NS excavation of additional unsuitable material, VDOT 303SX20-0003
Low bidders on VDOT contracts carried a median of $43.00 per CY for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 1 bids fell between $43.00 and $43.00.
- Owner
- Virginia DOT
- Item
- 303SX20-0003
- Unit
- CY
- Data through
- 28 OCT 2026
VDOT prints this item as “NS EXCAVATION OF ADDITIONAL UNSUITABLE MATERIAL”.
VDOT has bid this work under more than one code: 118 on lettings from 16 DEC 2003 to 22 SEP 2021 (210 bids); 303SX20-0003 on lettings from 19 NOV 2025 to 19 NOV 2025 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2003 | 1 | 1 | $20.00 | 3 | $18.00 |
| 2004 | 5 | 6 | $75.00 | 10 | $125.00 |
| 2005 | 1 | 1 | $62.42 | 2 | $39.46 |
| 2006 | 2 | 2 | $101.80 | 4 | $162.50 |
| 2007 | 2 | 2 | $34.75 | 6 | $26.25 |
| 2008 | 1 | 4 | $32.50 | 12 | $28.25 |
| 2009 | 1 | 1 | $257.00 | 2 | $206.00 |
| 2010 | 3 | 3 | $9.75 | 6 | $26.62 |
| 2011 | 3 | 5 | $27.90 | 17 | $33.00 |
| 2012 | 1 | 1 | $57.00 | 2 | $74.50 |
| 2013 | 4 | 5 | $22.20 | 14 | $32.50 |
| 2014 | 4 | 4 | $29.75 | 12 | $30.00 |
| 2015 | 7 | 10 | $19.00 | 27 | $25.00 |
| 2016 | 5 | 7 | $54.10 | 17 | $50.00 |
| 2017 | 3 | 5 | $70.00 | 15 | $68.00 |
| 2018 | 5 | 5 | $51.00 | 14 | $50.50 |
| 2019 | 6 | 7 | $28.00 | 17 | $40.00 |
| 2020 | 7 | 6 | $40.00 | 17 | $43.00 |
| 2021 | 4 | 4 | $64.00 | 11 | $75.00 |
| 2025 | 1 | 1 | $43.00 | 1 | $43.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 20 | $45.00 | 57 | $50.00 |
| Staunton | 14 | $26.50 | 41 | $25.00 |
| Culpeper | 15 | $33.00 | 35 | $32.00 |
| Salem | 8 | $41.27 | 20 | $37.50 |
| Hampton Roads | 8 | $82.50 | 17 | $75.00 |
| Richmond | 6 | $27.75 | 16 | $30.88 |
| Fredericksburg | 5 | $13.69 | 12 | $27.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 3.90 to 85 | 20 | $59.55 |
| 95 to 421 | 20 | $35.89 |
| 446 to 2,320 | 20 | $34.00 |
| 2,441 to 20,000 | 20 | $29.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Fielder'S Choice Enterprises, Inc. | 11 | 7 (64%) |
| Arthur Construction Co., Inc. | 11 | 6 (55%) |
| Curtis Contracting, Inc. | 7 | 5 (71%) |
| Key Construction Company, Incorporated | 6 | 4 (67%) |
| General Excavation, Inc. | 11 | 2 (18%) |
| Commonwealth Excavating, Inc. | 8 | 2 (25%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 19 NOV 2025 | C0000127206B17 | Culpeper | 28 | $43.00 | $43.00 | 1 | Freyssinet, Inc. | VDOT |
| 22 SEP 2021 | C0000119382N01 | Northern Virginia | 25 | $400.00 | $300.00 | 2 | L. S. Lee, Inc. | VDOT |
| 24 MAR 2021 | C00000118232N01 | Northern Virginia | 300 | $78.00 | $78.00 | 3 | Fort Myer Construction Corporation | VDOT |
| 24 MAR 2021 | C0000117337N01 | Northern Virginia | 2,320 | $37.50 | $40.00 | 3 | Stuart M. Perry, Incorporated | VDOT |
| 20 JAN 2021 | CM820BRA117425 | Staunton | 3.90 | $50.00 | $50.00 | 3 | Jones Road & Bridge, Inc. | VDOT |
| 23 SEP 2020 | C0000109321C01 | Richmond | 2,000 | $38.00 | $35.25 | 2 | Allan Myers Va, Inc. | VDOT |
| 22 JUL 2020 | C0000000116664 | Hampton Roads | 10 | $90.00 | $95.00 | 2 | M & F Concrete, Inc. | VDOT |
| 22 JUL 2020 | C0000109440C01 | Bristol | 95 | $40.00 | $41.85 | 2 | Jones Road & Bridge, Inc. | VDOT |
| 25 MAR 2020 | C0000109466M01 | Fredericksburg | 107 | $25.00 | $25.00 | 3 | Howard Brothers Contractor, Inc. | VDOT |
| 26 FEB 2020 | C0000115929N01 | Northern Virginia | 122 | n/a | $52.50 | 2 | Allan Myers Va, Inc. | VDOT |
| 22 JAN 2020 | C0000116047N01 | Northern Virginia | 4,762 | $40.00 | $43.00 | 3 | Arthur Construction Co., Inc. | VDOT |
| 22 JAN 2020 | C0000116048N01 | Northern Virginia | 9,093 | $40.00 | $43.00 | 3 | Arthur Construction Co., Inc. | VDOT |
| 18 DEC 2019 | C000109286M501 | Salem | 114 | $10.00 | $10.00 | 3 | James R. Vannoy & Sons Construction Company, Inc. | VDOT |
| 23 OCT 2019 | C0000105108D07 | Richmond | 1,187 | $28.00 | $29.25 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 22 MAY 2019 | C000114573N01B | Culpeper | 20 | $12.00 | $81.00 | 2 | S. B. Cox, Incorporated | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way