Remove exist. A/C pipe, VDOT 510SX20-0010

Low bidders on VDOT contracts carried a median of $188.34 per LF for this item, over the 24 months to 28 OCT 2026, across 6 low bids. Half of all 17 bids fell between $120.00 and $300.00.

Owner
Virginia DOT
Item
510SX20-0010
Unit
LF
Data through
28 OCT 2026

VDOT prints this item as “REMOVE EXIST. A/C PIPE”.

VDOT has bid this work under more than one code: 45506 on lettings from 22 APR 2003 to 26 MAY 2021 (108 bids); 510SX20-0010 on lettings from 17 DEC 2025 to 22 JUL 2026 (17 bids). They are combined here into one trend.

$188.34Low bidder's median, per LF
$192.00Median of all bids, per LF
6Contracts in the window

By year of letting

Remove exist. A/C pipe, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200310n/a2$14.97
200444$31.5010$32.25
200522$52.006$42.00
200633$48.008$37.48
200822$41.786$41.78
201011$23.003$15.00
201121$17.255$35.00
201222$276.886$104.16
201366$50.0017$55.00
201411$12.973$30.00
201566$50.0016$52.50
201711$19.003$43.10
201844$63.5012$53.81
201922$249.524$249.52
202022$112.405$125.00
202111$135.001$135.00
202511$100.004$146.00
202655$253.6013$250.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Richmond13$41.0034$46.55
Fredericksburg7$33.5723$33.57
Bristol7$53.7522$76.88
Salem6$95.4018$105.32
Staunton6$65.0012$63.05
Northern Virginia3$55.009$55.00
Remove exist. A/C pipe, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (LF)Low bidsLow-bid median
5 to 7011$77.50
70 to 13611$50.00
136 to 33411$86.00
360 to 6,90811$31.50
Remove exist. A/C pipe, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Fielder'S Choice Enterprises, Inc.93 (33%)
DLB, Inc.52 (40%)
Jones Road & Bridge, Inc.52 (40%)
Branscome Inc.51 (20%)
Remove exist. A/C pipe, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000119436C01Bristol77$123.09$136.554E. C. Pace Company, Inc.VDOT
25 FEB 2026C0000119431C01BBristol120$253.60$276.802King General Contractors, Inc.VDOT
04 FEB 2026C0000119457C01Salem5$300.00$576.503MCC ACQUISITION, LC dba VIRGINIA-CAROLINAVDOT
04 FEB 2026C0000119451M01Salem136$29.15$70.003W. C. English, IncorporatedVDOT
04 FEB 2026C000115407C01BRichmond180$345.00$345.001J. R. Caskey, Inc.VDOT
17 DEC 2025C0000119429C01Bristol307$100.00$146.004Ramirez Contracting, L.L.C.VDOT
26 MAY 2021C0000109370M01Staunton20$135.00$135.001A & J Development and Excavation, Inc.VDOT
22 APR 2020C0000107061C01Salem70$104.79$125.003Kanawha Stone Company, Inc.VDOT
25 MAR 2020C0000018003C01Staunton135$120.00$125.002General Excavation, Inc.VDOT
05 SEP 20190000116195C01Northern Virginia70$325.00$325.001Martins Construction Corp.VDOT
24 JUL 2019C0000100921C01Hampton Roads189$174.04$174.043Branscome Inc.VDOT
19 DEC 2018C000104661C01Richmond1,265$41.00$41.003Shoosmith Construction, Inc.VDOT
22 AUG 2018C0000090018C01Richmond1,010$39.40$39.403J. L. Kent & Sons, Inc.VDOT
25 JUL 2018C000097225B14Salem258$135.00$105.853D. A. Brown, Inc.VDOT
28 MAR 2018C0000008753C01Salem193$86.00$86.003Kanawha Stone Company, Inc.VDOT
Latest VDOT contracts carrying Remove exist. A/C pipe

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy