NS excavation of additional unsuitable material, VDOT 303SX20-0003

Low bidders on VDOT contracts carried a median of $43.00 per CY for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 1 bids fell between $43.00 and $43.00.

Owner
Virginia DOT
Item
303SX20-0003
Unit
CY
Data through
28 OCT 2026

VDOT prints this item as “NS EXCAVATION OF ADDITIONAL UNSUITABLE MATERIAL”.

VDOT has bid this work under more than one code: 118 on lettings from 16 DEC 2003 to 22 SEP 2021 (210 bids); 303SX20-0003 on lettings from 19 NOV 2025 to 19 NOV 2025 (2 bids). They are combined here into one trend.

$43.00Low bidder's median, per CY
$43.00Median of all bids, per CY
1Contracts in the window

By year of letting

NS excavation of additional unsuitable material, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200311$20.003$18.00
200456$75.0010$125.00
200511$62.422$39.46
200622$101.804$162.50
200722$34.756$26.25
200814$32.5012$28.25
200911$257.002$206.00
201033$9.756$26.62
201135$27.9017$33.00
201211$57.002$74.50
201345$22.2014$32.50
201444$29.7512$30.00
2015710$19.0027$25.00
201657$54.1017$50.00
201735$70.0015$68.00
201855$51.0014$50.50
201967$28.0017$40.00
202076$40.0017$43.00
202144$64.0011$75.00
202511$43.001$43.00

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northern Virginia20$45.0057$50.00
Staunton14$26.5041$25.00
Culpeper15$33.0035$32.00
Salem8$41.2720$37.50
Hampton Roads8$82.5017$75.00
Richmond6$27.7516$30.88
Fredericksburg5$13.6912$27.50
NS excavation of additional unsuitable material, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (CY)Low bidsLow-bid median
3.90 to 8520$59.55
95 to 42120$35.89
446 to 2,32020$34.00
2,441 to 20,00020$29.00
NS excavation of additional unsuitable material, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Fielder'S Choice Enterprises, Inc.117 (64%)
Arthur Construction Co., Inc.116 (55%)
Curtis Contracting, Inc.75 (71%)
Key Construction Company, Incorporated64 (67%)
General Excavation, Inc.112 (18%)
Commonwealth Excavating, Inc.82 (25%)
NS excavation of additional unsuitable material, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
19 NOV 2025C0000127206B17Culpeper28$43.00$43.001Freyssinet, Inc.VDOT
22 SEP 2021C0000119382N01Northern Virginia25$400.00$300.002L. S. Lee, Inc.VDOT
24 MAR 2021C00000118232N01Northern Virginia300$78.00$78.003Fort Myer Construction CorporationVDOT
24 MAR 2021C0000117337N01Northern Virginia2,320$37.50$40.003Stuart M. Perry, IncorporatedVDOT
20 JAN 2021CM820BRA117425Staunton3.90$50.00$50.003Jones Road & Bridge, Inc.VDOT
23 SEP 2020C0000109321C01Richmond2,000$38.00$35.252Allan Myers Va, Inc.VDOT
22 JUL 2020C0000000116664Hampton Roads10$90.00$95.002M & F Concrete, Inc.VDOT
22 JUL 2020C0000109440C01Bristol95$40.00$41.852Jones Road & Bridge, Inc.VDOT
25 MAR 2020C0000109466M01Fredericksburg107$25.00$25.003Howard Brothers Contractor, Inc.VDOT
26 FEB 2020C0000115929N01Northern Virginia122n/a$52.502Allan Myers Va, Inc.VDOT
22 JAN 2020C0000116047N01Northern Virginia4,762$40.00$43.003Arthur Construction Co., Inc.VDOT
22 JAN 2020C0000116048N01Northern Virginia9,093$40.00$43.003Arthur Construction Co., Inc.VDOT
18 DEC 2019C000109286M501Salem114$10.00$10.003James R. Vannoy & Sons Construction Company, Inc.VDOT
23 OCT 2019C0000105108D07Richmond1,187$28.00$29.253Burleigh Construction Co., Inc.VDOT
22 MAY 2019C000114573N01BCulpeper20$12.00$81.002S. B. Cox, IncorporatedVDOT
Latest VDOT contracts carrying NS excavation of additional unsuitable material

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy