Asphalt concrete TY. IM-19.0A, VDOT 315SD20-0004

Low bidders on VDOT contracts carried a median of $215.55 per TON for this item, over the 24 months to 28 OCT 2026, across 22 low bids. Half of all 73 bids fell between $160.00 and $300.00.

Owner
Virginia DOT
Item
315SD20-0004
Unit
TON
Data through
28 OCT 2026

VDOT prints this item as “ASPHALT CONCRETE TY. IM- 19.0A CONST”.

VDOT has bid this work under more than one code: 10610 on lettings from 29 JAN 2002 to 15 DEC 2021 (1,041 bids); 315SD20-0004 on lettings from 22 OCT 2025 to 26 AUG 2026 (73 bids). They are combined here into one trend.

$215.55Low bidder's median, per TON
$233.80Median of all bids, per TON
22Contracts in the window

By year of letting

Asphalt concrete TY. IM-19.0A, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20021414$38.7141$42.21
20031918$50.0048$50.00
20041616$50.0039$50.00
20051515$58.2536$64.98
20061717$86.0047$81.00
20071313$71.0039$75.00
20081717$95.0046$94.90
20091919$71.5054$80.70
20101616$72.8047$72.29
20111716$93.0050$95.39
20122424$99.1272$108.95
20132222$100.7863$93.88
20142727$95.4775$94.50
20152829$129.6375$129.63
20162727$114.0075$113.10
20171919$124.6053$116.00
20181617$112.7549$112.75
20191717$122.2043$120.00
20202020$130.4456$120.10
20211212$151.9933$155.00
202555$248.6610$251.83
20261717$168.7863$227.30

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Culpeper5$168.7822$250.00
Fredericksburg3$138.5014$179.95
Staunton3$140.009$140.00
Hampton Roads3$221.095$240.00
Asphalt concrete TY. IM-19.0A, VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (TON)Low bidsLow-bid median
27 to 635$440.00
64 to 2006$184.25
249 to 7305$227.30
765 to 2,3856$155.47
Asphalt concrete TY. IM-19.0A, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
W-L Construction & Paving, Inc.3124 (77%)
General Excavation, Inc.4521 (47%)
Howard Brothers Contractor, Inc.3419 (56%)
Branscome Inc.2712 (44%)
Blakemore Construction Corporation1312 (92%)
A & M Concrete Corp.3311 (33%)
Asphalt concrete TY. IM-19.0A, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
26 AUG 2026C0000115512C01Hampton Roads57$210.00$240.003Allan Myers Va, Inc.VDOT
22 JUL 2026C0000119468M01Salem827$243.30$221.652E. C. Pace Company, Inc.VDOT
22 JUL 2026C0000111704C01Richmond730$162.40$162.401J. L. Kent & Sons, Inc.VDOT
22 JUL 2026C0000115116C01Fredericksburg181$233.80$191.902J. L. Kent & Sons, Inc.VDOT
22 JUL 2026C0000126560B40Northern Virginia31$190.00$275.007Martins Construction Corp.VDOT
22 JUL 2026C0000120748C01Culpeper64$105.00$162.054General Excavation, Inc.VDOT
24 JUN 2026C0000108810C01Staunton2,385$148.00$148.502A & J Development and Excavation, Inc.VDOT
24 JUN 2026C0000115715C01Staunton1,186$140.00$138.752A & J Development and Excavation, Inc.VDOT
27 MAY 2026C0000119206C01Culpeper316$227.30$238.656J. L. Kent & Sons, Inc.VDOT
27 MAY 2026C0000118430B39Culpeper27$481.33$450.668Burleigh Construction Co., Inc.VDOT
27 MAY 2026C0000107309M01Salem163$270.00$267.504Burleigh Construction Co., Inc.VDOT
27 MAY 2026C000113172C01DFredericksburg160$130.00$255.004Ardent Company, LLCVDOT
22 APR 2026C0000101435C01Staunton978$105.50$130.005General Excavation, Inc.VDOT
22 APR 2026C0000118863C01Culpeper765$162.94$162.941Caton Construction Group, Inc.VDOT
04 FEB 2026C000118872C501Culpeper253$168.78$168.783Caton Construction Group, Inc.VDOT
Latest VDOT contracts carrying Asphalt concrete TY. IM-19.0A

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.