Comb. curb & gutter, STD. CG-7, VDOT 502SD20-0024
Low bidders on VDOT contracts carried a median of $54.78 per LF for this item, over the 24 months to 28 OCT 2026, across 22 low bids. Half of all 73 bids fell between $51.45 and $120.00.
- Owner
- Virginia DOT
- Item
- 502SD20-0024
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “COMB. CURB & GUTTER, STD. CG-7”.
VDOT has bid this work under more than one code: 12700 on lettings from 29 JAN 2002 to 15 DEC 2021 (674 bids); 502SD20-0024 on lettings from 22 OCT 2025 to 23 SEP 2026 (73 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 7 | 7 | $13.00 | 21 | $13.00 |
| 2003 | 3 | 3 | $12.00 | 9 | $15.40 |
| 2004 | 5 | 5 | $13.00 | 13 | $15.00 |
| 2005 | 7 | 7 | $15.90 | 19 | $18.00 |
| 2006 | 9 | 9 | $20.00 | 25 | $20.00 |
| 2007 | 6 | 6 | $21.40 | 16 | $21.50 |
| 2008 | 5 | 5 | $16.00 | 15 | $17.00 |
| 2009 | 10 | 10 | $16.48 | 29 | $17.00 |
| 2010 | 13 | 13 | $18.00 | 39 | $18.46 |
| 2011 | 13 | 13 | $19.50 | 39 | $20.00 |
| 2012 | 19 | 19 | $22.00 | 54 | $24.50 |
| 2013 | 19 | 19 | $23.00 | 51 | $25.00 |
| 2014 | 30 | 30 | $31.80 | 79 | $28.60 |
| 2015 | 18 | 18 | $30.61 | 50 | $30.00 |
| 2016 | 31 | 30 | $38.00 | 76 | $40.00 |
| 2017 | 8 | 8 | $33.50 | 21 | $32.00 |
| 2018 | 9 | 9 | $35.00 | 24 | $40.00 |
| 2019 | 13 | 13 | $30.32 | 35 | $35.00 |
| 2020 | 16 | 16 | $55.04 | 40 | $51.50 |
| 2021 | 7 | 7 | $35.00 | 19 | $35.00 |
| 2025 | 3 | 3 | $95.00 | 14 | $115.00 |
| 2026 | 19 | 19 | $53.00 | 59 | $60.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 6 | $95.38 | 24 | $108.00 |
| Fredericksburg | 3 | $51.80 | 11 | $70.00 |
| Northern Virginia | 3 | $25.00 | 9 | $55.00 |
Districts with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 20 to 50 | 5 | $32.00 |
| 100 to 482 | 6 | $83.69 |
| 529 to 1,050 | 5 | $53.00 |
| 1,100 to 1,778 | 6 | $54.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Fielder'S Choice Enterprises, Inc. | 18 | 14 (78%) |
| M & F Concrete, Inc. | 18 | 12 (67%) |
| Fort Myer Construction Corporation | 24 | 9 (38%) |
| Branscome Inc. | 17 | 9 (53%) |
| B & B Signal Co., L.L.C. | 12 | 8 (67%) |
| Tavares Concrete Co., Inc. | 10 | 8 (80%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.