VDOT contract C0000120748C01 bid tabulation
Smart scale - roundabout and r-cut intersection. Let by Virginia DOT on July 22, 2026, Fauquier, Culpeper. 4 bids received; low bid $10,953,491 by General Excavation, Inc..
- Owner
- Virginia DOT
- Letting
- 22 JUL 2026
- Pay items
- 197
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | General Excavation, Inc. | $10,953,491 | Low |
| 2 | Shirley Contracting Company, LLC | $12,852,446 | +17% |
| 3 | William A. Hazel, Inc. | $12,965,979 | +18% |
| 4 | Sagres Construction Corporation | $12,999,113 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. General Excavation, Inc. | 2. Shirley Contracting Company, LLC | 3. William A. Hazel, Inc. | 4. Sagres Construction Corporation |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Const rec docs SWM facility 2 SWM facilities (105SP20-0002) | LS | 1 | $15,500 | $10,000 | $17,940 | $6,371.24 |
| 0001-0020 | Baseline progress schedule (108SP20-0001) | LS | 1 | $10,700 | $350,000 | $11,960 | $19,698 |
| 0001-0030 | Progress schedule updates (108SP20-0002) | EACH | 23 | $750.00 | $5,000.00 | $837.00 | $1,134.49 |
| 0001-0040 | Clearing and grubbing (301SD20-0001) | LS | 1 | $106,200 | $400,000 | $92,690 | $218,093 |
| 0001-0050 | Endwall EW-12 (302SD20-0013) | EACH | 23 | $1,325.00 | $1,500.00 | $1,130.00 | $1,456.95 |
| 0001-0060 | 12" pipe (302SD20-0018) | LF | 36 | $192.00 | $345.00 | $193.00 | $486.56 |
| 0001-0070 | 15" pipe (302SD20-0023) | LF | 165 | $165.00 | $345.00 | $175.00 | $476.67 |
| 0001-0080 | 15" storm sewer pipe (302SD20-0027) | LF | 1,208 | $186.00 | $345.00 | $233.00 | $354.24 |
| 0001-0090 | 18" pipe (302SD20-0028) | LF | 73 | $229.00 | $350.00 | $286.00 | $511.34 |
| 0001-0100 | 18" conc. pipe (302SD20-0030) | LF | 43 | $240.00 | $350.00 | $317.00 | $512.25 |
| 0001-0110 | 24" pipe (302SD20-0037) | LF | 40 | $455.00 | $500.00 | $648.00 | $535.66 |
| 0001-0120 | 24" conc. pipe (302SD20-0039) | LF | 38 | $250.00 | $500.00 | $367.00 | $535.65 |
| 0001-0130 | 24" storm sewer pipe (302SD20-0041) | LF | 123 | $340.00 | $500.00 | $435.00 | $535.67 |
| 0001-0140 | 30" pipe (302SD20-0047) | LF | 78 | $426.00 | $615.00 | $406.00 | $562.07 |
| 0001-0150 | 23" X 14" elliptical pipe (302SD20-0132) | LF | 18 | $270.00 | $675.00 | $439.00 | $540.27 |
| 0001-0160 | 12" end section ES-1 (302SD20-0197) | EACH | 2 | $2,100.00 | $1,935.00 | $1,940.00 | $2,972.32 |
| 0001-0170 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 2 | $2,100.00 | $1,935.00 | $2,310.00 | $2,696.99 |
| 0001-0180 | 15" end section ES-1 (302SD20-0199) | EACH | 8 | $2,100.00 | $1,935.00 | $2,310.00 | $2,696.96 |
| 0001-0190 | 18" end section ES-1 (302SD20-0201) | EACH | 5 | $2,300.00 | $2,100.00 | $2,770.00 | $3,252.65 |
| 0001-0200 | 24" end section ES-1 (302SD20-0205) | EACH | 5 | $2,600.00 | $2,500.00 | $3,840.00 | $3,503.09 |
| 0001-0210 | 30" end section ES-1 (302SD20-0209) | EACH | 2 | $3,200.00 | $3,225.00 | $3,920.00 | $3,903.80 |
| 0001-0220 | 23" X 14" end section ES-1A (302SD20-0221) | EACH | 2 | $3,250.00 | $3,365.00 | $4,170.00 | $4,274.92 |
| 0001-0230 | Drop inlet DI-3B,L=4' (302SD20-0311) | EACH | 3 | $8,500.00 | $15,000 | $10,560 | $9,636.60 |
| 0001-0240 | Drop inlet DI-3B,L=6' (302SD20-0312) | EACH | 5 | $8,350.00 | $15,000 | $11,520 | $9,425.64 |
| 0001-0250 | Drop inlet DI-3B,L=8' (302SD20-0313) | EACH | 1 | $8,050.00 | $15,000 | $11,350 | $9,020.95 |
| 0001-0260 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 1 | $9,350.00 | $15,000 | $12,070 | $9,866.42 |
| 0001-0270 | Drop inlet DI-3B,L=12' (302SD20-0315) | EACH | 1 | $9,450.00 | $15,000 | $12,770 | $9,866.42 |
| 0001-0280 | Drop inlet DI-3B,L=14' (302SD20-0316) | EACH | 1 | $9,500.00 | $15,000 | $13,760 | $9,866.42 |
| 0001-0290 | Drop inlet DI-5 (302SD20-0446) | EACH | 3 | $6,800.00 | $10,000 | $14,020 | $8,745.54 |
| 0001-0300 | Drop inlet DI-13 TY.I (302SD20-0655) | EACH | 1 | $8,400.00 | $10,000 | $11,880 | $8,933.24 |
| 0001-0310 | Drop inlet DI-13 TY.II (302SD20-0656) | EACH | 2 | $10,700 | $10,000 | $11,880 | $11,387 |
| 0001-0320 | Manhole MH-1 or 2 (302SD20-0662) | LF | 21.90 | $962.00 | $5,000.00 | $1,700.00 | $2,167.55 |
| 0001-0330 | Frame & cover MH-1 (302SD20-0663) | EACH | 4 | $1,700.00 | $1,980.00 | $908.00 | $1,571.68 |
| 0001-0340 | Stormwater man.drain.STR.SWM-1 (302SD20-0673) | LF | 12.60 | $2,150.00 | $2,915.00 | $2,600.00 | $2,614.80 |
| 0001-0350 | Regular excavation (303SD20-0001) | CY | 9,114 | $53.00 | $200.00 | $81.50 | $65.34 |
| 0001-0360 | Borrow excavation (303SD20-0007) | CY | 17,114 | $68.00 | $2.00 | $44.00 | $64.51 |
| 0001-0370 | Temporary diversion dike (303SD20-0021) | LF | 356 | $19.00 | $25.00 | $6.85 | $12.12 |
| 0001-0380 | Check dam rock TY. I (303SD20-0022) | EACH | 18 | $2,490.00 | $1,800.00 | $1,100.00 | $408.70 |
| 0001-0390 | Check dam rock TY. II (303SD20-0023) | EACH | 56 | $693.00 | $475.00 | $837.00 | $385.64 |
| 0001-0400 | Siltation control excavation (303SD20-0029) | CY | 3,104 | $15.00 | $5.00 | $1.00 | $24.95 |
| 0001-0410 | Inlet protection type A (303SD20-0030) | EACH | 6 | $494.00 | $500.00 | $484.00 | $167.91 |
| 0001-0420 | Inlet protection type B (303SD20-0031) | EACH | 16 | $398.00 | $1,100.00 | $215.00 | $456.45 |
| 0001-0430 | Geotextile fabric (303SD20-0032) | SY | 473 | $8.00 | $12.00 | $12.95 | $3.01 |
| 0001-0440 | Temp. silt fence type B (303SD20-0033) | LF | 872 | $20.00 | $30.00 | $8.55 | $9.06 |
| 0001-0450 | Temp. silt fence type A (303SD20-0034) | LF | 8,874 | $8.00 | $25.00 | $2.85 | $6.49 |
| 0001-0460 | Storm water man. basin excav. (303SD20-0036) | CY | 2,339 | $28.00 | $200.00 | $21.30 | $72.67 |
| 0001-0470 | Cem. stab. aggr. base. matl. TY. I no. 21A (307SD20-0004) | TON | 1,506 | $150.00 | $100.00 | $167.00 | $84.17 |
| 0001-0480 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 4,784 | $73.00 | $100.00 | $92.65 | $60.08 |
| 0001-0490 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 93 | $46.00 | $125.00 | $170.00 | $66.44 |
| 0001-0500 | Aggr. matl. no. 1 (309SD20-0001) | TON | 93 | $88.00 | $85.00 | $124.00 | $66.57 |
| 0001-0510 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 3,408 | $125.00 | $130.00 | $205.00 | $214.42 |
| 0001-0520 | Asphalt concrete TY. IM- 19.0A const (315SD20-0004) | TON | 64 | $105.00 | $125.00 | $352.00 | $199.10 |
| 0001-0530 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 5,498 | $106.00 | $125.00 | $187.00 | $199.10 |
| 0001-0540 | Asphalt concrete TY. SM- 9.5A const (315SD20-0007) | TON | 123 | $161.00 | $160.00 | $284.00 | $199.10 |
| 0001-0550 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 5,127 | $130.00 | $110.00 | $145.00 | $199.10 |
| 0001-0560 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 3,601 | $7.00 | $3.00 | $3.55 | $2.90 |
| 0001-0570 | Liquid asphalt coating (rumble strip) (315SD20-0016) | SY | 400 | $11.00 | $3.00 | $5.30 | $8.58 |
| 0001-0580 | Asph.conc.curb backup matl. const (315SD20-0018) | TON | 187 | $188.00 | $200.00 | $437.00 | $447.21 |
| 0001-0590 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 13,320 | $11.00 | $5.00 | $11.90 | $6.13 |
| 0001-0600 | Cont.reinf.hydr.conc. pave. 11" reinforced W/6X6-W4XW4 (316SD20-0013) | SY | 369 | $282.00 | $300.00 | $389.00 | $398.20 |
| 0001-0610 | Conc. CL. A4 mod. low shrink., SPR. struct. maint. (404SD20-0017) | CY | 40 | $1,030.00 | $2,500.00 | $935.00 | $2,657.64 |
| 0001-0620 | CR reinf. steel CL. I SPR. struct. maint. (406SD20-0011) | LB | 3,080 | $4.50 | $25.00 | $6.30 | $5.10 |
| 0001-0630 | NS rem. port.of EX.STR. concrete median (bridge) (413SX20-0005) | LS | 1 | $106,000 | $50,000 | $18,960 | $41,666 |
| 0001-0640 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 32 | $192.00 | $300.00 | $239.00 | $130.06 |
| 0001-0650 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 666 | $158.00 | $125.00 | $239.00 | $130.06 |
| 0001-0660 | Underdrain UD-4 (501SD20-0004) | LF | 9,915 | $31.50 | $55.00 | $35.05 | $48.39 |
| 0001-0670 | Crossdrain CD-1 (501SD20-0006) | LF | 117 | $50.00 | $200.00 | $49.70 | $58.79 |
| 0001-0680 | Outlet pipe (501SD20-0009) | LF | 623 | $33.00 | $55.00 | $39.30 | $36.18 |
| 0001-0690 | NS underdrain modified outlet pipe 6" (501SX20-0001) | LF | 70 | $45.00 | $90.00 | $47.20 | $36.17 |
| 0001-0700 | NS underdrain modified UD-4 6" (501SX20-0001) | LF | 2,263 | $36.00 | $60.00 | $42.90 | $58.78 |
| 0001-0710 | Paved ditch PG-2A (502SD20-0003) | SY | 18 | $144.00 | $200.00 | $108.00 | $292.02 |
| 0001-0720 | Curb, STD. CG-2 (502SD20-0011) | LF | 135 | $48.00 | $35.00 | $32.30 | $100.00 |
| 0001-0730 | Curb, radial CG-2 (502SD20-0012) | LF | 132 | $48.00 | $35.00 | $32.30 | $100.00 |
| 0001-0740 | Curb, STD. CG-3 (502SD20-0014) | LF | 205 | $48.00 | $40.00 | $34.70 | $100.00 |
| 0001-0750 | Curb, radial CG-3 (502SD20-0015) | LF | 559 | $48.00 | $35.00 | $34.70 | $100.00 |
| 0001-0760 | Curb, asphalt MC-3B (502SD20-0020) | LF | 230 | $81.00 | $90.00 | $87.30 | $89.44 |
| 0001-0770 | Comb. curb & gutter, STD. CG-7 (502SD20-0024) | LF | 848 | $53.00 | $45.00 | $51.45 | $110.00 |
| 0001-0780 | Comb. curb & gutter, rad. CG-7 (502SD20-0025) | LF | 614 | $53.00 | $45.00 | $51.45 | $110.00 |
| 0001-0790 | Median strip MS-1 (502SD20-0053) | SY | 383 | $141.00 | $150.00 | $144.00 | $147.03 |
| 0001-0800 | Median strip MS-1A (502SD20-0056) | SY | 1,098 | $200.00 | $200.00 | $206.00 | $210.74 |
| 0001-0810 | Median strip MS-2 (502SD20-0058) | LF | 1,120 | $86.00 | $85.00 | $77.75 | $200.00 |
| 0001-0820 | Concrete class A3 misc. (504SD20-0001) | CY | 12.60 | $1,027.00 | $3,500.00 | $2,200.00 | $1,451.83 |
| 0001-0830 | Guardrail GR-MGS1 (505SD20-0011) | LF | 1,718 | $37.00 | $35.00 | $35.90 | $36.76 |
| 0001-0840 | Guardrail GR-MGS1, 9' post (505SD20-0013) | LF | 166 | $45.00 | $50.00 | $53.80 | $55.14 |
| 0001-0850 | Radial guardrail GR-MGS1 (505SD20-0014) | LF | 72 | $39.00 | $40.00 | $41.85 | $42.88 |
| 0001-0860 | Radial guardrail GR- MGS1, 9' post (505SD20-0016) | LF | 200 | $45.00 | $55.00 | $59.80 | $61.26 |
| 0001-0870 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 5 | $4,280.00 | $3,500.00 | $3,830.00 | $3,920.76 |
| 0001-0880 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 7 | $1,605.00 | $2,200.00 | $2,270.00 | $2,327.95 |
| 0001-0890 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 5 | $1,605.00 | $1,500.00 | $1,440.00 | $1,470.29 |
| 0001-0900 | Fixed object attach. GR- foa-2 TY. I (505SD20-0053) | EACH | 2 | $3,210.00 | $3,200.00 | $4,240.00 | $3,553.19 |
| 0001-0910 | Fixed object attach. GR- foa-2 TY. II (505SD20-0054) | EACH | 2 | $803.00 | $525.00 | $1,370.00 | $612.62 |
| 0001-0920 | Cable barricade CR-1 (505SD20-0066) | EACH | 1 | $2,140.00 | $3,500.00 | $3,590.00 | $3,675.72 |
| 0001-0930 | Remove existing guardrail (505SD20-0073) | LF | 2,040 | $7.00 | $5.00 | $3.60 | $3.68 |
| 0001-0940 | Fence FE-W1 (507SD20-0001) | LF | 517 | $26.75 | $15.00 | $11.95 | $12.25 |
| 0001-0950 | Line brace unit FE-W1 or FE-W2 (507SD20-0003) | EACH | 2 | $695.50 | $500.00 | $419.00 | $428.84 |
| 0001-0960 | Corner brace unit FE-W1 or FE-W2 (507SD20-0004) | EACH | 2 | $856.00 | $500.00 | $419.00 | $428.84 |
| 0001-0970 | High visibility fence, 4 feet (507SD20-0027) | LF | 700 | $4.00 | $5.00 | $5.40 | $4.16 |
| 0001-0980 | Demo. of pavement flexible (508SD20-0004) | SY | 9,452 | $25.00 | $22.00 | $24.70 | $25.19 |
| 0001-0990 | Flowable backfill (509SD20-0001) | CY | 83 | $390.00 | $1,000.00 | $470.00 | $281.69 |
| 0001-1000 | NS remove exist. fence existing fence (510SX20-0016) | LF | 534 | $9.00 | $5.00 | $4.80 | $4.90 |
| 0001-1010 | NS remove exist. endwall NS remove exist. endwall (510SX20-0028) | EACH | 8 | $1,900.00 | $500.00 | $1,800.00 | $1,640.74 |
| 0001-1020 | NS remove exist. concrete median (roadway) (510SX20-0038) | SY | 660 | $51.00 | $60.00 | $160.00 | $18.22 |
| 0001-1030 | NS remove exist. pipe (510SX20-0039) | LF | 183 | $104.84 | $90.00 | $51.75 | $86.41 |
| 0001-1040 | Allaying dust (511SD20-0001) | HR | 1,095 | $120.00 | $30.00 | $200.00 | $60.00 |
| 0001-1050 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 2 | $26,250 | $40,000 | $40,490 | $25,975 |
| 0001-1060 | Type 3 barricade 8' (512SD20-0013) | EACH | 4 | $592.00 | $100.00 | $720.00 | $649.38 |
| 0001-1070 | Temporary sign (512SD20-0014) | SF | 4,091 | $49.00 | $25.00 | $62.00 | $55.14 |
| 0001-1080 | Truck mounted attenuator (512SD20-0023) | HR | 4,380 | $31.00 | $30.00 | $161.00 | $25.00 |
| 0001-1090 | Group 2 channelizing devices (512SD20-0024) | DAY | 155,338 | $1.65 | $0.50 | $1.50 | $1.00 |
| 0001-1100 | Port.changeable mess. sign (512SD20-0025) | HR | 9,408 | $15.50 | $15.00 | $8.30 | $10.00 |
| 0001-1110 | Electronic arrow board (512SD20-0026) | HR | 4,380 | $6.50 | $5.00 | $11.05 | $8.00 |
| 0001-1120 | Flagger service (512SD20-0027) | HR | 2,850 | $67.00 | $35.00 | $105.00 | $28.66 |
| 0001-1130 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 2,150 | $54.00 | $45.00 | $44.00 | $98.02 |
| 0001-1140 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 2,500 | $1.00 | $1.00 | $6.10 | $1.04 |
| 0001-1150 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 110,987 | $0.66 | $1.00 | $0.60 | $0.76 |
| 0001-1160 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 1,245 | $5.00 | $5.00 | $15.90 | $5.51 |
| 0001-1170 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 48 | $83.00 | $100.00 | $128.00 | $94.34 |
| 0001-1180 | NS temp. PVMT MRKG TY. D, CL III, 4" with contrast (512SX20-0005) | LF | 14,077 | $5.10 | $6.00 | $8.10 | $5.76 |
| 0001-1190 | Mobilization (513SD20-0001) | LS | 1 | $580,000 | $675,000 | $640,000 | $619,120 |
| 0001-1200 | NS field office type 1 modified (514SX20-0001) | MO | 23 | $7,800.00 | $5,000.00 | $6,430.00 | $5,689.60 |
| 0001-1210 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 21,146 | $3.50 | $5.00 | $6.90 | $7.05 |
| 0001-1220 | Construction surveying constr. (517SD20-0001) | LS | 1 | $282,000 | $416,955 | $195,250 | $42,271 |
| 0001-1230 | Storm water management low permeability liner (523SP20-0002) | SY | 1,695 | $35.00 | $35.00 | $42.35 | $82.15 |
| 0001-1240 | Topsoil class A 2" (602SD20-0001) | ACRE | 8.56 | $34,300 | $4,000.00 | $26,520 | $29,666 |
| 0001-1250 | NS topsoil SWM liner cover material (602SX20-0006) | CY | 288 | $130.00 | $50.00 | $227.00 | $95.07 |
| 0001-1260 | Temporary seed (603SD20-0002) | LB | 856 | $12.75 | $15.00 | $6.80 | $14.60 |
| 0001-1270 | Regular seed (603SD20-0003) | LB | 2,381 | $8.00 | $10.00 | $12.05 | $8.90 |
| 0001-1280 | Overseeding (603SD20-0004) | LB | 1,840 | $8.00 | $10.00 | $12.50 | $8.75 |
| 0001-1290 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 38,297 | $0.50 | $1.00 | $0.90 | $0.55 |
| 0001-1300 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 54,922 | $0.75 | $1.00 | $1.15 | $0.85 |
| 0001-1310 | Fertilizer nitrogen - N (603SD20-0014) | LB | 856 | $1.50 | $2.00 | $2.90 | $1.54 |
| 0001-1320 | Fertilizer phosphorous - P (603SD20-0015) | LB | 599 | $1.50 | $2.00 | $2.90 | $1.54 |
| 0001-1330 | Fertilizer potassium - K (603SD20-0016) | LB | 599 | $1.50 | $2.00 | $2.90 | $1.54 |
| 0001-1340 | Lime (603SD20-0017) | TON | 47 | $302.00 | $325.00 | $478.00 | $345.52 |
| 0001-1350 | NS landscape permanent vegetative cover (605SX20-0013) | LS | 1 | $66,670 | $5,500.00 | $58,968 | $183,786 |
| 0001-1360 | NS plant or tree red cedar (605SX20-0018) | EACH | 5 | $975.00 | $600.00 | $1,670.00 | $857.67 |
| 0001-1370 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 2,485 | $2.50 | $10.00 | $2.20 | $2.76 |
| 0001-1380 | Rolled erosion CTRL product EC-3 type 1 (606SD20-0005) | SY | 155 | $4.50 | $12.00 | $8.65 | $4.93 |
| 0001-1390 | Rolled erosion CTRL product EC-3 type 2 (606SD20-0006) | SY | 147 | $4.75 | $15.00 | $8.65 | $4.93 |
| 0001-1400 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 15.72 | $5.00 | $22.00 | $8.65 | $4.92 |
| 0001-1410 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 71 | $182.00 | $125.00 | $478.00 | $280.55 |
| 0001-1420 | Remove existing 2 post sign structure (700SD20-0004) | EACH | 7 | $1,338.00 | $1,300.00 | $1,500.00 | $592.27 |
| 0001-1430 | Remove existing 1 post sign panel (700SD20-0007) | EACH | 2 | $107.00 | $125.00 | $120.00 | $305.49 |
| 0001-1440 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 26 | $375.00 | $300.00 | $419.00 | $280.55 |
| 0001-1450 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 450 | $26.00 | $30.00 | $28.10 | $12.47 |
| 0001-1460 | Sign post STP-1, 2 3/16", 10 gauge (700SD20-0035) | LF | 115 | $37.00 | $40.00 | $40.95 | $12.47 |
| 0001-1470 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 395 | $37.00 | $40.00 | $41.25 | $13.72 |
| 0001-1480 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 22 | $669.00 | $750.00 | $748.00 | $1,109.72 |
| 0001-1490 | Conc. found. STP-1, TY. D (700SD20-0041) | EACH | 62 | $321.00 | $350.00 | $359.00 | $1,221.94 |
| 0001-1500 | Conc. found. O/H sign structure (700SD20-0056) | CY | 11 | $3,103.00 | $7,000.00 | $3,470.00 | $3,134.65 |
| 0001-1510 | 8 conductor cable (700SD20-0144) | LF | 3,725 | $2.70 | $3.00 | $3.05 | $3.76 |
| 0001-1520 | 8 conductor cable egc (700SD20-0148) | LF | 1,425 | $2.50 | $3.00 | $2.75 | $3.76 |
| 0001-1530 | Conc. found. LF-1, TY. A (700SD20-0149) | EACH | 11 | $1,926.00 | $2,000.00 | $2,210.00 | $4,443.61 |
| 0001-1540 | Lighting pole LP-2 type E (700SD20-0157) | EACH | 11 | $5,885.00 | $6,200.00 | $6,760.00 | $7,884.43 |
| 0001-1550 | Electrical service work pad (700SD20-0174) | EACH | 1 | $4,708.00 | $5,000.00 | $5,410.00 | $1,835.10 |
| 0001-1560 | Junction box JB-S2 (700SD20-0178) | EACH | 7 | $2,033.00 | $2,500.00 | $2,340.00 | $2,781.49 |
| 0001-1570 | Elect. ser. GRD. electrode 10' (700SD20-0181) | EACH | 4 | $214.00 | $300.00 | $246.00 | $219.36 |
| 0001-1580 | Bored conduit 3" (700SD20-0192) | LF | 250 | $51.00 | $55.00 | $58.10 | $56.41 |
| 0001-1590 | Conduit PVC 2" (700SD20-0194) | LF | 1,545 | $9.75 | $12.00 | $11.05 | $11.28 |
| 0001-1600 | Trench excavation eci-1 (700SD20-0197) | LF | 1,545 | $20.00 | $22.00 | $22.75 | $31.34 |
| 0001-1610 | Sign post STP-2, 4", 8 gauge (700SD20-0200) | LF | 170 | $83.00 | $80.00 | $92.70 | $81.05 |
| 0001-1620 | Concrete foundation STP-2, type A (700SD20-0201) | EACH | 3 | $4,173.00 | $4,000.00 | $4,660.00 | $2,478.79 |
| 0001-1630 | Concrete foundation STP-2, type G (700SD20-0207) | EACH | 3 | $5,350.00 | $5,500.00 | $5,980.00 | $2,544.88 |
| 0001-1640 | Concrete foundation STP-2, type H (700SD20-0208) | EACH | 2 | $5,564.00 | $5,500.00 | $6,220.00 | $2,865.33 |
| 0001-1650 | Concrete foundation STP-2, type I (700SD20-0209) | EACH | 1 | $5,671.00 | $5,500.00 | $6,340.00 | $3,224.42 |
| 0001-1660 | Concrete foundation STP-2, type N (700SD20-0214) | EACH | 1 | $5,778.00 | $6,000.00 | $6,460.00 | $3,588.52 |
| 0001-1670 | NS sign structure, overhead cant. overhead cant. (700SX20-0003) | EACH | 1 | $90,950 | $95,000 | $101,700 | $94,413 |
| 0001-1680 | NS lighting electrical service SE-5 (rdo) (700SX20-0014) | LS | 1 | $4,066.00 | $5,000.00 | $4,670.00 | $9,833.59 |
| 0001-1690 | NS traffic sign relocate existing 1 post ground mount sight structure ST-1 (700SX20-0021) | EACH | 1 | $375.00 | $400.00 | $419.00 | $3,037.39 |
| 0001-1700 | Sign panel (701SD20-0001) | SF | 1,568 | $52.50 | $55.00 | $58.60 | $49.88 |
| 0001-1710 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 18,100 | $1.00 | $1.50 | $1.90 | $1.08 |
| 0001-1720 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 1,400 | $2.30 | $3.00 | $2.20 | $2.57 |
| 0001-1730 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 300 | $3.25 | $5.00 | $5.95 | $3.68 |
| 0001-1740 | Type B class I PVMT line MRKG 12" (704SD20-0009) | LF | 300 | $5.00 | $6.00 | $6.60 | $5.39 |
| 0001-1750 | Type B class I PVMT line MRKG 24" (704SD20-0010) | LF | 200 | $9.00 | $10.00 | $22.75 | $10.29 |
| 0001-1760 | Type B class VI contrast PVMT line MRKG 4" (704SD20-0030) | LF | 2,000 | $7.00 | $8.00 | $15.55 | $7.96 |
| 0001-1770 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 170 | $51.00 | $70.00 | $65.20 | $57.59 |
| 0001-1780 | PVMT MSG. mark. "only" TY B, CL II, 6' (704SD20-0036) | EACH | 3 | $642.00 | $700.00 | $621.00 | $735.14 |
| 0001-1790 | PVMT symb MRKG thru arrow TY B, CL II (704SD20-0045) | EACH | 1 | $241.00 | $275.00 | $468.00 | $275.68 |
| 0001-1800 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 13 | $241.00 | $275.00 | $451.00 | $275.68 |
| 0001-1810 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 1 | $402.00 | $450.00 | $789.00 | $459.46 |
| 0001-1820 | Symb MRKG fish hook, LFT TY B CL II (704SD20-0066) | EACH | 2 | $1,284.00 | $1,400.00 | $1,230.00 | $1,470.29 |
| 0001-1830 | Sym MRKG fish hook thru/RGHT TY B CL II (704SD20-0075) | EACH | 2 | $1,284.00 | $1,400.00 | $1,230.00 | $1,470.29 |
| 0001-1840 | PVMT symb MRKG yield 2' X 3' TY A (704SD20-0085) | EACH | 68 | $83.00 | $100.00 | $71.80 | $94.34 |
| 0001-1850 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 19 | $83.00 | $100.00 | $41.50 | $94.34 |
| 0001-1860 | PVMT MSG. mark. “only” TY A, 8’ (704SD20-0106) | EACH | 19 | $642.00 | $700.00 | $316.00 | $735.14 |
| 0001-1870 | Type B class VI contrast PVMT line MRKG 8" (704SD20-0125) | LF | 200 | $12.00 | $13.00 | $18.00 | $13.48 |
| 0001-1880 | NS pavement marking PVMT. MSG. mark. "west" TY. B, CL. II (704SX20-0002) | EACH | 1 | $535.00 | $600.00 | $1,140.00 | $612.62 |
| 0001-1890 | NS pavement marking PVMT. MSG. mark. "yield" TY. A, 8" (704SX20-0002) | EACH | 12 | $669.00 | $700.00 | $299.00 | $765.77 |
| 0001-1900 | NS pavement marking PVMT. MSG. mark. shield TY. B, CL II (704SX20-0002) | EACH | 1 | $2,675.00 | $3,000.00 | $3,250.00 | $3,063.10 |
| 0001-1910 | NS pavement marking PVMT. symb. MRKG. SI turn arr. U-turn arr. U-turn TY. B, CL II (704SX20-0002) | EACH | 3 | $375.00 | $400.00 | $2,100.00 | $428.83 |
| 0001-1920 | NS PVMT MRKG fish hook THR TY B, CL II (704SX20-0004) | EACH | 4 | $1,284.00 | $1,400.00 | $1,230.00 | $1,470.29 |
| 0001-1930 | NS PVMT MRKG PVMT. symb MRKG fish hook, thru TY A (704SX20-0004) | EACH | 4 | $1,284.00 | $1,400.00 | $304.00 | $1,470.29 |
| 0001-1940 | NS pave. message marking PVMT. MSG. mark. "to" TY. B, CL II (704SX20-0005) | EACH | 1 | $268.00 | $300.00 | $3,870.00 | $306.31 |
| 0001-1950 | NS pave. message marking PVMT. MSG. mark. "yield" TY. B, CL II (704SX20-0005) | EACH | 10 | $535.00 | $600.00 | $1,360.00 | $612.62 |
| 0001-1960 | Control center CCW-1 type C (705SD20-0003) | EACH | 1 | $18,190 | $18,000 | $20,900 | $23,553 |
| 0001-1970 | NS luminaire 133W LED pole-mount (705SX20-0001) | EACH | 11 | $1,070.00 | $1,100.00 | $1,230.00 | $1,323.68 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of July 22, 2026. Compiled by Mirage Metrics.