Temp. pave. marker 1 way, VDOT 512SD20-0044

Low bidders on VDOT contracts carried a median of $19.52 per EACH for this item, over the 24 months to 28 OCT 2026, across 12 low bids. Half of all 37 bids fell between $12.78 and $30.00.

Owner
Virginia DOT
Item
512SD20-0044
Unit
EACH
Data through
28 OCT 2026

VDOT has bid this work under more than one code: 54240 on lettings from 29 JAN 2002 to 15 DEC 2021 (963 bids); 512SD20-0044 on lettings from 22 OCT 2025 to 23 SEP 2026 (37 bids). They are combined here into one trend.

$19.52Low bidder's median, per EACH
$19.13Median of all bids, per EACH
12Contracts in the window

By year of letting

Temp. pave. marker 1 way, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20022828$5.2881$5.30
20033231$5.0084$5.25
20043030$5.0076$5.00
20053535$5.4589$5.00
20062020$5.0055$6.10
20071919$6.1051$5.75
20082020$7.3154$6.09
20091616$5.3546$5.58
201099$3.3023$6.20
20111514$6.7240$6.70
20121212$4.9232$5.83
20132522$4.8853$5.00
20142323$5.5953$6.70
20151717$11.0046$11.00
20161311$12.6033$12.60
20171111$10.5032$12.50
201899$11.8521$12.00
201999$12.5023$11.67
202099$11.5026$11.75
20211212$11.9329$12.00
202544$19.0015$23.00
202688$19.5222$19.09

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
7 to 663$35.00
78 to 1003$20.00
301 to 5003$15.00
1,131 to 1,8603$15.50
Temp. pave. marker 1 way, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Cleco Corporation5832 (55%)
Elk Knob, Inc.4622 (48%)
Lanford Brothers Company, Incorporated7218 (25%)
Burleigh Construction Co., Inc.3412 (35%)
W-L Construction & Paving, Inc.2111 (52%)
General Excavation, Inc.2010 (50%)
Temp. pave. marker 1 way, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
23 SEP 2026C0000119597C01BRichmond1,282$19.05$19.051Curtis Contracting, Inc.VDOT
26 AUG 2026C0000129131C01BRichmond54$104.47$102.232Caton Construction Group, Inc.VDOT
22 JUL 2026C0000119468M01Salem80$5.79$15.392E. C. Pace Company, Inc.VDOT
22 JUL 2026C0000122360M01Fredericksburg1,860$15.50$16.256Martins Construction Corp.VDOT
24 JUN 2026C0000128696N01Staunton78$50.00$50.003Lanford Brothers Company, IncorporatedVDOT
27 MAY 2026CM527PMZ128662Hampton Roads453$15.00$16.752Allan Myers Va, Inc.VDOT
25 FEB 2026C0000125982C01Culpeper100$20.00$14.914EUROVIA ATLANTIC COAST LLC dba VIRGINIAVDOT
04 FEB 2026C0000119190C01Richmond66$30.00$24.002Gray and Sons Construction, Inc.VDOT
17 DEC 2025C0000126197N01Lynchburg500$26.00$23.253Superior Paving CorporationVDOT
17 DEC 2025C0000119452C50Salem7$35.00$35.005Crossroads Bridge IncVDOT
19 NOV 2025C0000116160B01Bristol301$12.00$12.003Caton Construction Group, Inc.VDOT
22 OCT 2025C0000118396B57Northern Virginia1,131$8.50$9.754Martins Construction Corp.VDOT
15 DEC 2021C0000118581C01Richmond21$25.00$25.001Shirley Contracting Company, LLCVDOT
27 OCT 2021C0000119068B29Hampton Roads345$10.00$10.503Curtis Contracting, Inc.VDOT
22 SEP 2021C0000110621D16Salem52$14.00$12.003F & B Contractors, LTD.VDOT
Latest VDOT contracts carrying Temp. pave. marker 1 way

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy