VDOT contract C0000123290C01 bid tabulation

Roundabout. Let by Virginia DOT on September 23, 2026, Goochland, Richmond. 5 bids received; low bid $5,070,390 by Caton Construction Group, Inc..

Owner
Virginia DOT
Letting
23 SEP 2026
Pay items
130
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Caton Construction Group, Inc.$5,070,390Low
2Curtis Contracting, Inc.$5,132,377+1.0%
3J. R. Caskey, Inc.$5,154,681+2.0%
4Shirley Contracting Company, LLC$6,203,572+22%
5Sagres Construction Corporation$7,125,097+41%
VDOT contract C0000123290C01: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Caton Construction Group, Inc.2. Curtis Contracting, Inc.3. J. R. Caskey, Inc.4. Shirley Contracting Company, LLC5. Sagres Construction Corporation
0001-0010Baseline progress schedule (108SP20-0001)LS1$9,652.68$12,701$50,000$50,750$25,000
0001-0020Progress schedule updates (108SP20-0002)EACH18$1,930.54$1,270.08$350.00$2,000.00$2,500.00
0001-0030Clearing and grubbing (301SD20-0001)LS1$70,292$771,216$250,000$335,000$250,000
0001-0040Endwall EW-12 (302SD20-0013)EACH1$2,608.79$1,270.08$2,500.00$2,500.00$1,750.00
0001-005015" storm sewer pipe (302SD20-0027)LF776$229.23$513.07$350.00$250.00$500.00
0001-006024" conc. pipe (302SD20-0039)LF53$218.49$492.16$425.00$350.00$550.00
0001-007024" storm sewer pipe (302SD20-0041)LF209$218.49$498.86$300.00$350.00$550.00
0001-008030" storm sewer pipe (302SD20-0051)LF53$261.00$531.20$300.00$400.00$800.00
0001-0090Drop inlet DI-2AA (302SD20-0240)EACH2$18,139$21,852$15,000$20,000$17,500
0001-0100Drop inlet DI-2B,L=4' (302SD20-0241)EACH2$16,517$13,155$15,000$20,000$17,000
0001-0110Drop inlet DI-2B,L=6' (302SD20-0242)EACH1$18,088$12,700$15,000$20,000$16,500
0001-0120Drop inlet DI-3B,L=4' (302SD20-0311)EACH2$14,485$11,320$15,000$15,000$16,750
0001-0130Drop inlet DI-3B,L=6' (302SD20-0312)EACH2$16,825$11,861$15,000$15,000$18,500
0001-0140Drop inlet DI-3B,L=8' (302SD20-0313)EACH1$15,318$11,877$15,000$15,000$15,000
0001-0150Drop inlet DI-3B,L=10' (302SD20-0314)EACH1$16,586$21,128$15,000$15,000$15,000
0001-0160Drop inlet DI-3BB,L=6' (302SD20-0321)EACH1$16,820$24,036$20,000$21,000$15,000
0001-0170Drop inlet DI-3CC,L=6' (302SD20-0337)EACH2$16,415$12,645$15,000$20,000$15,000
0001-0180Drop inlet DI-7 (302SD20-0447)EACH1$14,413$12,645$20,264$20,000$20,000
0001-0190Manhole MH-1 or 2 (302SD20-0662)LF11.50$8,339.01$2,003.93$2,000.00$2,500.00$3,500.00
0001-0200Frame & cover MH-1 (302SD20-0663)EACH2$8,889.44$1,237.19$2,000.00$1,750.00$2,000.00
0001-0210Stormwater man.drain.STR.SWM-1 (302SD20-0673)LF6.10$2,045.48$1,483.20$3,500.00$5,000.00$2,500.00
0001-0220Temp. sediment riser pipe 48" (302SD20-0683)LF6.10$3,698.32$1,883.39$2,500.00$1,750.00$3,000.00
0001-0230Regular excavation (303SD20-0001)CY5,035$88.05$63.45$85.00$155.00$85.00
0001-0240Borrow excavation (303SD20-0007)CY6,738$63.28$33.37$45.00$50.00$115.00
0001-0250Temporary diversion dike (303SD20-0021)LF437$23.37$19.51$20.00$30.00$55.00
0001-0260Check dam rock TY. II (303SD20-0023)EACH5$723.08$408.43$850.00$2,000.00$500.00
0001-0270Check dam sediment retention roll 20" (303SD20-0025)EACH3$8.82$349.34$850.00$1,250.00$400.00
0001-0280Dewatering basin EC-8 (303SD20-0028)EACH1$4,803.87$6,078.04$1,500.00$20,000$50,000
0001-0290Siltation control excavation (303SD20-0029)CY7,582.50$1.00$0.66$0.01$4.80$20.00
0001-0300Inlet protection type A (303SD20-0030)EACH1$512.77$1,317.28$1,000.00$500.00$300.00
0001-0310Inlet protection type B (303SD20-0031)EACH14$244.43$362.04$1,000.00$400.00$500.00
0001-0320Geotextile fabric (303SD20-0032)SY4,178$12.79$3.11$5.00$7.00$6.00
0001-0330Temp. silt fence type B (303SD20-0033)LF710$6.72$11.75$15.00$13.00$12.32
0001-0340Temp. silt fence type A (303SD20-0034)LF1,172$16.32$4.89$15.00$13.00$5.51
0001-0350Storm water man. basin excav. (303SD20-0036)CY1,756$208.84$39.97$32.07$80.00$85.00
0001-0360Aggr. matl. no. 21B (308SD20-0007)TON5,003$83.19$50.60$60.00$85.00$75.00
0001-0370Crusher run aggr. no. 25 or 26 (308SX20-0003)TON164$64.28$74.42$90.00$83.00$60.00
0001-0380Tack coat (310SD20-0001)GAL747$2.04$2.54$2.00$12.00$7.50
0001-0390Asphalt concrete TY. SM- 12.5D const (315SD20-0002)TON495$172.45$214.64$260.00$230.00$400.00
0001-0400Asphalt concrete TY. IM- 19.0D const (315SD20-0005)TON422$169.39$210.83$300.00$230.00$375.00
0001-0410Asphalt concrete BM-25.0 (315SD20-0010)TON1,264$160.20$199.40$230.00$234.00$350.00
0001-0420Saw-cut asphalt concrete asphalt saw- cut (315SD20-0104)LF2,875$10.11$6.35$10.00$9.00$5.00
0001-0430Reinf. hydr.cem.conc. pave. 8" (316SD20-0007)SY489$400.00$409.57$850.00$344.00$500.00
0001-0440Cofferdam (401SD20-0007)EACH1$14,306$1,270.08$5,000.00$1,000.00$25,000
0001-0450Erosion CTRL. stone CL. A1, EC-1 (414SD20-0001)TON138.30$284.58$130.63$150.00$230.00$235.18
0001-0460Dry riprap CL. AI (414SD20-0008)TON27$190.27$198.35$150.00$320.00$229.40
0001-0470Underdrain UD-4 (501SD20-0004)LF1,685$63.08$31.75$40.00$65.75$46.36
0001-0480Outlet pipe (501SD20-0009)LF66$71.80$38.10$35.00$47.25$53.94
0001-0490Curb, STD. CG-2 (502SD20-0011)LF416$32.00$59.69$125.00$72.25$120.00
0001-0500Curb, radial CG-2 (502SD20-0012)LF970$64.00$59.69$125.00$70.50$120.00
0001-0510Curb, radial CG-3 (502SD20-0015)LF359$64.00$83.83$125.00$85.25$120.00
0001-0520Comb. curb & gutter, STD. CG-6 (502SD20-0022)LF858$32.00$59.69$125.00$75.25$140.00
0001-0530Comb. curb & gutter, rad. CG-6 (502SD20-0023)LF700$64.00$59.69$125.00$78.00$140.00
0001-0540Comb. curb & gutter, STD. CG-7 (502SD20-0024)LF22$32.00$59.69$125.00$89.00$150.00
0001-0550Comb. curb & gutter, rad. CG-7 (502SD20-0025)LF102$64.00$59.69$125.00$86.50$155.00
0001-0560Median strip MS-1 (502SD20-0053)SY301$300.00$278.98$500.00$348.00$275.00
0001-0570Concrete class A3 misc. (504SD20-0001)CY12.29$3,380.00$1,509.49$1,150.00$2,000.00$3,100.00
0001-0580Guardrail GR-MGS1 (505SD20-0011)LF119$40.00$51.74$55.00$70.00$50.00
0001-0590Guardrail terminal GR- MGS2 (505SD20-0017)EACH1$3,900.00$4,073.40$5,300.00$7,000.00$5,000.00
0001-0600Guardrail end anchorage GR-MGS3 (505SD20-0018)EACH1$1,900.00$4,374.27$2,500.00$3,300.00$2,400.00
0001-0610Guardrail height transition GR-MGS4 (505SD20-0019)EACH2$1,500.00$2,601.12$2,000.00$2,750.00$2,000.00
0001-0620Remove existing guardrail (505SD20-0073)LF366$5.00$19.60$7.00$9.00$10.00
0001-0630BR-GR post attachment various types (505SP20-0013)EACH2$3,000.00$8,524.79$6,500.00$7,500.00$3,800.00
0001-0640Fence FE-CL (507SD20-0005)LF580$34.80$58.42$40.00$58.00$40.00
0001-0650Gate FE-CL 14' (507SD20-0014)EACH1$1,500.00$3,302.22$10,000$4,350.00$2,500.00
0001-0660Demo. of pavement flexible (508SD20-0004)SY4,015$40.86$17.42$18.00$28.00$35.00
0001-0670Allaying dust (511SD20-0001)HR209$11.73$82.56$1.00$90.00$119.59
0001-0680Traffic barrier service MB-11A (512SD20-0003)LF100$85.58$239.56$180.00$160.00$452.45
0001-0690Type 3 barricade 8' (512SD20-0013)EACH17$639.49$900.62$500.00$760.00$231.28
0001-0700Temporary sign (512SD20-0014)SF2,329$18.48$44.45$0.01$80.00$35.08
0001-0710Truck mounted attenuator (512SD20-0023)HR1,016$100.96$63.50$40.00$125.00$35.28
0001-0720Group 2 channelizing devices (512SD20-0024)DAY21,659$0.36$0.67$0.50$3.00$1.09
0001-0730Port.changeable mess. sign (512SD20-0025)HR1,512$12.82$30.00$25.00$11.00$20.00
0001-0740Flagger service (512SD20-0027)HR960$79.25$46.73$125.00$85.00$45.00
0001-0750Traffic barrier ser. conc. MB-7D PC (512SD20-0031)LF140$114.97$118.27$130.00$91.00$350.00
0001-0760Eradicate linear PVMT MRKG (512SD20-0042)LF1,180$2.06$3.81$0.01$3.00$2.17
0001-0770Temp. pave. marker 2 way (512SD20-0045)EACH227$15.45$31.75$6.00$30.00$20.84
0001-0780Temp. PVMT MRKG TY. D, CL. III, 4" (512SD20-0061)LF10,216$3.04$4.89$1.50$4.25$2.94
0001-0790Temp. PVMT MRKG TY. D, CL. III, 6" (512SD20-0062)LF2,334$3.61$5.91$2.50$6.50$4.41
0001-0800Temp. PVMT MRKG TY. D, CL. III, 8" (512SD20-0063)LF184$3.97$11.75$12.00$8.50$5.88
0001-0810Impact attenuator IA-1 (512SD20-0069)EACH1$15,604$34,805$15,000$21,750$36,777
0001-0820Mobilization (513SD20-0001)LS1$250,000$301,540$287,000$340,000$385,000
0001-0830Field office TY.I (514SD20-0001)MO18$9,878.44$4,000.76$4,000.00$7,500.00$8,500.00
0001-0840Flexible pave.planing 0"-2" (515SD20-0004)SY1,832$10.20$12.70$15.00$15.00$25.00
0001-0850Construction surveying constr. (517SD20-0001)LS1$62,200$50,803$125,000$125,200$188,000
0001-0860Topsoil class B (602SD20-0006)CY998$179.00$124.47$50.00$85.00$90.00
0001-0870Temporary seed (603SD20-0002)LB180$15.00$19.05$7.00$9.00$7.00
0001-0880Regular seed (603SD20-0003)LB484$10.00$12.70$7.00$8.00$12.50
0001-0890Overseeding (603SD20-0004)LB387$5.00$6.35$7.00$9.00$12.50
0001-0900Legume seed (603SD20-0005)LB21$10.00$12.70$11.00$65.00$15.00
0001-0910Legume overseeding (603SD20-0006)LB17$15.00$19.05$11.00$65.00$15.00
0001-0920Hydraulic erosion control product type 2 (603SD20-0008)SY10,285$1.25$1.59$1.00$2.00$5.00
0001-0930Hydraulic erosion control product type 3 (603SD20-0009)SY9,317$1.50$1.91$1.00$2.50$5.00
0001-0940Fertilizer nitrogen - N (603SD20-0014)LB180$4.00$5.08$2.00$12.00$7.50
0001-0950Fertilizer phosphorous - P (603SD20-0015)LB126$4.00$5.08$2.00$12.00$7.50
0001-0960Fertilizer potassium - K (603SD20-0016)LB126$4.00$5.08$2.00$12.00$7.50
0001-0970Lime (603SD20-0017)TON10$450.00$571.54$500.00$260.00$612.95
0001-0980Bed preparation (605SD20-0001)UNIT646$25.00$31.75$10.00$50.00$125.00
0001-0990Mulching (605SD20-0002)CY54$100.00$127.01$70.00$185.00$79.68
0001-1000Plant (andropogon gerardii 'blackhawks' #1 cont) (605SD20-0008)EACH79$20.25$25.72$70.00$37.00$245.18
0001-1010Plant (liatris spicata #1 cont) (605SD20-0008)EACH89$10.00$12.70$70.00$19.00$245.18
0001-1020Plant (liriope muscari 'big blue' 2" plug 50 cell) (605SD20-0008)EACH1,529$16.00$20.32$5.00$30.00$91.94
0001-1030Plant (narcissus pseudonarcissus 'king alfred' DN2 bulb) (605SD20-0008)EACH269$31.00$39.37$7.00$57.00$91.94
0001-1040Plant (rudbeckia fulgida 'goldsturm' #1 cont) (605SD20-0008)EACH89$50.00$63.50$70.00$92.00$91.94
0001-1050Plant (schizachyrium scoparium #1 cont) (605SD20-0008)EACH89$50.00$63.50$70.00$92.00$91.94
0001-1060Rolled erosion CTRL product EC-2 type 2 (606SD20-0002)SY163$2.85$3.62$3.00$27.00$6.13
0001-1070Rolled erosion CTRL product EC-3 type 3 (606SD20-0007)SY2,214$4.75$6.03$4.00$7.00$6.13
0001-1080Gabions (610SD20-0001)CY30$577.61$1,215.62$700.00$1,160.00$1,000.00
0001-1090Remove existing 1 post sign structure (700SD20-0003)EACH15$190.00$456.08$1,000.00$220.00$607.37
0001-1100Remove existing 2 post sign structure (700SD20-0004)EACH3$280.00$456.08$1,000.00$3,000.00$607.37
0001-1110Remove existing 3 post sign structure (700SD20-0005)EACH3$400.00$1,265.62$1,000.00$3,000.00$607.37
0001-1120Relocate EX. 1 post GRND mount SGN panel (700SD20-0012)EACH1$175.00$1,199.15$700.16$500.00$936.74
0001-1130Sign post STP-1, 2", 14 gauge (700SD20-0034)LF210$9.00$46.80$50.00$60.00$77.80
0001-1140Sign post STP-1, 2 3/16", 10 gauge (700SD20-0035)LF102$11.00$53.42$35.00$70.00$78.50
0001-1150Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036)LF88$11.00$53.43$35.00$70.00$78.50
0001-1160Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037)LF156$10.00$53.42$35.00$60.00$78.50
0001-1170Conc. found. STP-1, TY. A (700SD20-0038)EACH30$775.00$619.97$600.00$1,000.00$592.08
0001-1180Conc. found. STP-1, TY. B (700SD20-0039)EACH11$820.00$1,237.49$700.00$1,320.00$592.09
0001-1190Sign post STP-2, 4", 8 gauge (700SD20-0200)LF68$72.00$83.08$200.00$230.00$139.17
0001-1200Concrete foundation STP-2, type A (700SD20-0201)EACH3$1,856.00$1,289.11$8,000.00$10,000$2,092.43
0001-1210Concrete foundation STP-2, type H (700SD20-0208)EACH1$1,910.00$1,612.23$10,000$11,000$2,091.02
0001-1220Sign panel (701SD20-0001)SF651$38.00$39.76$75.00$105.00$54.65
0001-1230Type B class I PVMT line MRKG 4" (704SD20-0006)LF1,830$2.06$2.35$5.00$4.00$3.00
0001-1240Type B class I PVMT line MRKG 6" (704SD20-0007)LF1,401$3.09$2.60$5.00$6.00$4.00
0001-1250Type B class I PVMT line MRKG 8" (704SD20-0008)LF65$4.12$12.70$5.00$8.00$6.00
0001-1260PVMT symb MRKG SGL turn arr. TY B CL II (704SD20-0048)EACH2$360.50$438.18$500.00$600.00$450.00
0001-1270Symb MRKG fish hook LFT/thru TY B CL II (704SD20-0069)EACH2$540.75$952.57$500.00$2,100.00$1,500.00
0001-1280PVMT symb MRKG yield 2' X 3' TY A (704SD20-0085)EACH70$20.60$31.75$100.00$82.00$60.00
0001-1290PVMT symb MRKG yield 2' X 3' TY B, CL II (704SD20-0087)EACH20$77.25$82.56$500.00$157.00$125.00
0001-1300PVMT MSG. mark. “only” TY B, CL II, 8’ (704SD20-0108)EACH1$412.00$1,397.09$2,000.00$870.00$650.00
VDOT contract C0000123290C01: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

Every contract let that day: VDOT letting of September 23, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way