VDOT contract C0000123290C01 bid tabulation
Roundabout. Let by Virginia DOT on September 23, 2026, Goochland, Richmond. 5 bids received; low bid $5,070,390 by Caton Construction Group, Inc..
- Owner
- Virginia DOT
- Letting
- 23 SEP 2026
- Pay items
- 130
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Caton Construction Group, Inc. | $5,070,390 | Low |
| 2 | Curtis Contracting, Inc. | $5,132,377 | +1.0% |
| 3 | J. R. Caskey, Inc. | $5,154,681 | +2.0% |
| 4 | Shirley Contracting Company, LLC | $6,203,572 | +22% |
| 5 | Sagres Construction Corporation | $7,125,097 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Caton Construction Group, Inc. | 2. Curtis Contracting, Inc. | 3. J. R. Caskey, Inc. | 4. Shirley Contracting Company, LLC | 5. Sagres Construction Corporation |
|---|---|---|---|---|---|---|---|---|
| 0001-0010 | Baseline progress schedule (108SP20-0001) | LS | 1 | $9,652.68 | $12,701 | $50,000 | $50,750 | $25,000 |
| 0001-0020 | Progress schedule updates (108SP20-0002) | EACH | 18 | $1,930.54 | $1,270.08 | $350.00 | $2,000.00 | $2,500.00 |
| 0001-0030 | Clearing and grubbing (301SD20-0001) | LS | 1 | $70,292 | $771,216 | $250,000 | $335,000 | $250,000 |
| 0001-0040 | Endwall EW-12 (302SD20-0013) | EACH | 1 | $2,608.79 | $1,270.08 | $2,500.00 | $2,500.00 | $1,750.00 |
| 0001-0050 | 15" storm sewer pipe (302SD20-0027) | LF | 776 | $229.23 | $513.07 | $350.00 | $250.00 | $500.00 |
| 0001-0060 | 24" conc. pipe (302SD20-0039) | LF | 53 | $218.49 | $492.16 | $425.00 | $350.00 | $550.00 |
| 0001-0070 | 24" storm sewer pipe (302SD20-0041) | LF | 209 | $218.49 | $498.86 | $300.00 | $350.00 | $550.00 |
| 0001-0080 | 30" storm sewer pipe (302SD20-0051) | LF | 53 | $261.00 | $531.20 | $300.00 | $400.00 | $800.00 |
| 0001-0090 | Drop inlet DI-2AA (302SD20-0240) | EACH | 2 | $18,139 | $21,852 | $15,000 | $20,000 | $17,500 |
| 0001-0100 | Drop inlet DI-2B,L=4' (302SD20-0241) | EACH | 2 | $16,517 | $13,155 | $15,000 | $20,000 | $17,000 |
| 0001-0110 | Drop inlet DI-2B,L=6' (302SD20-0242) | EACH | 1 | $18,088 | $12,700 | $15,000 | $20,000 | $16,500 |
| 0001-0120 | Drop inlet DI-3B,L=4' (302SD20-0311) | EACH | 2 | $14,485 | $11,320 | $15,000 | $15,000 | $16,750 |
| 0001-0130 | Drop inlet DI-3B,L=6' (302SD20-0312) | EACH | 2 | $16,825 | $11,861 | $15,000 | $15,000 | $18,500 |
| 0001-0140 | Drop inlet DI-3B,L=8' (302SD20-0313) | EACH | 1 | $15,318 | $11,877 | $15,000 | $15,000 | $15,000 |
| 0001-0150 | Drop inlet DI-3B,L=10' (302SD20-0314) | EACH | 1 | $16,586 | $21,128 | $15,000 | $15,000 | $15,000 |
| 0001-0160 | Drop inlet DI-3BB,L=6' (302SD20-0321) | EACH | 1 | $16,820 | $24,036 | $20,000 | $21,000 | $15,000 |
| 0001-0170 | Drop inlet DI-3CC,L=6' (302SD20-0337) | EACH | 2 | $16,415 | $12,645 | $15,000 | $20,000 | $15,000 |
| 0001-0180 | Drop inlet DI-7 (302SD20-0447) | EACH | 1 | $14,413 | $12,645 | $20,264 | $20,000 | $20,000 |
| 0001-0190 | Manhole MH-1 or 2 (302SD20-0662) | LF | 11.50 | $8,339.01 | $2,003.93 | $2,000.00 | $2,500.00 | $3,500.00 |
| 0001-0200 | Frame & cover MH-1 (302SD20-0663) | EACH | 2 | $8,889.44 | $1,237.19 | $2,000.00 | $1,750.00 | $2,000.00 |
| 0001-0210 | Stormwater man.drain.STR.SWM-1 (302SD20-0673) | LF | 6.10 | $2,045.48 | $1,483.20 | $3,500.00 | $5,000.00 | $2,500.00 |
| 0001-0220 | Temp. sediment riser pipe 48" (302SD20-0683) | LF | 6.10 | $3,698.32 | $1,883.39 | $2,500.00 | $1,750.00 | $3,000.00 |
| 0001-0230 | Regular excavation (303SD20-0001) | CY | 5,035 | $88.05 | $63.45 | $85.00 | $155.00 | $85.00 |
| 0001-0240 | Borrow excavation (303SD20-0007) | CY | 6,738 | $63.28 | $33.37 | $45.00 | $50.00 | $115.00 |
| 0001-0250 | Temporary diversion dike (303SD20-0021) | LF | 437 | $23.37 | $19.51 | $20.00 | $30.00 | $55.00 |
| 0001-0260 | Check dam rock TY. II (303SD20-0023) | EACH | 5 | $723.08 | $408.43 | $850.00 | $2,000.00 | $500.00 |
| 0001-0270 | Check dam sediment retention roll 20" (303SD20-0025) | EACH | 3 | $8.82 | $349.34 | $850.00 | $1,250.00 | $400.00 |
| 0001-0280 | Dewatering basin EC-8 (303SD20-0028) | EACH | 1 | $4,803.87 | $6,078.04 | $1,500.00 | $20,000 | $50,000 |
| 0001-0290 | Siltation control excavation (303SD20-0029) | CY | 7,582.50 | $1.00 | $0.66 | $0.01 | $4.80 | $20.00 |
| 0001-0300 | Inlet protection type A (303SD20-0030) | EACH | 1 | $512.77 | $1,317.28 | $1,000.00 | $500.00 | $300.00 |
| 0001-0310 | Inlet protection type B (303SD20-0031) | EACH | 14 | $244.43 | $362.04 | $1,000.00 | $400.00 | $500.00 |
| 0001-0320 | Geotextile fabric (303SD20-0032) | SY | 4,178 | $12.79 | $3.11 | $5.00 | $7.00 | $6.00 |
| 0001-0330 | Temp. silt fence type B (303SD20-0033) | LF | 710 | $6.72 | $11.75 | $15.00 | $13.00 | $12.32 |
| 0001-0340 | Temp. silt fence type A (303SD20-0034) | LF | 1,172 | $16.32 | $4.89 | $15.00 | $13.00 | $5.51 |
| 0001-0350 | Storm water man. basin excav. (303SD20-0036) | CY | 1,756 | $208.84 | $39.97 | $32.07 | $80.00 | $85.00 |
| 0001-0360 | Aggr. matl. no. 21B (308SD20-0007) | TON | 5,003 | $83.19 | $50.60 | $60.00 | $85.00 | $75.00 |
| 0001-0370 | Crusher run aggr. no. 25 or 26 (308SX20-0003) | TON | 164 | $64.28 | $74.42 | $90.00 | $83.00 | $60.00 |
| 0001-0380 | Tack coat (310SD20-0001) | GAL | 747 | $2.04 | $2.54 | $2.00 | $12.00 | $7.50 |
| 0001-0390 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 495 | $172.45 | $214.64 | $260.00 | $230.00 | $400.00 |
| 0001-0400 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 422 | $169.39 | $210.83 | $300.00 | $230.00 | $375.00 |
| 0001-0410 | Asphalt concrete BM-25.0 (315SD20-0010) | TON | 1,264 | $160.20 | $199.40 | $230.00 | $234.00 | $350.00 |
| 0001-0420 | Saw-cut asphalt concrete asphalt saw- cut (315SD20-0104) | LF | 2,875 | $10.11 | $6.35 | $10.00 | $9.00 | $5.00 |
| 0001-0430 | Reinf. hydr.cem.conc. pave. 8" (316SD20-0007) | SY | 489 | $400.00 | $409.57 | $850.00 | $344.00 | $500.00 |
| 0001-0440 | Cofferdam (401SD20-0007) | EACH | 1 | $14,306 | $1,270.08 | $5,000.00 | $1,000.00 | $25,000 |
| 0001-0450 | Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001) | TON | 138.30 | $284.58 | $130.63 | $150.00 | $230.00 | $235.18 |
| 0001-0460 | Dry riprap CL. AI (414SD20-0008) | TON | 27 | $190.27 | $198.35 | $150.00 | $320.00 | $229.40 |
| 0001-0470 | Underdrain UD-4 (501SD20-0004) | LF | 1,685 | $63.08 | $31.75 | $40.00 | $65.75 | $46.36 |
| 0001-0480 | Outlet pipe (501SD20-0009) | LF | 66 | $71.80 | $38.10 | $35.00 | $47.25 | $53.94 |
| 0001-0490 | Curb, STD. CG-2 (502SD20-0011) | LF | 416 | $32.00 | $59.69 | $125.00 | $72.25 | $120.00 |
| 0001-0500 | Curb, radial CG-2 (502SD20-0012) | LF | 970 | $64.00 | $59.69 | $125.00 | $70.50 | $120.00 |
| 0001-0510 | Curb, radial CG-3 (502SD20-0015) | LF | 359 | $64.00 | $83.83 | $125.00 | $85.25 | $120.00 |
| 0001-0520 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 858 | $32.00 | $59.69 | $125.00 | $75.25 | $140.00 |
| 0001-0530 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 700 | $64.00 | $59.69 | $125.00 | $78.00 | $140.00 |
| 0001-0540 | Comb. curb & gutter, STD. CG-7 (502SD20-0024) | LF | 22 | $32.00 | $59.69 | $125.00 | $89.00 | $150.00 |
| 0001-0550 | Comb. curb & gutter, rad. CG-7 (502SD20-0025) | LF | 102 | $64.00 | $59.69 | $125.00 | $86.50 | $155.00 |
| 0001-0560 | Median strip MS-1 (502SD20-0053) | SY | 301 | $300.00 | $278.98 | $500.00 | $348.00 | $275.00 |
| 0001-0570 | Concrete class A3 misc. (504SD20-0001) | CY | 12.29 | $3,380.00 | $1,509.49 | $1,150.00 | $2,000.00 | $3,100.00 |
| 0001-0580 | Guardrail GR-MGS1 (505SD20-0011) | LF | 119 | $40.00 | $51.74 | $55.00 | $70.00 | $50.00 |
| 0001-0590 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 1 | $3,900.00 | $4,073.40 | $5,300.00 | $7,000.00 | $5,000.00 |
| 0001-0600 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 1 | $1,900.00 | $4,374.27 | $2,500.00 | $3,300.00 | $2,400.00 |
| 0001-0610 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 2 | $1,500.00 | $2,601.12 | $2,000.00 | $2,750.00 | $2,000.00 |
| 0001-0620 | Remove existing guardrail (505SD20-0073) | LF | 366 | $5.00 | $19.60 | $7.00 | $9.00 | $10.00 |
| 0001-0630 | BR-GR post attachment various types (505SP20-0013) | EACH | 2 | $3,000.00 | $8,524.79 | $6,500.00 | $7,500.00 | $3,800.00 |
| 0001-0640 | Fence FE-CL (507SD20-0005) | LF | 580 | $34.80 | $58.42 | $40.00 | $58.00 | $40.00 |
| 0001-0650 | Gate FE-CL 14' (507SD20-0014) | EACH | 1 | $1,500.00 | $3,302.22 | $10,000 | $4,350.00 | $2,500.00 |
| 0001-0660 | Demo. of pavement flexible (508SD20-0004) | SY | 4,015 | $40.86 | $17.42 | $18.00 | $28.00 | $35.00 |
| 0001-0670 | Allaying dust (511SD20-0001) | HR | 209 | $11.73 | $82.56 | $1.00 | $90.00 | $119.59 |
| 0001-0680 | Traffic barrier service MB-11A (512SD20-0003) | LF | 100 | $85.58 | $239.56 | $180.00 | $160.00 | $452.45 |
| 0001-0690 | Type 3 barricade 8' (512SD20-0013) | EACH | 17 | $639.49 | $900.62 | $500.00 | $760.00 | $231.28 |
| 0001-0700 | Temporary sign (512SD20-0014) | SF | 2,329 | $18.48 | $44.45 | $0.01 | $80.00 | $35.08 |
| 0001-0710 | Truck mounted attenuator (512SD20-0023) | HR | 1,016 | $100.96 | $63.50 | $40.00 | $125.00 | $35.28 |
| 0001-0720 | Group 2 channelizing devices (512SD20-0024) | DAY | 21,659 | $0.36 | $0.67 | $0.50 | $3.00 | $1.09 |
| 0001-0730 | Port.changeable mess. sign (512SD20-0025) | HR | 1,512 | $12.82 | $30.00 | $25.00 | $11.00 | $20.00 |
| 0001-0740 | Flagger service (512SD20-0027) | HR | 960 | $79.25 | $46.73 | $125.00 | $85.00 | $45.00 |
| 0001-0750 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 140 | $114.97 | $118.27 | $130.00 | $91.00 | $350.00 |
| 0001-0760 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 1,180 | $2.06 | $3.81 | $0.01 | $3.00 | $2.17 |
| 0001-0770 | Temp. pave. marker 2 way (512SD20-0045) | EACH | 227 | $15.45 | $31.75 | $6.00 | $30.00 | $20.84 |
| 0001-0780 | Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061) | LF | 10,216 | $3.04 | $4.89 | $1.50 | $4.25 | $2.94 |
| 0001-0790 | Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062) | LF | 2,334 | $3.61 | $5.91 | $2.50 | $6.50 | $4.41 |
| 0001-0800 | Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063) | LF | 184 | $3.97 | $11.75 | $12.00 | $8.50 | $5.88 |
| 0001-0810 | Impact attenuator IA-1 (512SD20-0069) | EACH | 1 | $15,604 | $34,805 | $15,000 | $21,750 | $36,777 |
| 0001-0820 | Mobilization (513SD20-0001) | LS | 1 | $250,000 | $301,540 | $287,000 | $340,000 | $385,000 |
| 0001-0830 | Field office TY.I (514SD20-0001) | MO | 18 | $9,878.44 | $4,000.76 | $4,000.00 | $7,500.00 | $8,500.00 |
| 0001-0840 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 1,832 | $10.20 | $12.70 | $15.00 | $15.00 | $25.00 |
| 0001-0850 | Construction surveying constr. (517SD20-0001) | LS | 1 | $62,200 | $50,803 | $125,000 | $125,200 | $188,000 |
| 0001-0860 | Topsoil class B (602SD20-0006) | CY | 998 | $179.00 | $124.47 | $50.00 | $85.00 | $90.00 |
| 0001-0870 | Temporary seed (603SD20-0002) | LB | 180 | $15.00 | $19.05 | $7.00 | $9.00 | $7.00 |
| 0001-0880 | Regular seed (603SD20-0003) | LB | 484 | $10.00 | $12.70 | $7.00 | $8.00 | $12.50 |
| 0001-0890 | Overseeding (603SD20-0004) | LB | 387 | $5.00 | $6.35 | $7.00 | $9.00 | $12.50 |
| 0001-0900 | Legume seed (603SD20-0005) | LB | 21 | $10.00 | $12.70 | $11.00 | $65.00 | $15.00 |
| 0001-0910 | Legume overseeding (603SD20-0006) | LB | 17 | $15.00 | $19.05 | $11.00 | $65.00 | $15.00 |
| 0001-0920 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 10,285 | $1.25 | $1.59 | $1.00 | $2.00 | $5.00 |
| 0001-0930 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 9,317 | $1.50 | $1.91 | $1.00 | $2.50 | $5.00 |
| 0001-0940 | Fertilizer nitrogen - N (603SD20-0014) | LB | 180 | $4.00 | $5.08 | $2.00 | $12.00 | $7.50 |
| 0001-0950 | Fertilizer phosphorous - P (603SD20-0015) | LB | 126 | $4.00 | $5.08 | $2.00 | $12.00 | $7.50 |
| 0001-0960 | Fertilizer potassium - K (603SD20-0016) | LB | 126 | $4.00 | $5.08 | $2.00 | $12.00 | $7.50 |
| 0001-0970 | Lime (603SD20-0017) | TON | 10 | $450.00 | $571.54 | $500.00 | $260.00 | $612.95 |
| 0001-0980 | Bed preparation (605SD20-0001) | UNIT | 646 | $25.00 | $31.75 | $10.00 | $50.00 | $125.00 |
| 0001-0990 | Mulching (605SD20-0002) | CY | 54 | $100.00 | $127.01 | $70.00 | $185.00 | $79.68 |
| 0001-1000 | Plant (andropogon gerardii 'blackhawks' #1 cont) (605SD20-0008) | EACH | 79 | $20.25 | $25.72 | $70.00 | $37.00 | $245.18 |
| 0001-1010 | Plant (liatris spicata #1 cont) (605SD20-0008) | EACH | 89 | $10.00 | $12.70 | $70.00 | $19.00 | $245.18 |
| 0001-1020 | Plant (liriope muscari 'big blue' 2" plug 50 cell) (605SD20-0008) | EACH | 1,529 | $16.00 | $20.32 | $5.00 | $30.00 | $91.94 |
| 0001-1030 | Plant (narcissus pseudonarcissus 'king alfred' DN2 bulb) (605SD20-0008) | EACH | 269 | $31.00 | $39.37 | $7.00 | $57.00 | $91.94 |
| 0001-1040 | Plant (rudbeckia fulgida 'goldsturm' #1 cont) (605SD20-0008) | EACH | 89 | $50.00 | $63.50 | $70.00 | $92.00 | $91.94 |
| 0001-1050 | Plant (schizachyrium scoparium #1 cont) (605SD20-0008) | EACH | 89 | $50.00 | $63.50 | $70.00 | $92.00 | $91.94 |
| 0001-1060 | Rolled erosion CTRL product EC-2 type 2 (606SD20-0002) | SY | 163 | $2.85 | $3.62 | $3.00 | $27.00 | $6.13 |
| 0001-1070 | Rolled erosion CTRL product EC-3 type 3 (606SD20-0007) | SY | 2,214 | $4.75 | $6.03 | $4.00 | $7.00 | $6.13 |
| 0001-1080 | Gabions (610SD20-0001) | CY | 30 | $577.61 | $1,215.62 | $700.00 | $1,160.00 | $1,000.00 |
| 0001-1090 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 15 | $190.00 | $456.08 | $1,000.00 | $220.00 | $607.37 |
| 0001-1100 | Remove existing 2 post sign structure (700SD20-0004) | EACH | 3 | $280.00 | $456.08 | $1,000.00 | $3,000.00 | $607.37 |
| 0001-1110 | Remove existing 3 post sign structure (700SD20-0005) | EACH | 3 | $400.00 | $1,265.62 | $1,000.00 | $3,000.00 | $607.37 |
| 0001-1120 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 1 | $175.00 | $1,199.15 | $700.16 | $500.00 | $936.74 |
| 0001-1130 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 210 | $9.00 | $46.80 | $50.00 | $60.00 | $77.80 |
| 0001-1140 | Sign post STP-1, 2 3/16", 10 gauge (700SD20-0035) | LF | 102 | $11.00 | $53.42 | $35.00 | $70.00 | $78.50 |
| 0001-1150 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 88 | $11.00 | $53.43 | $35.00 | $70.00 | $78.50 |
| 0001-1160 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 156 | $10.00 | $53.42 | $35.00 | $60.00 | $78.50 |
| 0001-1170 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 30 | $775.00 | $619.97 | $600.00 | $1,000.00 | $592.08 |
| 0001-1180 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 11 | $820.00 | $1,237.49 | $700.00 | $1,320.00 | $592.09 |
| 0001-1190 | Sign post STP-2, 4", 8 gauge (700SD20-0200) | LF | 68 | $72.00 | $83.08 | $200.00 | $230.00 | $139.17 |
| 0001-1200 | Concrete foundation STP-2, type A (700SD20-0201) | EACH | 3 | $1,856.00 | $1,289.11 | $8,000.00 | $10,000 | $2,092.43 |
| 0001-1210 | Concrete foundation STP-2, type H (700SD20-0208) | EACH | 1 | $1,910.00 | $1,612.23 | $10,000 | $11,000 | $2,091.02 |
| 0001-1220 | Sign panel (701SD20-0001) | SF | 651 | $38.00 | $39.76 | $75.00 | $105.00 | $54.65 |
| 0001-1230 | Type B class I PVMT line MRKG 4" (704SD20-0006) | LF | 1,830 | $2.06 | $2.35 | $5.00 | $4.00 | $3.00 |
| 0001-1240 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 1,401 | $3.09 | $2.60 | $5.00 | $6.00 | $4.00 |
| 0001-1250 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 65 | $4.12 | $12.70 | $5.00 | $8.00 | $6.00 |
| 0001-1260 | PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048) | EACH | 2 | $360.50 | $438.18 | $500.00 | $600.00 | $450.00 |
| 0001-1270 | Symb MRKG fish hook LFT/thru TY B CL II (704SD20-0069) | EACH | 2 | $540.75 | $952.57 | $500.00 | $2,100.00 | $1,500.00 |
| 0001-1280 | PVMT symb MRKG yield 2' X 3' TY A (704SD20-0085) | EACH | 70 | $20.60 | $31.75 | $100.00 | $82.00 | $60.00 |
| 0001-1290 | PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087) | EACH | 20 | $77.25 | $82.56 | $500.00 | $157.00 | $125.00 |
| 0001-1300 | PVMT MSG. mark. “only” TY B, CL II, 8’ (704SD20-0108) | EACH | 1 | $412.00 | $1,397.09 | $2,000.00 | $870.00 | $650.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of September 23, 2026. Compiled by Mirage Metrics.