18" storm sewer pipe, VDOT 302SD20-0032

Low bidders on VDOT contracts carried a median of $210.00 per LF for this item, over the 24 months to 28 OCT 2026, across 28 low bids. Half of all 80 bids fell between $171.75 and $350.00.

Owner
Virginia DOT
Item
302SD20-0032
Unit
LF
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 1186 on lettings from 25 NOV 2009 to 27 OCT 2021 (508 bids); 302SD20-0032 on lettings from 19 NOV 2025 to 26 AUG 2026 (80 bids). They are combined here into one trend.

$210.00Low bidder's median, per LF
$230.53Median of all bids, per LF
28Contracts in the window

By year of letting

18" storm sewer pipe, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200922$31.776$33.44
20101112$50.2836$48.32
20111211$54.2035$54.79
20121515$65.0042$57.35
20131818$59.0052$61.00
20141717$60.0049$68.00
20152728$76.1576$76.14
20162019$62.0553$65.00
20171111$82.6331$91.50
201899$66.0527$80.00
20191212$112.4432$122.50
20201414$91.0038$102.31
20211011$145.3030$100.00
202555$231.9120$231.49
20262323$210.0060$230.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Bristol7$231.9121$231.91
Salem5$150.0016$200.00
Lynchburg5$165.0013$175.00
Culpeper3$302.0010$300.00
Richmond4$210.007$210.00
18" storm sewer pipe, VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
10 to 1327$250.00
142 to 2667$210.00
340 to 5477$165.00
619 to 1,1457$231.91
18" storm sewer pipe, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
General Excavation, Inc.1710 (59%)
Haymes Brothers, Inc.1410 (71%)
Fielder'S Choice Enterprises, Inc.228 (36%)
J. L. Kent & Sons, Inc.157 (47%)
Allan Myers Va, Inc.126 (50%)
Howard Brothers Contractor, Inc.85 (63%)
18" storm sewer pipe, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
26 AUG 2026C0000119687C01BRichmond169$210.00$205.002Gray and Sons Construction, Inc.VDOT
26 AUG 2026C0000124095M01Salem619$420.00$371.914Allegheny Construction Company, Inc.VDOT
26 AUG 2026C0000115512C01Hampton Roads15$1,025.00$867.473Allan Myers Va, Inc.VDOT
26 AUG 2026C0000129131C01BRichmond453$615.26$557.632Caton Construction Group, Inc.VDOT
22 JUL 2026C0000120697C01Salem1,028$110.00$200.003Crossroads Bridge IncVDOT
22 JUL 2026C0000111704C01Richmond517$140.00$140.001J. L. Kent & Sons, Inc.VDOT
22 JUL 2026C0000119436C01Bristol470$178.10$213.174E. C. Pace Company, Inc.VDOT
22 JUL 2026C0000120611C01Salem659$245.00$245.001Branch Civil, Inc.VDOT
22 JUL 2026C0000120710C01Lynchburg208$137.01$181.002Caton Construction Group, Inc.VDOT
24 JUN 2026C0000108810C01Staunton171$102.00$176.882A & J Development and Excavation, Inc.VDOT
24 JUN 2026C0000115470C01Bristol1,145$194.27$220.632W-L Construction & Paving, Inc.VDOT
27 MAY 2026C0000119206C01Culpeper340$302.00$287.506J. L. Kent & Sons, Inc.VDOT
27 MAY 2026C0000123889C01BFredericksburg53$1,100.00$1,100.003BRANSCOME OPERATING, LLC dba BRANSCOMEVDOT
22 APR 2026C0000118863C01Culpeper547$109.81$109.811Caton Construction Group, Inc.VDOT
22 APR 2026C0000119163C01Lynchburg770$350.00$227.122Allegheny Construction Company, Inc.VDOT
Latest VDOT contracts carrying 18" storm sewer pipe

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy