15" storm sewer pipe, VDOT 302SD20-0027

Low bidders on VDOT contracts carried a median of $201.00 per LF for this item, over the 24 months to 28 OCT 2026, across 33 low bids. Half of all 94 bids fell between $165.75 and $350.00.

Owner
Virginia DOT
Item
302SD20-0027
Unit
LF
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 1156 on lettings from 25 NOV 2009 to 27 OCT 2021 (675 bids); 302SD20-0027 on lettings from 22 OCT 2025 to 23 SEP 2026 (94 bids). They are combined here into one trend.

$201.00Low bidder's median, per LF
$231.12Median of all bids, per LF
33Contracts in the window

By year of letting

15" storm sewer pipe, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200933$34.009$34.00
20102223$54.6069$48.00
20111615$40.4047$50.00
20121616$50.6745$50.00
20132929$55.0084$56.51
20142525$56.5472$65.00
20153133$70.0086$75.00
20162726$72.5071$71.80
20171212$80.7434$98.07
20181313$78.4439$91.00
20191616$99.3543$110.00
20201717$98.5046$107.50
2021910$97.5029$95.00
202577$244.4824$247.24
20262626$193.0070$227.12

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Salem6$187.5021$200.00
Culpeper4$167.0014$275.00
Lynchburg5$150.0013$150.00
Fredericksburg3$250.0012$350.00
Bristol4$296.5011$210.00
Richmond5$229.2311$350.00
Hampton Roads4$667.618$667.61
15" storm sewer pipe, VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
10 to 488$279.00
49 to 2758$210.81
324 to 7768$236.85
1,096 to 2,9719$142.77
15" storm sewer pipe, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Fielder'S Choice Enterprises, Inc.4015 (38%)
Haymes Brothers, Inc.1714 (82%)
General Excavation, Inc.2713 (48%)
J. L. Kent & Sons, Inc.2011 (55%)
Howard Brothers Contractor, Inc.1810 (56%)
E. V. Williams, Inc.107 (70%)
15" storm sewer pipe, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
23 SEP 2026C0000119597C01BRichmond104$516.93$516.931Curtis Contracting, Inc.VDOT
23 SEP 2026C0000123290C01Richmond776$229.23$350.005Caton Construction Group, Inc.VDOT
26 AUG 2026C000119218C01BHampton Roads20$735.21$735.213BRANSCOME OPERATING, LLC dba BRANSCOMEVDOT
26 AUG 2026C0000115512C01Hampton Roads17$1,000.00$1,000.003Allan Myers Va, Inc.VDOT
26 AUG 2026C0000129131C01BRichmond1,239$523.00$511.502Caton Construction Group, Inc.VDOT
22 JUL 2026C0000119468M01Salem1,425$116.27$220.632E. C. Pace Company, Inc.VDOT
22 JUL 2026C0000111704C01Richmond565$177.50$177.501J. L. Kent & Sons, Inc.VDOT
22 JUL 2026C0000119641C02Staunton49$211.62$285.812G. B. Foltz Contracting, Inc.VDOT
22 JUL 2026C0000120611C01Salem2,274$201.00$201.001Branch Civil, Inc.VDOT
22 JUL 2026C0000120748C01Culpeper1,208$186.00$289.004General Excavation, Inc.VDOT
22 JUL 2026C0000120710C01Lynchburg386$182.51$181.252Caton Construction Group, Inc.VDOT
24 JUN 2026C0000108810C01Staunton2,971$89.00$136.882A & J Development and Excavation, Inc.VDOT
24 JUN 2026C0000119467C01Salem102$200.00$178.752Haymes Brothers, Inc.VDOT
27 MAY 2026C0000119206C01Culpeper125$148.00$260.006J. L. Kent & Sons, Inc.VDOT
27 MAY 2026C0000119458C01Salem1,224$133.25$166.626Branch Civil, Inc.VDOT
Latest VDOT contracts carrying 15" storm sewer pipe

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy