VDOT contract C0000119468M01 bid tabulation
Smart scale - road widening. Let by Virginia DOT on July 22, 2026, Roanoke, Salem. 2 bids received; low bid $3,715,713 by E. C. Pace Company, Inc..
- Owner
- Virginia DOT
- Letting
- 22 JUL 2026
- Pay items
- 129
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E. C. Pace Company, Inc. | $3,715,713 | Low |
| 2 | Allegheny Construction Company, Inc. | $5,461,636 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E. C. Pace Company, Inc. | 2. Allegheny Construction Company, Inc. |
|---|---|---|---|---|---|
| 0001-0010 | Const rec docs SWM facility NS construction docs for SWM facility (105SP20-0002) | LS | 1 | $8,182.57 | $22,000 |
| 0001-0020 | Baseline progress schedule (108SP20-0001) | LS | 1 | $10,263 | $20,000 |
| 0001-0030 | Progress schedule updates (108SP20-0002) | EACH | 17 | $2,080.32 | $2,000.00 |
| 0001-0040 | Clearing and grubbing (301SD20-0001) | LS | 1 | $37,882 | $700,000 |
| 0001-0050 | Bedding matl. aggr. no. 57 (302SD20-0002) | TON | 29 | $87.47 | $200.00 |
| 0001-0060 | 15" conc. pipe (302SD20-0025) | LF | 50 | $336.53 | $550.00 |
| 0001-0070 | 15" storm sewer pipe (302SD20-0027) | LF | 1,425 | $116.27 | $325.00 |
| 0001-0080 | 36" storm sewer pipe (302SD20-0061) | LF | 96 | $354.01 | $800.00 |
| 0001-0090 | 15" end section ES-1 or 2 (302SD20-0198) | EACH | 2 | $2,068.89 | $1,200.00 |
| 0001-0100 | Drop inlet DI-1 (302SD20-0237) | EACH | 2 | $6,827.13 | $12,000 |
| 0001-0110 | Drop inlet DI-3B,L=8' (302SD20-0313) | EACH | 2 | $6,640.31 | $13,000 |
| 0001-0120 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 3 | $9,551.07 | $13,400 |
| 0001-0130 | Drop inlet DI-3B,L=14' (302SD20-0316) | EACH | 2 | $9,987.67 | $14,000 |
| 0001-0140 | Drop inlet DI-3C,L=16' (302SD20-0334) | EACH | 1 | $10,923 | $14,500 |
| 0001-0150 | Drop inlet DI-3C,L=18' (302SD20-0335) | EACH | 1 | $11,606 | $15,000 |
| 0001-0160 | Drop inlet DI-4EE,L=10' (302SD20-0425) | EACH | 1 | $17,828 | $50,000 |
| 0001-0170 | Drop inlet DI-5 (302SD20-0446) | EACH | 1 | $7,176.16 | $11,000 |
| 0001-0180 | Manhole MH-1 or 2 (302SD20-0662) | LF | 30.30 | $904.77 | $1,400.00 |
| 0001-0190 | Frame & cover MH-1 (302SD20-0663) | EACH | 4 | $1,078.89 | $9.00 |
| 0001-0200 | Stormwater man.drain.STR.SWM-1 (302SD20-0673) | LF | 7.50 | $2,998.48 | $3,200.00 |
| 0001-0210 | NS pipe rehab 36", method B, category C (302SX20-0013) | LF | 16 | $613.41 | $1,200.00 |
| 0001-0220 | Regular excavation (303SD20-0001) | CY | 10,223 | $39.30 | $60.00 |
| 0001-0230 | Embankment (303SD20-0010) | CY | 358 | $52.62 | $60.00 |
| 0001-0240 | Geotextile embankment stab. (303SD20-0013) | SY | 510 | $5.00 | $20.00 |
| 0001-0250 | Slope drain (303SD20-0018) | EACH | 2 | $2,039.80 | $3,000.00 |
| 0001-0260 | Temporary diversion dike (303SD20-0021) | LF | 181 | $10.80 | $15.00 |
| 0001-0270 | Check dam rock TY. II (303SD20-0023) | EACH | 82 | $405.64 | $650.00 |
| 0001-0280 | Dewatering basin EC-8 (303SD20-0028) | EACH | 2 | $769.43 | $5,600.00 |
| 0001-0290 | Siltation control excavation (303SD20-0029) | CY | 755 | $1.50 | $25.00 |
| 0001-0300 | Inlet protection type A (303SD20-0030) | EACH | 1 | $322.63 | $1,000.00 |
| 0001-0310 | Inlet protection type B (303SD20-0031) | EACH | 11 | $410.00 | $1,000.00 |
| 0001-0320 | Geotextile fabric (303SD20-0032) | SY | 146 | $3.27 | $30.00 |
| 0001-0330 | Temp. silt fence type A (303SD20-0034) | LF | 1,251 | $3.97 | $7.00 |
| 0001-0340 | Temp. sediment basin excavation (303SD20-0035) | CY | 286 | $33.90 | $60.00 |
| 0001-0350 | Storm water man. basin excav. (303SD20-0036) | CY | 1,121 | $19.39 | $35.00 |
| 0001-0360 | Borrow excavation (305SD20-0001) | CY | 4,590 | $48.15 | $25.00 |
| 0001-0370 | Aggr. matl. no. 3 (305SD20-0013) | TON | 1,283 | $46.28 | $85.00 |
| 0001-0380 | Aggr. base matl. TY. I no. 21B (308SD20-0012) | TON | 3,015 | $59.73 | $65.00 |
| 0001-0390 | Aggr. matl. no. 1 (309SD20-0001) | TON | 447 | $47.78 | $75.00 |
| 0001-0400 | Asphalt concrete TY. IM- 19.0A const (315SD20-0004) | TON | 827 | $243.30 | $200.00 |
| 0001-0410 | Asphalt concrete TY. SM- 9.5D const (315SD20-0008) | TON | 1,036 | $239.98 | $195.00 |
| 0001-0420 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 2,094 | $235.59 | $190.00 |
| 0001-0430 | NS saw-cut asph conc full depth (315SX20-0011) | LF | 1,400 | $2.56 | $8.00 |
| 0001-0440 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 5.30 | $208.32 | $140.00 |
| 0001-0450 | Erosion CTRL. stone CL. I, EC-1 (414SD20-0003) | TON | 40 | $136.28 | $140.00 |
| 0001-0460 | Dry riprap CL. AI (414SD20-0008) | TON | 72.10 | $95.66 | $120.00 |
| 0001-0470 | Paved ditch PG-5 (502SD20-0004) | SY | 58 | $210.39 | $330.00 |
| 0001-0480 | Curb, STD. CG-2 (502SD20-0011) | LF | 129 | $78.28 | $120.00 |
| 0001-0490 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 1,698 | $56.11 | $105.00 |
| 0001-0500 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 308 | $63.85 | $105.00 |
| 0001-0510 | Comb. curb & gutter, STD. CG-7 (502SD20-0024) | LF | 165 | $54.57 | $105.00 |
| 0001-0520 | Entrance gutter CG-9D (502SD20-0029) | SY | 155 | $89.77 | $125.00 |
| 0001-0530 | NS saw cut H.C.C. items sawcut EX curb and gutter (502SX20-0010) | LF | 13 | $26.03 | $50.00 |
| 0001-0540 | Concrete class A3 misc. (504SD20-0001) | CY | 39.10 | $303.96 | $1,350.00 |
| 0001-0550 | CG-12 detectable warning surface (504SD20-0002) | SY | 7 | $1,910.56 | $1,400.00 |
| 0001-0560 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 489 | $73.76 | $185.00 |
| 0001-0570 | Remove existing guardrail (505SD20-0073) | LF | 639 | $10.89 | $12.00 |
| 0001-0580 | High visibility fence, 4 feet (507SD20-0027) | LF | 300 | $5.61 | $5.00 |
| 0001-0590 | Obscuring roadway (508SD20-0001) | UNIT | 28.80 | $1,194.43 | $450.00 |
| 0001-0600 | Demo. of pavement flexible (508SD20-0004) | SY | 4,588 | $18.30 | $16.00 |
| 0001-0610 | Flowable backfill (509SD20-0001) | CY | 5 | $588.49 | $1,400.00 |
| 0001-0620 | Remove GR-7 terminal (510SD20-0001) | EACH | 4 | $869.58 | $500.00 |
| 0001-0630 | Adjust exist frame & cover (510SD20-0050) | EACH | 2 | $979.83 | $1,700.00 |
| 0001-0640 | NS modify exist. drainage structure (510SX20-0031) | EACH | 1 | $4,578.00 | $9,000.00 |
| 0001-0650 | NS modify exist. pool drains (510SX20-0031) | EACH | 2 | $66.92 | $1,200.00 |
| 0001-0660 | Allaying dust (511SD20-0001) | HR | 1,800 | $8.00 | $0.01 |
| 0001-0670 | Traffic barrier service MB-11A (512SD20-0003) | LF | 300 | $102.63 | $70.00 |
| 0001-0680 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 1 | $11,788 | $30,000 |
| 0001-0690 | Type 3 barricade 4' (512SD20-0012) | EACH | 2 | $221.55 | $600.00 |
| 0001-0700 | Type 3 barricade 8' (512SD20-0013) | EACH | 4 | $604.90 | $650.00 |
| 0001-0710 | Temporary sign (512SD20-0014) | SF | 1,390 | $31.26 | $25.00 |
| 0001-0720 | Truck mounted attenuator (512SD20-0023) | HR | 200 | $45.60 | $80.00 |
| 0001-0730 | Group 2 channelizing devices (512SD20-0024) | DAY | 8,360 | $1.93 | $4.00 |
| 0001-0740 | Port.changeable mess. sign (512SD20-0025) | HR | 2,424 | $7.63 | $12.00 |
| 0001-0750 | Electronic arrow board (512SD20-0026) | HR | 384 | $6.93 | $4.00 |
| 0001-0760 | Flagger service (512SD20-0027) | HR | 936 | $83.21 | $85.00 |
| 0001-0770 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 3,640 | $3.69 | $4.75 |
| 0001-0780 | Eradicate nonlinear PVMT MRKG (512SD20-0043) | SF | 250 | $12.31 | $10.00 |
| 0001-0790 | Temp. pave. marker 1 way (512SD20-0044) | EACH | 80 | $5.79 | $25.00 |
| 0001-0800 | Temp. pave. marker 2 way (512SD20-0045) | EACH | 220 | $5.79 | $30.00 |
| 0001-0810 | Temp. PVMT MRKG TY. A, 4" (512SD20-0046) | LF | 21,060 | $1.78 | $2.25 |
| 0001-0820 | Temp. PVMT MRKG TY. A, 8" (512SD20-0048) | LF | 1,780 | $1.82 | $4.00 |
| 0001-0830 | Temp. PVMT MRKG TY. A, 24" (512SD20-0050) | LF | 520 | $17.16 | $15.00 |
| 0001-0840 | Temp. PVMT. symb. MRKG SNGL turn arrow TY. A (512SD20-0052) | EACH | 11 | $127.09 | $300.00 |
| 0001-0850 | Portable temporary rumble strip array (512SP20-0001) | DAY | 100 | $183.55 | $120.00 |
| 0001-0860 | Mobilization (513SD20-0001) | LS | 1 | $79,819 | $260,000 |
| 0001-0870 | Field office TY.I (514SD20-0001) | MO | 18 | $4,815.54 | $5,200.00 |
| 0001-0880 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 4,800 | $10.68 | $12.00 |
| 0001-0890 | Closing well (516SD20-0001) | EACH | 1 | $2,080.32 | $2,700.00 |
| 0001-0900 | Construction surveying constr. (517SD20-0001) | LS | 1 | $102,144 | $135,000 |
| 0001-0910 | 1" water service line (520SD20-0003) | LF | 82 | $62.75 | $80.00 |
| 0001-0920 | 6" water main (520SD20-0013) | LF | 7 | $875.53 | $900.00 |
| 0001-0930 | 12" water main (520SD20-0019) | LF | 8 | $986.12 | $1,300.00 |
| 0001-0940 | 6" gate valve & box (520SD20-0089) | EACH | 1 | $3,805.35 | $5,400.00 |
| 0001-0950 | Fire hydrant (520SD20-0162) | EACH | 1 | $7,272.80 | $8,000.00 |
| 0001-0960 | 5/8" water meter box & yoke (520SD20-0167) | EACH | 1 | $3,146.16 | $4,000.00 |
| 0001-0970 | NS water facilities 12" gate valve & manhole (520SX20-0002) | EACH | 1 | $7,953.81 | $10,000 |
| 0001-0980 | Mailbox post, single (521SD20-0001) | EACH | 2 | $438.69 | $800.00 |
| 0001-0990 | Storm water management low perm liner (523SP20-0002) | SY | 1,131 | $44.39 | $44.00 |
| 0001-1000 | Topsoil class B (602SD20-0004) | CY | 126 | $151.63 | $180.00 |
| 0001-1010 | NS topsoil 4" topsoil (602SX20-0005) | ACRE | 1.52 | $15,473 | $12,000 |
| 0001-1020 | Temporary seed (603SD20-0002) | LB | 304 | $16.64 | $20.00 |
| 0001-1030 | Regular seed (603SD20-0003) | LB | 449 | $16.64 | $18.00 |
| 0001-1040 | Overseeding (603SD20-0004) | LB | 359 | $16.64 | $8.00 |
| 0001-1050 | Legume seed (603SD20-0005) | LB | 23 | $24.97 | $30.00 |
| 0001-1060 | Legume overseeding (603SD20-0006) | LB | 18 | $24.97 | $30.00 |
| 0001-1070 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 2,541 | $0.83 | $1.50 |
| 0001-1080 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 14,012 | $1.04 | $1.70 |
| 0001-1090 | Sediment retention roll 18" min (603SD20-0011) | LF | 275 | $23.37 | $20.00 |
| 0001-1100 | Fertilizer nitrogen - N (603SD20-0014) | LB | 152 | $3.12 | $4.00 |
| 0001-1110 | Fertilizer phosphorous - P (603SD20-0015) | LB | 106 | $3.12 | $4.00 |
| 0001-1120 | Fertilizer potassium - K (603SD20-0016) | LB | 106 | $3.12 | $4.00 |
| 0001-1130 | Lime (603SD20-0017) | TON | 8.36 | $194.16 | $500.00 |
| 0001-1140 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 174 | $18.06 | $4.00 |
| 0001-1150 | Rolled erosion CTRL product EC-2 type 3 (606SD20-0003) | SY | 898 | $15.57 | $5.00 |
| 0001-1160 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 2 | $185.46 | $50.00 |
| 0001-1170 | Mowing (608SD20-0001) | HR | 40 | $71.21 | $100.00 |
| 0001-1180 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 6 | $148.53 | $500.00 |
| 0001-1190 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 5 | $636.30 | $650.00 |
| 0001-1200 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 175 | $30.86 | $30.00 |
| 0001-1210 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 14 | $684.45 | $675.00 |
| 0001-1220 | Sign panel (701SD20-0001) | SF | 75.13 | $80.36 | $70.00 |
| 0001-1230 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 8,900 | $2.15 | $4.00 |
| 0001-1240 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 200 | $6.41 | $6.00 |
| 0001-1250 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 250 | $6.78 | $7.00 |
| 0001-1260 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 330 | $30.26 | $30.00 |
| 0001-1270 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 8 | $504.13 | $450.00 |
| 0001-1280 | DBL turn arr.thru/LT or RT TY B, CL II (704SD20-0051) | EACH | 2 | $881.09 | $800.00 |
| 0001-1290 | PVMT MSG. mark. “only” TY B, CL II, 8’ (704SD20-0108) | EACH | 2 | $978.95 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of July 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.