350.00 | $400.00 | $158.20 |
| 0001-0870 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 146 | $6.30 | $5.00 | $4.00 | $4.80 |
| 0001-0880 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 119 | $6.67 | $5.00 | $4.00 | $5.09 |
| 0001-0890 | Rolled erosion CTRL product EC-2 type 3 (606SD20-0003) | SY | 253 | $7.41 | $6.00 | $4.00 | $5.65 |
| 0001-0900 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 324 | $10.38 | $8.00 | $4.00 | $7.91 |
| 0001-0910 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 5 | $361.91 | $146.00 | $280.00 | $422.62 |
| 0001-0920 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 170 | $26.53 | $24.00 | $35.00 | $20.22 |
| 0001-0930 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 122 | $29.54 | $33.00 | $35.00 | $22.51 |
| 0001-0940 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 26 | $826.13 | $493.00 | $600.00 | $629.41 |
| 0001-0950 | Sign panel (701SD20-0001) | SF | 288 | $46.97 | $55.00 | $35.00 | $35.79 |
| 0001-0960 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 10,225 | $1.84 | $1.50 | $1.75 | $0.90 |
| 0001-0970 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 485 | $25.90 | $20.00 | $25.00 | $28.25 |
| 0001-0980 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 19 | $507.42 | $400.00 | $400.00 | $113.00 |
| 0001-0990 | PVMT MSG. mark. "only" TY B, CL II, 6' (704SD20-0036) | EACH | 5 | $592.95 | $460.00 | $550.00 | $565.00 |
| 0001-1000 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 7 | $761.32 | $560.00 | $600.00 | $423.75 |
| 0001-1010 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 21 | $40.06 | $2,970.00 | $35.00 | $113.00 |
| 0001-1020 | NS pavement marking U- turn symb, TY. B. CL. II (704SX20-0002) | EACH | 4 | $810.31 | $612.00 | $600.00 | $1,695.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of July 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.