Median strip MS-1, VDOT 502SD20-0053
Low bidders on VDOT contracts carried a median of $253.69 per SY for this item, over the 24 months to 28 OCT 2026, across 28 low bids. Half of all 77 bids fell between $180.00 and $321.50.
- Owner
- Virginia DOT
- Item
- 502SD20-0053
- Unit
- SY
- Data through
- 28 OCT 2026
VDOT prints this item as “MEDIAN STRIP MS-1”.
VDOT has bid this work under more than one code: 21020 on lettings from 23 APR 2002 to 17 NOV 2021 (404 bids); 502SD20-0053 on lettings from 19 NOV 2025 to 23 SEP 2026 (77 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 8 | 8 | $44.83 | 21 | $47.65 |
| 2003 | 6 | 5 | $71.59 | 12 | $60.50 |
| 2004 | 6 | 6 | $64.38 | 14 | $50.00 |
| 2005 | 4 | 4 | $69.00 | 11 | $65.00 |
| 2006 | 6 | 6 | $68.50 | 16 | $78.50 |
| 2007 | 5 | 5 | $56.17 | 14 | $65.75 |
| 2008 | 9 | 9 | $88.00 | 26 | $92.40 |
| 2009 | 6 | 6 | $61.10 | 17 | $67.20 |
| 2010 | 6 | 6 | $58.50 | 18 | $60.00 |
| 2011 | 8 | 8 | $78.47 | 24 | $84.12 |
| 2012 | 7 | 7 | $90.00 | 20 | $90.00 |
| 2013 | 9 | 9 | $80.00 | 25 | $80.00 |
| 2014 | 13 | 13 | $94.00 | 38 | $96.60 |
| 2015 | 5 | 4 | $100.00 | 13 | $92.00 |
| 2016 | 8 | 8 | $113.64 | 21 | $114.00 |
| 2017 | 8 | 8 | $150.84 | 21 | $148.00 |
| 2018 | 6 | 6 | $180.77 | 15 | $217.48 |
| 2019 | 6 | 6 | $120.00 | 18 | $128.93 |
| 2020 | 13 | 13 | $150.00 | 33 | $130.00 |
| 2021 | 10 | 10 | $170.20 | 26 | $150.00 |
| 2025 | 5 | 5 | $270.00 | 13 | $260.37 |
| 2026 | 23 | 23 | $211.00 | 64 | $240.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 3 | $195.00 | 13 | $240.00 |
| Richmond | 5 | $305.00 | 13 | $305.00 |
| Salem | 3 | $247.00 | 10 | $232.10 |
| Bristol | 3 | $190.00 | 8 | $220.43 |
| Staunton | 4 | $196.59 | 8 | $176.36 |
| Culpeper | 3 | $158.55 | 7 | $150.00 |
| Lynchburg | 3 | $185.00 | 6 | $199.75 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 4 to 66 | 7 | $325.00 |
| 119 to 169.80 | 7 | $185.00 |
| 172 to 393 | 7 | $300.00 |
| 433 to 800 | 7 | $195.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Blakemore Construction Corporation | 16 | 8 (50%) |
| General Excavation, Inc. | 14 | 7 (50%) |
| Tavares Concrete Co., Inc. | 10 | 6 (60%) |
| Phillip C. Clarke Electrical Contractor, Inc. | 10 | 6 (60%) |
| Curtis Contracting, Inc. | 14 | 5 (36%) |
| Howard Brothers Contractor, Inc. | 12 | 5 (42%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 23 SEP 2026 | C0000123290C01 | Richmond | 301 | $300.00 | $300.00 | 5 | Caton Construction Group, Inc. | VDOT |
| 26 AUG 2026 | C0000119687C01B | Richmond | 154 | $600.00 | $396.25 | 2 | Gray and Sons Construction, Inc. | VDOT |
| 26 AUG 2026 | C0000115512C01 | Hampton Roads | 4 | $300.00 | $500.00 | 3 | Allan Myers Va, Inc. | VDOT |
| 22 JUL 2026 | C0000119641C02 | Staunton | 800 | $182.18 | $176.36 | 2 | G. B. Foltz Contracting, Inc. | VDOT |
| 22 JUL 2026 | C0000119114C01 | Northern Virginia | 569 | $195.00 | $185.00 | 2 | A & M Concrete Corp. | VDOT |
| 22 JUL 2026 | C0000126560B40 | Northern Virginia | 123 | $176.00 | $240.00 | 7 | Martins Construction Corp. | VDOT |
| 22 JUL 2026 | C0000120611C01 | Salem | 673 | $379.00 | $379.00 | 1 | Branch Civil, Inc. | VDOT |
| 22 JUL 2026 | C0000120748C01 | Culpeper | 383 | $141.00 | $145.51 | 4 | General Excavation, Inc. | VDOT |
| 22 JUL 2026 | C0000115403C01C | Richmond | 283 | $305.00 | $305.00 | 3 | MCC ACQUISITION, LC dba VIRGINIA-CAROLINA | VDOT |
| 24 JUN 2026 | C0000108810C01 | Staunton | 66 | $130.00 | $130.00 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 24 JUN 2026 | C0000115470C01 | Bristol | 393 | $140.66 | $170.33 | 2 | W-L Construction & Paving, Inc. | VDOT |
| 24 JUN 2026 | C0000115715C01 | Staunton | 433 | $211.00 | $208.00 | 2 | A & J Development and Excavation, Inc. | VDOT |
| 27 MAY 2026 | C0000119644C01 | Staunton | 47 | $650.00 | $400.00 | 2 | Arthur Construction Co., Inc. | VDOT |
| 27 MAY 2026 | C0000119458C01 | Salem | 440 | $135.25 | $181.34 | 6 | Branch Civil, Inc. | VDOT |
| 27 MAY 2026 | C0000113412C01B | Fredericksburg | 169.80 | $180.00 | $297.06 | 4 | Allan Myers Va, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.