VDOT contract C0000119442C01 bid tabulation
Smart scale - roundabout. Let by Virginia DOT on December 17, 2025, Washington, Bristol. 2 bids received; low bid $4,142,277 by Jones Road & Bridge, Inc..
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 128
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jones Road & Bridge, Inc. | $4,142,277 | Low |
| 2 | King General Contractors, Inc. | $4,511,939 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jones Road & Bridge, Inc. | 2. King General Contractors, Inc. |
|---|---|---|---|---|---|
| 0001-0010 | NS const rec docs SWM facility as-built (105SP20-0002) | LS | 1 | $11,625 | $16,039 |
| 0001-0020 | Clearing and grubbing (301SD20-0001) | LS | 1 | $99,000 | $92,534 |
| 0001-0030 | Bedding matl.aggr.no. 25 or 26 (302SD20-0001) | TON | 28.20 | $80.00 | $80.20 |
| 0001-0040 | Bedding matl. aggr. no. 57 (302SD20-0002) | TON | 100 | $82.00 | $86.60 |
| 0001-0050 | 18" conc. pipe (302SD20-0030) | LF | 209 | $256.59 | $114.70 |
| 0001-0060 | 18" storm sewer pipe (302SD20-0032) | LF | 767 | $231.91 | $114.70 |
| 0001-0070 | 72" conc. pipe (302SD20-0093) | LF | 76 | $1,380.56 | $957.40 |
| 0001-0080 | 18" end section ES-1 or 2 (302SD20-0200) | EACH | 1 | $1,336.74 | $1,473.10 |
| 0001-0090 | 18" end section ES-1 (302SD20-0201) | EACH | 1 | $2,048.25 | $1,473.10 |
| 0001-0100 | Drop inlet DI-2B,L=10' (302SD20-0244) | EACH | 1 | $9,479.80 | $9,824.70 |
| 0001-0110 | Drop inlet DI-3B,L=4' (302SD20-0311) | EACH | 1 | $8,802.72 | $8,012.20 |
| 0001-0120 | Drop inlet DI-3B,L=6' (302SD20-0312) | EACH | 3 | $8,312.72 | $7,579.20 |
| 0001-0130 | Drop inlet DI-3B,L=8' (302SD20-0313) | EACH | 4 | $9,056.33 | $8,220.80 |
| 0001-0140 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 5 | $9,576.36 | $9,902.40 |
| 0001-0150 | Drop inlet DI-3C,L=6' (302SD20-0329) | EACH | 1 | $8,938.29 | $8,128.20 |
| 0001-0160 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $11,262 | $12,621 |
| 0001-0170 | Manhole MH-1 or 2 (302SD20-0662) | LF | 30.40 | $1,200.00 | $1,603.90 |
| 0001-0180 | Frame & cover MH-1 (302SD20-0663) | EACH | 4 | $1,187.17 | $1,279.40 |
| 0001-0190 | NS manhole special design precast (302SX20-0027) | LF | 16.10 | $3,200.00 | $6,681.00 |
| 0001-0200 | Regular excavation (303SD20-0001) | CY | 4,399 | $55.00 | $55.50 |
| 0001-0210 | Borrow excavation (303SD20-0007) | CY | 3,678 | $58.00 | $64.20 |
| 0001-0220 | Minor STR. excav. pipe culvert (303SD20-0016) | CY | 281.50 | $70.00 | $55.50 |
| 0001-0230 | Slope drain (303SD20-0018) | EACH | 3 | $2,500.00 | $1,295.50 |
| 0001-0240 | Temporary diversion dike (303SD20-0021) | LF | 672 | $6.00 | $185.10 |
| 0001-0250 | Check dam rock TY. II (303SD20-0023) | EACH | 30 | $606.65 | $925.30 |
| 0001-0260 | Check dam sediment retention roll 18" (303SD20-0024) | EACH | 10 | $404.43 | $987.00 |
| 0001-0270 | Siltation control excavation (303SD20-0029) | CY | 944 | $0.03 | $2.50 |
| 0001-0280 | Inlet protection type A (303SD20-0030) | EACH | 6 | $647.10 | $789.60 |
| 0001-0290 | Inlet protection type B (303SD20-0031) | EACH | 17 | $622.83 | $826.60 |
| 0001-0300 | Temp. silt fence type B (303SD20-0033) | LF | 1,155 | $10.37 | $13.60 |
| 0001-0310 | Temp. silt fence type A (303SD20-0034) | LF | 2,810 | $8.29 | $8.00 |
| 0001-0320 | Geotextile subgrade stab. (305SD20-0009) | SY | 240 | $9.09 | $7.50 |
| 0001-0330 | Aggr. matl. no. 1 (305SD20-0010) | TON | 833 | $78.00 | $55.50 |
| 0001-0340 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 2,495 | $85.00 | $49.40 |
| 0001-0350 | Tack coat (310SD20-0001) | GAL | 113 | $17.89 | $19.60 |
| 0001-0360 | Asphalt concrete TY. SM- 12.5A const (315SD20-0001) | TON | 491 | $239.64 | $269.20 |
| 0001-0370 | Asphalt concrete TY. IM- 19.0A const (315SD20-0004) | TON | 411 | $248.66 | $288.40 |
| 0001-0380 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 548 | $233.28 | $272.50 |
| 0001-0390 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 529 | $5.96 | $6.20 |
| 0001-0400 | NS hydraulic cem. conc. 7" concrete class A4 (truck apron) integrally colored (316SX20-0009) | SY | 286 | $2,000.00 | $382.50 |
| 0001-0410 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 24.30 | $98.20 | $70.40 |
| 0001-0420 | Underdrain UD-2 (501SD20-0002) | LF | 118 | $70.00 | $49.40 |
| 0001-0430 | Underdrain UD-4 (501SD20-0004) | LF | 575 | $65.00 | $45.70 |
| 0001-0440 | Outlet pipe (501SD20-0009) | LF | 40 | $75.00 | $49.35 |
| 0001-0450 | Paved ditch PG-2A (502SD20-0003) | SY | 107.50 | $180.00 | $166.56 |
| 0001-0460 | Curb, STD. CG-2 (502SD20-0011) | LF | 194 | $90.00 | $86.37 |
| 0001-0470 | Curb, radial CG-2 (502SD20-0012) | LF | 529 | $90.00 | $80.20 |
| 0001-0480 | Curb, STD. CG-3 (502SD20-0014) | LF | 56 | $90.00 | $106.11 |
| 0001-0490 | Curb, radial CG-3 (502SD20-0015) | LF | 18 | $90.00 | $167.80 |
| 0001-0500 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 720 | $93.00 | $90.68 |
| 0001-0510 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 925 | $93.00 | $91.92 |
| 0001-0520 | Entrance gutter CG-9D (502SD20-0029) | SY | 28 | $250.00 | $315.85 |
| 0001-0530 | Median strip MS-1 (502SD20-0053) | SY | 152 | $190.00 | $220.85 |
| 0001-0540 | NS comb. curb & gutter modified (502SX20-0003) | LF | 97 | $95.00 | $108.57 |
| 0001-0550 | NS curb modified CG-3 radial (502SX20-0007) | LF | 214 | $90.00 | $74.03 |
| 0001-0560 | NS comb. curb & gutter modified CG-7 radial (502SX20-0008) | LF | 193 | $95.84 | $99.94 |
| 0001-0570 | NS saw cut H.C.C. items concrete (502SX20-0010) | LF | 25 | $11.92 | $74.03 |
| 0001-0580 | Concrete class A3 misc. (504SD20-0001) | CY | 1.50 | $3,000.00 | $1,048.72 |
| 0001-0590 | CG-12 detectable warning surface (504SD20-0002) | SY | 21 | $1,500.00 | $1,147.43 |
| 0001-0600 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 694 | $115.00 | $199.57 |
| 0001-0610 | Guardrail GR-MGS1 (505SD20-0011) | LF | 600 | $42.00 | $36.40 |
| 0001-0620 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 3 | $4,800.00 | $6,292.34 |
| 0001-0630 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 1 | $1,800.00 | $4,318.27 |
| 0001-0640 | Remove existing guardrail (505SD20-0073) | LF | 798 | $12.00 | $23.44 |
| 0001-0650 | Retaining wall RW-3 (506SD20-0002) | CY | 85 | $1,709.15 | $2,652.65 |
| 0001-0660 | Retaining wall excavation (506SD20-0007) | CY | 300 | $49.66 | $86.37 |
| 0001-0670 | Obscuring roadway (508SD20-0001) | UNIT | 7 | $2,979.43 | $5,798.82 |
| 0001-0680 | Demo. of pavement rigid (508SD20-0003) | SY | 110 | $39.73 | $172.73 |
| 0001-0690 | Demo. of pavement flexible (508SD20-0004) | SY | 2,935 | $29.79 | $86.37 |
| 0001-0700 | Flowable backfill (509SD20-0001) | CY | 5 | $663.92 | $678.59 |
| 0001-0710 | NS adjust exist. drop inlet (DI) (510SX20-0033) | EACH | 1 | $2,645.51 | $7,402.75 |
| 0001-0720 | NS remove exist. electrical board (510SX20-0040) | EACH | 1 | $1,986.29 | $12,338 |
| 0001-0730 | Allaying dust (511SD20-0001) | HR | 100 | $29.79 | $37.01 |
| 0001-0740 | Type 3 barricade 4' (512SD20-0012) | EACH | 9 | $600.00 | $678.59 |
| 0001-0750 | Type 3 barricade 8' (512SD20-0013) | EACH | 7 | $800.00 | $801.96 |
| 0001-0760 | Temporary sign (512SD20-0014) | SF | 1,128 | $29.93 | $61.69 |
| 0001-0770 | Group 2 channelizing devices (512SD20-0024) | DAY | 6,200 | $1.32 | $1.85 |
| 0001-0780 | Port.changeable mess. sign (512SD20-0025) | HR | 1,680 | $6.74 | $2.47 |
| 0001-0790 | Flagger service (512SD20-0027) | HR | 1,320 | $36.40 | $37.01 |
| 0001-0800 | Warning light TY. B (512SD20-0029) | DAY | 896 | $0.47 | $1.85 |
| 0001-0810 | Warning light TY. C (512SD20-0030) | DAY | 161 | $0.67 | $13.57 |
| 0001-0820 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 60 | $67.41 | $80.20 |
| 0001-0830 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 1,723 | $2.16 | $8.02 |
| 0001-0840 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 2,581 | $2.50 | $3.70 |
| 0001-0850 | Temp. PVMT MRKG TY. A, 6" (512SD20-0047) | LF | 2,692 | $2.51 | $11.10 |
| 0001-0860 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 20 | $26.74 | $123.38 |
| 0001-0870 | Mobilization (513SD20-0001) | LS | 1 | $199,000 | $240,589 |
| 0001-0880 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 1,129 | $29.28 | $35.04 |
| 0001-0890 | NS demo. of BLDG. D-1 EV charging station (516SX20-0008) | LS | 1 | $7,876.00 | $6,785.86 |
| 0001-0900 | Construction surveying constr. (517SD20-0001) | LS | 1 | $54,487 | $111,041 |
| 0001-0910 | 3/4" water service line (520SD20-0002) | LF | 26 | $60.00 | $49.35 |
| 0001-0920 | 2" water service line (520SD20-0006) | LF | 31 | $70.00 | $129.55 |
| 0001-0930 | 4" DI water main (520SD20-0012) | LF | 12 | $210.00 | $259.10 |
| 0001-0940 | 6" DI water main (520SD20-0014) | LF | 429 | $200.00 | $339.29 |
| 0001-0950 | 10" DI water main (520SD20-0018) | LF | 370 | $248.00 | $542.87 |
| 0001-0960 | 4" gate valve & box (520SD20-0088) | EACH | 2 | $3,956.55 | $4,009.82 |
| 0001-0970 | 6" gate valve & box (520SD20-0089) | EACH | 1 | $5,076.56 | $6,477.41 |
| 0001-0980 | Fire hydrant (520SD20-0162) | EACH | 1 | $8,500.00 | $10,487 |
| 0001-0990 | Manhole frame & cover F & C-1 (520SD20-0274) | EACH | 1 | $1,630.03 | $493.52 |
| 0001-1000 | Reconstruct existing sanitary manhole (520SD20-0275) | LF | 8 | $983.12 | $1,110.41 |
| 0001-1010 | 18" steel encase. pipe 20" steel encasement pipe (520SD20-0295) | LF | 76 | $498.37 | $339.29 |
| 0001-1020 | NS water facilities 3/4" water meter box and yoke (520SX20-0002) | EACH | 1 | $4,763.96 | $3,948.13 |
| 0001-1030 | Topsoil class B (602SD20-0004) | CY | 355 | $191.46 | $166.56 |
| 0001-1040 | Temporary seed (603SD20-0002) | LB | 200 | $18.00 | $24.68 |
| 0001-1050 | Regular seed (603SD20-0003) | LB | 425 | $19.20 | $24.68 |
| 0001-1060 | Overseeding (603SD20-0004) | LB | 340 | $19.20 | $24.68 |
| 0001-1070 | Legume seed (603SD20-0005) | LB | 13 | $36.00 | $30.84 |
| 0001-1080 | Legume overseeding (603SD20-0006) | LB | 10 | $36.00 | $30.84 |
| 0001-1090 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 6,050 | $1.08 | $2.47 |
| 0001-1100 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 15,730 | $1.32 | $2.47 |
| 0001-1110 | Sediment retention roll 18" min (603SD20-0011) | LF | 486 | $4.99 | $12.34 |
| 0001-1120 | Fertilizer nitrogen - N (603SD20-0014) | LB | 200 | $2.40 | $5.55 |
| 0001-1130 | Fertilizer phosphorous - P (603SD20-0015) | LB | 140 | $2.40 | $5.55 |
| 0001-1140 | Fertilizer potassium - K (603SD20-0016) | LB | 140 | $2.40 | $5.55 |
| 0001-1150 | Lime (603SD20-0017) | TON | 11 | $168.00 | $69.09 |
| 0001-1160 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 272 | $6.00 | $6.17 |
| 0001-1170 | Rolled erosion CTRL product EC-2 type 3 (606SD20-0003) | SY | 47 | $7.80 | $7.40 |
| 0001-1180 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 7 | $152.11 | $308.45 |
| 0001-1190 | Remove existing 1 post sign panel (700SD20-0007) | EACH | 7 | $116.78 | $308.45 |
| 0001-1200 | Remove existing 2 post sign panel (700SD20-0008) | EACH | 1 | $272.48 | $1,172.10 |
| 0001-1210 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 2 | $496.42 | $1,850.69 |
| 0001-1220 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 220 | $26.70 | $30.84 |
| 0001-1230 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 20 | $38.71 | $30.84 |
| 0001-1240 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 24 | $547.45 | $1,233.79 |
| 0001-1250 | Sign panel (701SD20-0001) | SF | 134 | $60.61 | $43.18 |
| 0001-1260 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 1,400 | $5.09 | $8.64 |
| 0001-1270 | Type B class II PVMT line MRKG 8" (704SD20-0013) | LF | 360 | $8.20 | $185.07 |
| 0001-1280 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 14 | $38.88 | $308.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.