Storm water man. basin excav., VDOT 303SD20-0036

Low bidders on VDOT contracts carried a median of $50.00 per CY for this item, over the 24 months to 28 OCT 2026, across 16 low bids. Half of all 45 bids fell between $39.97 and $120.00.

Owner
Virginia DOT
Item
303SD20-0036
Unit
CY
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 27545 on lettings from 21 MAY 2002 to 15 DEC 2021 (304 bids); 303SD20-0036 on lettings from 19 NOV 2025 to 23 SEP 2026 (45 bids). They are combined here into one trend.

$50.00Low bidder's median, per CY
$69.00Median of all bids, per CY
16Contracts in the window

By year of letting

Storm water man. basin excav., VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200222$6.436$7.00
200455$10.0012$11.00
200533$8.008$9.00
200633$10.599$11.55
200755$10.0015$10.00
200855$9.1615$12.00
200977$5.0021$7.50
201066$11.6618$9.95
201155$11.5415$15.15
201255$9.7415$15.00
201388$13.8523$16.00
201477$30.0017$25.00
20151212$11.7030$12.84
201688$10.4522$13.65
201766$18.5017$28.28
201855$21.5015$20.88
201988$26.3620$23.11
202055$30.0014$17.00
202144$32.3911$29.78
202544$64.0015$69.14
20261212$40.5030$67.28

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Bristol3$50.0010$64.78
Salem4$61.509$71.98
Culpeper3$28.008$70.84
Storm water man. basin excav., VDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Quantity (CY)Low bidsLow-bid median
63 to 5074$90.00
524 to 1,1214$64.00
1,165 to 2,3394$36.50
2,943 to 6,3004$50.77
Storm water man. basin excav., VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
E. V. Williams, Inc.86 (75%)
Branscome Inc.195 (26%)
General Excavation, Inc.175 (29%)
J. L. Kent & Sons, Inc.115 (45%)
Allegheny Construction Company, Inc.95 (56%)
Phillips Construction, LLC55 (100%)
Storm water man. basin excav., VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
23 SEP 2026C0000123290C01Richmond1,756$208.84$80.005Caton Construction Group, Inc.VDOT
26 AUG 2026C0000124095M01Salem1,165$45.00$95.994Allegheny Construction Company, Inc.VDOT
26 AUG 2026C0000129131C01BRichmond3,008$175.00$137.502Caton Construction Group, Inc.VDOT
22 JUL 2026C0000119468M01Salem1,121$19.39$27.202E. C. Pace Company, Inc.VDOT
22 JUL 2026C0000120611C01Salem63$967.00$967.001Branch Civil, Inc.VDOT
22 JUL 2026C0000120748C01Culpeper2,339$28.00$50.344General Excavation, Inc.VDOT
24 JUN 2026C0000108810C01Staunton6,300$36.00$31.382A & J Development and Excavation, Inc.VDOT
24 JUN 2026C0000115470C01Bristol2,943$65.55$62.772W-L Construction & Paving, Inc.VDOT
22 APR 2026C0000118863C01Culpeper3,333$5.27$5.271Caton Construction Group, Inc.VDOT
22 APR 2026C0000119163C01Lynchburg1,861$20.00$23.772Allegheny Construction Company, Inc.VDOT
22 APR 2026C0000119167C01Lynchburg418$20.00$110.002Caton Construction Group, Inc.VDOT
04 FEB 2026C000118872C501Culpeper694$180.00$120.003Caton Construction Group, Inc.VDOT
17 DEC 2025C0000119429C01Bristol507$50.00$66.124Ramirez Contracting, L.L.C.VDOT
19 NOV 2025C0000119441C01Bristol524$50.00$63.254Ramirez Contracting, L.L.C.VDOT
19 NOV 2025C0000119503C01Salem785$78.00$60.002Jones Road & Bridge, Inc.VDOT
Latest VDOT contracts carrying Storm water man. basin excav.

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.