VDOT contract C0000119457C01 bid tabulation
Smart scale - intersection improvements / lanes addition. Let by Virginia DOT on February 4, 2026, Henry, Salem. 3 bids received; low bid $997,354 by MCC ACQUISITION, LC dba VIRGINIA-CAROLINA.
- Owner
- Virginia DOT
- Letting
- 04 FEB 2026
- Pay items
- 85
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | $997,354 | Low |
| 2 | Allegheny Construction Company, Inc. | $1,147,604 | +15% |
| 3 | F & B Contractors, LTD. | $1,230,956 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | 2. Allegheny Construction Company, Inc. | 3. F & B Contractors, LTD. |
|---|---|---|---|---|---|---|
| 0001-0010 | Clearing and grubbing (301SD20-0001) | LS | 1 | $143,500 | $75,000 | $43,497 |
| 0001-0020 | 18" pipe (302SD20-0028) | LF | 51 | $135.00 | $190.00 | $162.30 |
| 0001-0030 | 18" storm sewer pipe (302SD20-0032) | LF | 67 | $148.00 | $240.00 | $162.10 |
| 0001-0040 | 24" storm sewer pipe (302SD20-0041) | LF | 118 | $276.00 | $250.00 | $202.40 |
| 0001-0050 | 18" end section ES-1 or 2 (302SD20-0200) | EACH | 1 | $2,400.00 | $850.00 | $1,223.50 |
| 0001-0060 | 24" end section ES-1 or 2 (302SD20-0204) | EACH | 1 | $2,550.00 | $1,100.00 | $1,529.20 |
| 0001-0070 | Drop inlet DI-3B,L=14' (302SD20-0316) | EACH | 1 | $9,750.00 | $13,500 | $12,883 |
| 0001-0080 | Drop inlet DI-3C,L=16' (302SD20-0334) | EACH | 1 | $10,150 | $13,500 | $13,422 |
| 0001-0090 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $9,500.00 | $11,000 | $11,411 |
| 0001-0100 | Regular excavation (303SD20-0001) | CY | 699 | $125.00 | $145.00 | $127.50 |
| 0001-0110 | Borrow excavation (303SD20-0007) | CY | 407 | $65.00 | $110.00 | $54.60 |
| 0001-0120 | Check dam sediment retention roll 18" (303SD20-0024) | EACH | 18 | $150.00 | $600.00 | $436.50 |
| 0001-0130 | Siltation control excavation (303SD20-0029) | CY | 136 | $1.00 | $0.10 | $57.40 |
| 0001-0140 | Inlet protection type A (303SD20-0030) | EACH | 1 | $550.00 | $700.00 | $370.00 |
| 0001-0150 | Inlet protection type B (303SD20-0031) | EACH | 2 | $550.00 | $700.00 | $400.00 |
| 0001-0160 | Geotextile fabric (303SD20-0032) | SY | 12 | $60.00 | $15.00 | $64.80 |
| 0001-0170 | Temp. silt fence type A (303SD20-0034) | LF | 600 | $7.00 | $5.00 | $6.80 |
| 0001-0180 | Geotextile subgrade stab. (305SD20-0009) | SY | 1,525 | $4.00 | $5.00 | $10.00 |
| 0001-0190 | Aggr. matl. no. 1 (308SD20-0001) | TON | 383 | $70.00 | $74.00 | $70.00 |
| 0001-0200 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 270 | $50.00 | $77.00 | $68.80 |
| 0001-0210 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 325 | $60.00 | $55.00 | $57.90 |
| 0001-0220 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 255 | $190.00 | $280.00 | $267.20 |
| 0001-0230 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 554 | $170.00 | $235.00 | $217.30 |
| 0001-0240 | Saw-cut asphalt concrete full depth sawcut (315SD20-0104) | LF | 1,550 | $10.00 | $8.00 | $8.40 |
| 0001-0250 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 3 | $95.00 | $200.00 | $372.90 |
| 0001-0260 | Dry riprap CL.I 26" (414SD20-0012) | TON | 30 | $95.00 | $145.00 | $116.40 |
| 0001-0270 | Median barrier MB-7D (502SD20-0036) | LF | 20 | $250.00 | $55.00 | $124.00 |
| 0001-0280 | Median strip MS-1 (502SD20-0053) | SY | 57 | $247.00 | $365.00 | $273.00 |
| 0001-0290 | NS median strip median strip modified MS-1 (502SX20-0012) | SY | 68 | $218.00 | $365.00 | $273.00 |
| 0001-0300 | Concrete class A3 misc. (504SD20-0001) | CY | 0.74 | $2,500.00 | $1,800.00 | $5,900.00 |
| 0001-0310 | Guardrail GR-MGS1 (505SD20-0011) | LF | 200 | $45.00 | $55.00 | $54.20 |
| 0001-0320 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 1 | $4,480.00 | $3,000.00 | $5,004.20 |
| 0001-0330 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 1 | $3,360.00 | $3,000.00 | $3,754.20 |
| 0001-0340 | Guardrail terminal GR-11 (505SD20-0029) | EACH | 1 | $4,480.00 | $3,000.00 | $5,004.20 |
| 0001-0350 | Remove existing guardrail (505SD20-0073) | LF | 180 | $11.25 | $20.00 | $15.20 |
| 0001-0360 | Demo. of pavement flexible (508SD20-0004) | SY | 325 | $18.00 | $32.00 | $55.80 |
| 0001-0370 | Adjust exist. air release valve box (510SD20-0044) | EACH | 1 | $750.00 | $2,600.00 | $3,004.20 |
| 0001-0380 | Adjust exist frame & cover (510SD20-0050) | EACH | 2 | $1,500.00 | $1,300.00 | $1,500.00 |
| 0001-0390 | Connect to exist. A/C pipe (510SX20-0009) | EACH | 2 | $3,225.00 | $3,000.00 | $6,004.20 |
| 0001-0400 | Remove exist. A/C pipe (510SX20-0010) | LF | 5 | $300.00 | $650.00 | $576.50 |
| 0001-0410 | Allaying dust (511SD20-0001) | HR | 150 | $1.00 | $1.00 | $65.00 |
| 0001-0420 | Type 3 barricade 4' (512SD20-0012) | EACH | 2 | $400.00 | $475.00 | $377.00 |
| 0001-0430 | Type 3 barricade 8' (512SD20-0013) | EACH | 5 | $550.00 | $500.00 | $475.80 |
| 0001-0440 | Temporary sign (512SD20-0014) | SF | 926 | $27.00 | $24.00 | $39.60 |
| 0001-0450 | Truck mounted attenuator (512SD20-0023) | HR | 560 | $15.00 | $35.00 | $75.00 |
| 0001-0460 | Group 2 channelizing devices (512SD20-0024) | DAY | 11,260 | $2.25 | $1.00 | $1.50 |
| 0001-0470 | Port.changeable mess. sign (512SD20-0025) | HR | 480 | $17.00 | $7.00 | $10.30 |
| 0001-0480 | Electronic arrow board (512SD20-0026) | HR | 560 | $12.00 | $6.00 | $5.90 |
| 0001-0490 | Warning light TY. B (512SD20-0029) | DAY | 240 | $10.00 | $2.00 | $5.00 |
| 0001-0500 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 768 | $8.50 | $8.00 | $3.90 |
| 0001-0510 | Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061) | LF | 464 | $16.00 | $16.00 | $7.70 |
| 0001-0520 | Temp. PVMT MRKG TY. D, CL. III, 24" (512SD20-0065) | LF | 26 | $25.00 | $24.00 | $37.70 |
| 0001-0530 | Mobilization (513SD20-0001) | LS | 1 | $47,500 | $85,000 | $91,529 |
| 0001-0540 | Field office TY.II (514SD20-0002) | MO | 6 | $4,000.00 | $4,000.00 | $3,690.80 |
| 0001-0550 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 518 | $12.00 | $35.00 | $39.30 |
| 0001-0560 | Flex pavement planing above 4" (515SD20-0006) | SY | 535 | $16.00 | $52.00 | $44.30 |
| 0001-0570 | NS demo. of BLDG. concrete column demo D-900 (516SX20-0008) | LS | 1 | $3,500.00 | $1.00 | $15,029 |
| 0001-0580 | NS demo. of BLDG. concrete column demo D-901 (516SX20-0008) | LS | 1 | $3,500.00 | $1.00 | $15,029 |
| 0001-0590 | Construction surveying constr. (517SD20-0001) | LS | 1 | $20,000 | $37,000 | $50,275 |
| 0001-0600 | 1" water service line (520SD20-0003) | LF | 48 | $110.00 | $75.00 | $64.20 |
| 0001-0610 | 6" DI water main (520SD20-0014) | LF | 281 | $150.00 | $215.00 | $364.20 |
| 0001-0620 | 6" gate valve & box (520SD20-0089) | EACH | 2 | $3,100.00 | $5,000.00 | $3,604.20 |
| 0001-0630 | Topsoil class B (602SD20-0004) | CY | 145 | $100.00 | $120.00 | $90.00 |
| 0001-0640 | Temporary seed (603SD20-0002) | LB | 108 | $18.00 | $21.00 | $24.20 |
| 0001-0650 | Regular seed (603SD20-0003) | LB | 113 | $20.00 | $24.00 | $25.50 |
| 0001-0660 | Overseeding (603SD20-0004) | LB | 90 | $20.00 | $6.00 | $25.50 |
| 0001-0670 | Hydraulic erosion control product type 1 (603SD20-0007) | SY | 1,210 | $1.05 | $0.85 | $1.80 |
| 0001-0680 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 2,710 | $1.50 | $1.40 | $2.10 |
| 0001-0690 | Fertilizer nitrogen - N (603SD20-0014) | LB | 36 | $4.50 | $3.00 | $6.70 |
| 0001-0700 | Fertilizer phosphorous - P (603SD20-0015) | LB | 25 | $4.50 | $3.00 | $6.70 |
| 0001-0710 | Fertilizer potassium - K (603SD20-0016) | LB | 25 | $4.50 | $3.00 | $6.70 |
| 0001-0720 | Lime (603SD20-0017) | TON | 1.98 | $600.00 | $250.00 | $290.00 |
| 0001-0730 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 378 | $3.00 | $3.50 | $10.10 |
| 0001-0740 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 1,440 | $6.25 | $6.50 | $14.80 |
| 0001-0750 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 8 | $250.00 | $450.00 | $473.00 |
| 0001-0760 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 6 | $450.00 | $200.00 | $191.70 |
| 0001-0770 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 195 | $40.00 | $24.00 | $26.70 |
| 0001-0780 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 10 | $525.00 | $700.00 | $719.20 |
| 0001-0790 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 3 | $750.00 | $1,000.00 | $963.00 |
| 0001-0800 | Sign panel (701SD20-0001) | SF | 78 | $40.00 | $35.00 | $36.40 |
| 0001-0810 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 1,322 | $8.75 | $8.00 | $8.30 |
| 0001-0820 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 495 | $9.00 | $8.30 | $12.20 |
| 0001-0830 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 40 | $32.00 | $30.00 | $57.20 |
| 0001-0840 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 4 | $520.00 | $500.00 | $563.50 |
| 0001-0850 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 2 | $900.00 | $885.00 | $1,126.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.