VDOT contract C0000128731N01 bid tabulation
On-call - ada curb ramp improvements. Let by Virginia DOT on June 24, 2026, Richmond, Fredericksburg. 4 bids received; low bid $331,715 by North Construction, Inc..
- Owner
- Virginia DOT
- Letting
- 24 JUN 2026
- Pay items
- 27
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | North Construction, Inc. | $331,715 | Low |
| 2 | M & F Concrete, Inc. | $414,327 | +25% |
| 3 | Arthur Construction Co., Inc. | $498,095 | +50% |
| 4 | Finley Asphalt & Sealing, Inc. | $626,941 | +89% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. North Construction, Inc. | 2. M & F Concrete, Inc. | 3. Arthur Construction Co., Inc. | 4. Finley Asphalt & Sealing, Inc. |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Siltation control excavation (303SD20-0029) | CY | 50 | $10.00 | $1.00 | $25.00 | $35.00 |
| 0001-0020 | Inlet protection type B (303SD20-0031) | EACH | 25 | $90.00 | $300.00 | $250.00 | $350.00 |
| 0001-0030 | NS aggregate material base matl.TY. I or II no. 21A or 21B (305SX20-0002) | TON | 200 | $50.00 | $60.00 | $60.00 | $60.00 |
| 0001-0040 | Saw-cut asphalt concrete . (315SD20-0104) | LF | 200 | $2.00 | $7.00 | $10.00 | $6.00 |
| 0001-0050 | NS pavement restoration (315SX20-0005) | TON | 25 | $100.00 | $300.00 | $300.00 | $350.00 |
| 0001-0060 | Curb, STD. CG-2 (502SD20-0011) | LF | 800 | $50.00 | $49.00 | $55.00 | $110.56 |
| 0001-0070 | Curb, radial CG-2 (502SD20-0012) | LF | 300 | $50.00 | $49.00 | $55.00 | $110.56 |
| 0001-0080 | Curb, STD. CG-3 (502SD20-0014) | LF | 100 | $35.00 | $42.00 | $35.00 | $110.56 |
| 0001-0090 | Curb, radial CG-3 (502SD20-0015) | LF | 100 | $35.00 | $42.00 | $35.00 | $110.56 |
| 0001-0100 | Comb. curb & gutter, STD. CG-6 (502SD20-0022) | LF | 100 | $60.00 | $52.00 | $65.00 | $110.56 |
| 0001-0110 | Comb. curb & gutter, rad. CG-6 (502SD20-0023) | LF | 250 | $60.00 | $52.00 | $65.00 | $110.56 |
| 0001-0120 | Comb. curb & gutter, STD. CG-7 (502SD20-0024) | LF | 50 | $45.00 | $52.00 | $65.00 | $110.56 |
| 0001-0130 | Comb. curb & gutter, rad. CG-7 (502SD20-0025) | LF | 1,000 | $45.00 | $52.00 | $65.00 | $110.56 |
| 0001-0140 | CG-12 detectable warning surface (504SD20-0002) | SY | 175 | $420.00 | $585.00 | $225.00 | $200.00 |
| 0001-0150 | Hydr. cement conc. sidewalk 4" (504SD20-0003) | SY | 200 | $85.00 | $101.25 | $171.00 | $169.98 |
| 0001-0160 | Concrete class A-3 misc (504SD20-0010) | CY | 20 | $200.00 | $600.00 | $1,500.00 | $1,000.00 |
| 0001-0170 | Remove comb. curb and gutter (510SX20-0002) | LF | 1,000 | $20.00 | $20.00 | $125.00 | $10.00 |
| 0001-0180 | NS remove exist. hydraulic cement concrete (510SX20-0038) | SY | 600 | $25.00 | $45.00 | $18.00 | $27.00 |
| 0001-0190 | Type 3 barricade 4' (512SD20-0012) | EACH | 40 | $250.00 | $200.00 | $500.00 | $517.50 |
| 0001-0200 | Truck mounted attenuator (512SD20-0023) | HR | 500 | $15.00 | $35.00 | $5.00 | $97.75 |
| 0001-0210 | Group 2 channelizing devices (512SD20-0024) | DAY | 1,500 | $0.25 | $2.00 | $1.00 | $1.15 |
| 0001-0220 | Port.changeable mess. sign (512SD20-0025) | HR | 144 | $10.00 | $8.00 | $5.00 | $92.00 |
| 0001-0230 | Electronic arrow board (512SD20-0026) | HR | 500 | $5.00 | $25.00 | $3.00 | $92.00 |
| 0001-0240 | Flagger service (512SD20-0027) | HR | 200 | $40.00 | $60.00 | $50.00 | $65.00 |
| 0001-0250 | NS mobilization task order over $50,000 (richmond districtwide) (513SX20-0001) | EACH | 4 | $5,000.00 | $2,500.00 | $3,500.00 | $5,000.00 |
| 0001-0260 | NS mobilization task order under $50,000 (richmond districtwide) (513SX20-0001) | EACH | 1 | $5,000.00 | $2,500.00 | $15,000 | $7,500.00 |
| 0001-0270 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 100 | $15.00 | $25.00 | $60.00 | $97.35 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of June 24, 2026. Compiled by Mirage Metrics.