Underdrain UD-2, VDOT 501SD20-0002
Low bidders on VDOT contracts carried a median of $55.00 per LF for this item, over the 24 months to 28 OCT 2026, across 8 low bids. Half of all 17 bids fell between $44.33 and $70.00.
- Owner
- Virginia DOT
- Item
- 501SD20-0002
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “UNDERDRAIN UD-2”.
VDOT has bid this work under more than one code: 585 on lettings from 23 APR 2002 to 17 NOV 2021 (109 bids); 501SD20-0002 on lettings from 17 DEC 2025 to 22 JUL 2026 (17 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 2 | 2 | $10.25 | 6 | $13.25 |
| 2003 | 2 | 1 | $14.55 | 4 | $12.00 |
| 2004 | 2 | 2 | $18.50 | 6 | $20.50 |
| 2005 | 1 | 1 | $20.00 | 2 | $22.60 |
| 2007 | 2 | 2 | $26.02 | 6 | $20.00 |
| 2008 | 4 | 4 | $17.75 | 12 | $22.60 |
| 2009 | 3 | 3 | $19.00 | 9 | $19.00 |
| 2010 | 1 | 1 | $28.00 | 3 | $28.00 |
| 2011 | 1 | 1 | $35.00 | 3 | $30.00 |
| 2013 | 2 | 2 | $28.98 | 6 | $18.00 |
| 2014 | 4 | 4 | $24.67 | 9 | $32.00 |
| 2015 | 3 | 3 | $33.81 | 9 | $30.00 |
| 2016 | 2 | 1 | $43.72 | 3 | $35.00 |
| 2018 | 1 | 1 | $62.00 | 3 | $25.50 |
| 2019 | 3 | 3 | $30.15 | 8 | $29.00 |
| 2020 | 1 | 1 | $38.00 | 2 | $26.84 |
| 2021 | 6 | 6 | $33.19 | 18 | $36.92 |
| 2025 | 2 | 2 | $60.00 | 6 | $60.00 |
| 2026 | 6 | 6 | $55.00 | 11 | $50.00 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Branch Highways, Inc. | 5 | 3 (60%) |
| Martin and Gass, Incorporated | 5 | 3 (60%) |
| J. L. Kent & Sons, Inc. | 5 | 2 (40%) |
| Shirley Contracting Company, LLC | 5 | 1 (20%) |
| General Excavation, Inc. | 7 | 0 (0%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000111704C01 | Richmond | 611 | $88.60 | $88.60 | 1 | J. L. Kent & Sons, Inc. | VDOT |
| 22 JUL 2026 | C0000115403C01C | Richmond | 264 | $72.00 | $69.00 | 3 | MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | VDOT |
| 24 JUN 2026 | C0000108810C01 | Staunton | 7,645 | $45.00 | $36.75 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 24 JUN 2026 | C0000115470C01 | Bristol | 577 | $35.97 | $42.98 | 2 | W-L Construction & Paving, Inc. | VDOT |
| 22 APR 2026 | C0000118863C01 | Culpeper | 126 | $50.00 | $50.00 | 1 | Caton Construction Group, Inc. | VDOT |
| 22 APR 2026 | C0000119167C01 | Lynchburg | 180 | $60.00 | $32.50 | 2 | Caton Construction Group, Inc. | VDOT |
| 17 DEC 2025 | C0000119442C01 | Bristol | 118 | $70.00 | $59.70 | 2 | Jones Road & Bridge, Inc. | VDOT |
| 17 DEC 2025 | C0000119429C01 | Bristol | 145 | $50.00 | $62.50 | 4 | Ramirez Contracting, L.L.C. | VDOT |
| 17 NOV 2021 | C0000106670C01 | Fredericksburg | 4,681 | $22.20 | $30.00 | 3 | J. L. Kent & Sons, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 1,093 | $47.00 | $44.50 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 23 JUN 2021 | C0000107081C01 | Culpeper | 72 | $150.00 | $63.00 | 3 | J. L. Kent & Sons, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 172 | $41.38 | $27.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C000106197C01 | Richmond | 270 | $25.00 | $32.47 | 3 | Jireh Construction Company, Inc. | VDOT |
| 20 JAN 2021 | C0000109481C01 | Hampton Roads | 1,472 | $15.12 | $23.37 | 3 | Henry S. Branscome, L.L.C. | VDOT |
| 23 SEP 2020 | C0000109321C01 | Richmond | 332 | $38.00 | $26.84 | 2 | Allan Myers Va, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.