VDOT contract C0000125982C01 bid tabulation
Roadway safety improvements. Let by Virginia DOT on February 25, 2026, Fauquier, Culpeper. 4 bids received; low bid $1,286,704 by EUROVIA ATLANTIC COAST LLC dba VIRGINIA.
- Owner
- Virginia DOT
- Letting
- 25 FEB 2026
- Pay items
- 50
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | EUROVIA ATLANTIC COAST LLC dba VIRGINIA | $1,286,704 | Low |
| 2 | Independence Excavating, Inc. | $1,298,826 | +1.0% |
| 3 | General Excavation, Inc. | $1,433,306 | +11% |
| 4 | Sagres Construction Corporation | $1,593,486 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. EUROVIA ATLANTIC COAST LLC dba VIRGINIA | 2. Independence Excavating, Inc. | 3. General Excavation, Inc. | 4. Sagres Construction Corporation |
|---|---|---|---|---|---|---|---|
| 0001-0010 | Regular excavation (303SD20-0001) | CY | 900 | $85.00 | $173.00 | $100.00 | $148.30 |
| 0001-0020 | Borrow excavation (303SD20-0007) | CY | 1,660 | $65.00 | $95.00 | $120.00 | $106.27 |
| 0001-0030 | Erosion control mulch (303SD20-0019) | SY | 550 | $0.95 | $1.00 | $8.00 | $9.05 |
| 0001-0040 | Check dam rock TY. II (303SD20-0023) | EACH | 8 | $600.00 | $1,500.00 | $730.00 | $1,107.30 |
| 0001-0050 | Siltation control excavation (303SD20-0029) | CY | 85 | $20.00 | $60.00 | $20.00 | $17.40 |
| 0001-0060 | Inlet protection type A (303SD20-0030) | EACH | 1 | $510.00 | $800.00 | $1,050.00 | $171.51 |
| 0001-0070 | Temp. silt fence type A (303SD20-0034) | LF | 390 | $4.25 | $12.00 | $6.00 | $4.03 |
| 0001-0080 | Aggr. matl. no. 21A (308SD20-0003) | TON | 274 | $115.00 | $100.00 | $85.00 | $58.79 |
| 0001-0090 | Asphalt concrete TY. SM- 12.5E const (315SD20-0003) | TON | 1,065 | $155.00 | $165.00 | $195.00 | $203.17 |
| 0001-0100 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 462 | $200.00 | $166.00 | $191.00 | $203.17 |
| 0001-0110 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 3,396 | $3.80 | $3.00 | $3.50 | $5.47 |
| 0001-0120 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 366 | $10.00 | $6.00 | $9.00 | $4.91 |
| 0001-0130 | NS pavement high friction epoxy overlay (315SX20-0004) | SY | 6,685 | $33.35 | $24.00 | $34.00 | $41.65 |
| 0001-0140 | Guardrail GR-MGS1 (505SD20-0011) | LF | 360 | $45.00 | $85.00 | $41.00 | $48.88 |
| 0001-0150 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 2 | $4,400.00 | $4,000.00 | $5,190.00 | $4,783.31 |
| 0001-0160 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 2 | $1,450.00 | $2,000.00 | $2,305.00 | $1,571.16 |
| 0001-0170 | Remove existing guardrail (505SD20-0073) | LF | 414 | $11.60 | $13.00 | $12.00 | $12.57 |
| 0001-0180 | Demo. of pavement flexible (508SD20-0004) | SY | 167 | $21.25 | $78.00 | $33.00 | $7.06 |
| 0001-0190 | Allaying dust (511SD20-0001) | HR | 100 | $117.50 | $80.00 | $111.00 | $25.00 |
| 0001-0200 | Temporary sign (512SD20-0014) | SF | 116 | $81.50 | $20.00 | $50.00 | $39.04 |
| 0001-0210 | Truck mounted attenuator (512SD20-0023) | HR | 480 | $57.25 | $35.00 | $58.00 | $55.24 |
| 0001-0220 | Group 2 channelizing devices (512SD20-0024) | DAY | 12,000 | $1.00 | $0.20 | $2.50 | $1.22 |
| 0001-0230 | Port.changeable mess. sign (512SD20-0025) | HR | 672 | $10.00 | $12.00 | $14.00 | $80.00 |
| 0001-0240 | Electronic arrow board (512SD20-0026) | HR | 480 | $3.00 | $8.00 | $5.50 | $2.44 |
| 0001-0250 | Temp. pave. marker 1 way (512SD20-0044) | EACH | 100 | $20.00 | $9.00 | $23.00 | $9.82 |
| 0001-0260 | Temp. PVMT MRKG TY. A, 6" (512SD20-0047) | LF | 22,205 | $0.65 | $0.40 | $0.65 | $0.49 |
| 0001-0270 | Mobilization (513SD20-0001) | LS | 1 | $100,000 | $135,000 | $101,500 | $328,691 |
| 0001-0280 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 8,777 | $5.25 | $5.00 | $6.70 | $7.06 |
| 0001-0290 | Construction surveying constr. (517SD20-0001) | LS | 1 | $163,500 | $100,000 | $122,200 | $13,258 |
| 0001-0300 | Topsoil class A 2" (602SD20-0001) | ACRE | 1 | $40,000 | $18,000 | $38,800 | $22,847 |
| 0001-0310 | Temporary seed (603SD20-0002) | LB | 145 | $21.50 | $10.00 | $14.00 | $5.22 |
| 0001-0320 | Regular seed (603SD20-0003) | LB | 300 | $10.00 | $6.00 | $8.00 | $7.06 |
| 0001-0330 | Overseeding (603SD20-0004) | LB | 240 | $15.00 | $8.00 | $8.00 | $9.34 |
| 0001-0340 | Legume seed (603SD20-0005) | LB | 6 | $53.00 | $20.00 | $17.00 | $8.16 |
| 0001-0350 | Legume overseeding (603SD20-0006) | LB | 5 | $92.50 | $21.00 | $17.00 | $10.45 |
| 0001-0360 | Hydraulic erosion control product type 1 (603SD20-0007) | SY | 363 | $0.50 | $0.50 | $0.25 | $0.31 |
| 0001-0370 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 6,050 | $0.75 | $0.60 | $0.50 | $0.55 |
| 0001-0380 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 4,840 | $1.00 | $0.80 | $0.75 | $0.80 |
| 0001-0390 | Fertilizer nitrogen - N (603SD20-0014) | LB | 100 | $13.50 | $2.00 | $1.40 | $1.29 |
| 0001-0400 | Fertilizer phosphorous - P (603SD20-0015) | LB | 70 | $8.25 | $1.50 | $1.40 | $1.29 |
| 0001-0410 | Fertilizer potassium - K (603SD20-0016) | LB | 70 | $8.25 | $2.00 | $1.40 | $1.29 |
| 0001-0420 | Lime (603SD20-0017) | TON | 6 | $650.00 | $300.00 | $300.00 | $368.28 |
| 0001-0430 | NS landscape vegetation establishment (605SX20-0013) | LS | 1 | $2.65 | $22,000 | $24,300 | $12,276 |
| 0001-0440 | Rolled erosion CTRL product EC-2 type 1 (606SD20-0001) | SY | 1,389 | $8.25 | $20.00 | $7.50 | $1.62 |
| 0001-0450 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 1 | $205.00 | $200.00 | $186.00 | $328.98 |
| 0001-0460 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 9 | $30.00 | $30.00 | $28.00 | $19.36 |
| 0001-0470 | Conc. found. STP-1, TY. D (700SD20-0041) | EACH | 1 | $5,850.00 | $5,000.00 | $5,308.00 | $417.28 |
| 0001-0480 | Sign panel (701SD20-0001) | SF | 5 | $60.00 | $60.00 | $55.00 | $64.95 |
| 0001-0490 | Type B class VI PVMT line MRKG 6" (704SD20-0027) | LF | 4,427 | $9.00 | $6.00 | $8.50 | $6.43 |
| 0001-0500 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 24 | $380.00 | $130.00 | $344.00 | $153.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of February 25, 2026. Compiled by Mirage Metrics.