NS underdrain modified outlet pipe 6", VDOT 501SX20-0001

Low bidders on VDOT contracts carried a median of $45.00 per LF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 4 bids fell between $42.79 and $57.90.

Owner
Virginia DOT
Item
501SX20-0001
Unit
LF
Data through
28 OCT 2026

VDOT prints this item as “NS UNDERDRAIN MODIFIED OUTLET PIPE 6"”.

VDOT has bid this work under more than one code: 598 on lettings from 23 JUL 2002 to 15 DEC 2021 (233 bids); 501SX20-0001 on lettings from 22 JUL 2026 to 22 JUL 2026 (4 bids). They are combined here into one trend.

$45.00Low bidder's median, per LF
$46.10Median of all bids, per LF
1Contracts in the window

By year of letting

NS underdrain modified outlet pipe 6", VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200244$12.0012$11.50
200311$7.003$7.00
200433$12.007$12.00
200511$15.003$15.00
200666$16.5018$15.00
200722$12.404$12.40
200822$10.726$14.25
200911$6.003$8.71
201069$12.0025$13.17
201111$35.003$23.06
201222$10.886$10.50
201345$13.3015$13.00
201488$14.0022$14.62
201566$11.5020$13.15
201644$18.156$17.04
201788$25.0019$18.00
201856$15.1317$17.00
201934$48.5010$42.75
202047$25.0019$24.37
202122$14.824$14.82
202611$45.004$46.10

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northern Virginia22$12.0062$12.65
Staunton18$12.5044$12.77
Richmond13$11.7133$12.00
Salem11$25.0027$18.00
Bristol7$14.1220$18.54
Hampton Roads5$35.0015$23.06
Fredericksburg3$45.0012$35.00
Culpeper3$25.0010$40.59
NS underdrain modified outlet pipe 6", VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (LF)Low bidsLow-bid median
4 to 10020$35.00
102 to 44221$14.12
460 to 1,13521$11.71
1,155 to 82,84321$10.80
NS underdrain modified outlet pipe 6", VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Branscome Inc.94 (44%)
W. C. English, Incorporated74 (57%)
General Excavation, Inc.113 (27%)
Fort Myer Construction Corporation63 (50%)
Shirley Contracting Company, LLC82 (25%)
Allan Myers Va, Inc.82 (25%)
NS underdrain modified outlet pipe 6", VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000120748C01Culpeper70$45.00$46.104General Excavation, Inc.VDOT
15 DEC 2021C0000119781N01Staunton10$10.00$7.502North Construction, Inc.VDOT
28 APR 2021C0000116165N01Bristol920$19.64$22.322W-L Construction & Paving, Inc.VDOT
16 DEC 2020C0000104946C01Lynchburg506$20.00$20.003Haymes Brothers, Inc.VDOT
18 NOV 2020C0000109419C01Bristol40$42.97$28.863Phillips Construction, LLC of Ky(Use In Va By:Phillips ConstVDOT
18 NOV 2020C0000109419C01Bristol364$10.61$24.373Phillips Construction, LLC of Ky(Use In Va By:Phillips ConstVDOT
18 NOV 2020C0000109419C01Bristol2,813$7.09$22.223Phillips Construction, LLC of Ky(Use In Va By:Phillips ConstVDOT
23 SEP 2020C0000109321C01Richmond19.50$200.00$112.072Allan Myers Va, Inc.VDOT
23 SEP 2020C0000109321C01Richmond172$40.00$32.072Allan Myers Va, Inc.VDOT
25 MAR 2020CM420PM1115256Richmond570$25.00$25.003Allan Myers Va, Inc.VDOT
18 DEC 2019C0000108906C01Salem265$43.50$34.752Branch Civil, Inc.VDOT
18 DEC 2019C0000108906C01Salem38$53.50$47.752Branch Civil, Inc.VDOT
24 APR 2019C0000109549C01Culpeper53$21.00$21.003Tavares Concrete Co., Inc.VDOT
27 FEB 2019CM419PMC113546Richmond30$100.00$195.003Colony Construction, Inc.VDOT
19 DEC 2018C0000093077B35Hampton Roads1,100$7.90$10.003Corman Kokosing Construction CompanyVDOT
Latest VDOT contracts carrying NS underdrain modified outlet pipe 6"

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy