VDOT contract C0000126197N01 bid tabulation
2026 plant mix - primary / rubblization. Let by Virginia DOT on December 17, 2025, Appomattox, Lynchburg. 3 bids received; low bid $8,668,920 by Superior Paving Corporation.
- Owner
- Virginia DOT
- Letting
- 17 DEC 2025
- Pay items
- 91
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Paving Corporation | $8,668,920 | Low |
| 2 | Adams Construction Company | $9,699,044 | +12% |
| 3 | White'S Construction Company, Inc. | $10,797,401 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Paving Corporation | 2. Adams Construction Company | 3. White'S Construction Company, Inc. |
|---|---|---|---|---|---|---|
| 0001-0010 | Endwall EW-12 (302SD20-0013) | EACH | 12 | $3,275.00 | $4,939.70 | $3,250.00 |
| 0001-0020 | 15" pipe (302SD20-0023) | LF | 30 | $365.00 | $1,220.40 | $1,050.00 |
| 0001-0030 | Drop inlet DI-13 TY.I (302SD20-0655) | EACH | 6 | $9,200.00 | $10,461 | $9,000.00 |
| 0001-0040 | Undercut excavation (303SD20-0002) | CY | 275 | $40.00 | $75.55 | $65.00 |
| 0001-0050 | Grading (303SD20-0004) | LS | 1 | $975,000 | $643,469 | $894,625 |
| 0001-0060 | Siltation control excavation (303SD20-0029) | CY | 757 | $13.00 | $87.17 | $75.00 |
| 0001-0070 | Inlet protection type A (303SD20-0030) | EACH | 21 | $900.00 | $1,208.77 | $1,040.00 |
| 0001-0080 | Inlet protection type B (303SD20-0031) | EACH | 6 | $1,825.00 | $1,249.45 | $1,075.00 |
| 0001-0090 | Geotextile fabric (303SD20-0032) | SY | 900 | $7.00 | $11.62 | $10.00 |
| 0001-0100 | Temp. silt fence type A (303SD20-0034) | LF | 7,600 | $7.00 | $3.43 | $6.39 |
| 0001-0110 | Borrow excavation (305SD20-0001) | CY | 4,000 | $32.00 | $95.17 | $81.88 |
| 0001-0120 | Aggr.base mat.TY. I no.21A or 21B (305SD20-0012) | TON | 8,880 | $42.45 | $78.48 | $67.52 |
| 0001-0130 | NS aggr. material #57 stone (309SX20-0001) | TON | 400 | $60.00 | $110.91 | $95.42 |
| 0001-0140 | NS aggr. material surge stone (309SX20-0001) | TON | 400 | $60.00 | $116.72 | $100.42 |
| 0001-0150 | Cover matl. aggr. no. 78 (312SD20-0005) | TON | 863 | $90.00 | $109.18 | $103.50 |
| 0001-0160 | Liquid asphalt matl. CRS- 2L (312SX20-0003) | GAL | 27,390 | $3.50 | $3.43 | $4.03 |
| 0001-0170 | Asphalt concrete TY. SM- 12.5D const (315SD20-0002) | TON | 8,063 | $115.00 | $110.19 | $132.25 |
| 0001-0180 | Asphalt concrete TY. IM- 19.0D const (315SD20-0005) | TON | 7,741 | $112.50 | $100.10 | $129.38 |
| 0001-0190 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 22,704 | $1.00 | $0.62 | $0.61 |
| 0001-0200 | Liquid asphalt coating (rumble strip) (315SD20-0016) | SY | 5,312 | $2.50 | $0.78 | $0.77 |
| 0001-0210 | Asph.conc.curb backup matl. const (315SD20-0018) | TON | 157 | $230.00 | $204.17 | $264.50 |
| 0001-0220 | Asphalt concrete base course BM-25.0 (315SD20-0100) | TON | 18,102 | $107.50 | $96.04 | $126.94 |
| 0001-0230 | NS pavement rubblized H.C. concrete (315SX20-0004) | SY | 55,283 | $4.00 | $3.49 | $4.44 |
| 0001-0240 | NS pavement pavement marker grooves (316SX20-0004) | SY | 550 | $34.00 | $17.43 | $17.25 |
| 0001-0250 | Underdrain UD-1 (501SD20-0001) | LF | 900 | $30.00 | $40.68 | $62.21 |
| 0001-0260 | Underdrain UD-4 (501SD20-0004) | LF | 3,556 | $30.00 | $29.06 | $31.18 |
| 0001-0270 | Outlet pipe (501SD20-0009) | LF | 560 | $30.00 | $40.68 | $48.00 |
| 0001-0280 | Curb, asphalt MC-3B (502SD20-0020) | LF | 3,795 | $23.50 | $24.37 | $27.03 |
| 0001-0290 | Guardrail GR-MGS1 (505SD20-0011) | LF | 10,275 | $36.00 | $34.87 | $34.50 |
| 0001-0300 | Radial guardrail GR-MGS1 (505SD20-0014) | LF | 50 | $39.00 | $37.19 | $36.80 |
| 0001-0310 | Guardrail terminal GR- MGS2 (505SD20-0017) | EACH | 12 | $4,500.00 | $4,067.99 | $4,025.00 |
| 0001-0320 | Guardrail end anchorage GR-MGS3 (505SD20-0018) | EACH | 12 | $1,800.00 | $1,743.42 | $1,725.00 |
| 0001-0330 | Guardrail height transition GR-MGS4 (505SD20-0019) | EACH | 7 | $1,800.00 | $1,743.42 | $1,725.00 |
| 0001-0340 | Guardrail terminal GR-6 NCHRP 350 (505SD20-0027) | LF | 12.50 | $200.00 | $185.96 | $184.00 |
| 0001-0350 | Guardrail GR-2 (505SD20-0030) | LF | 100 | $36.00 | $34.87 | $34.50 |
| 0001-0360 | Fixed object attach. GR- foa-2 TY. II (505SD20-0054) | EACH | 1 | $1,000.00 | $929.83 | $920.00 |
| 0001-0370 | Remove existing guardrail (505SD20-0073) | LF | 8,575 | $6.00 | $5.81 | $5.75 |
| 0001-0380 | NS guardrail GR-MGS2 end terminal site prep., 6' moderate (505SX20-0058) | EACH | 12 | $900.00 | $1,162.28 | $2,500.00 |
| 0001-0390 | NS guardrail post leave- out (505SX20-0058) | EACH | 614 | $60.00 | $58.11 | $57.50 |
| 0001-0400 | Demo. of pavement rigid (508SD20-0003) | SY | 14,851 | $7.20 | $20.93 | $18.01 |
| 0001-0410 | Demo. of pavement flexible (508SD20-0004) | SY | 170 | $50.00 | $43.21 | $25.00 |
| 0001-0420 | NS remove exist. drop inlet DI (510SX20-0026) | EACH | 6 | $2,500.00 | $1,743.43 | $1,500.00 |
| 0001-0430 | NS remove exist. 15" HDPE pipe (510SX20-0039) | LF | 30 | $250.00 | $232.46 | $200.00 |
| 0001-0440 | NS remove exist. MC-3B (510SX20-0039) | LF | 3,795 | $6.00 | $5.81 | $5.00 |
| 0001-0450 | NS remove exist. guardrail terminal (510SX20-0040) | EACH | 15 | $400.00 | $348.68 | $345.00 |
| 0001-0460 | Impact atten.ser. TY. 1 TL- 3, >=40 MPH (512SD20-0007) | EACH | 4 | $12,000 | $10,751 | $17,250 |
| 0001-0470 | Type 3 barricade 8' (512SD20-0013) | EACH | 14 | $800.00 | $319.63 | $800.00 |
| 0001-0480 | Temporary sign (512SD20-0014) | SF | 3,370 | $18.00 | $16.27 | $34.50 |
| 0001-0490 | Truck mounted attenuator (512SD20-0023) | HR | 1,804 | $40.00 | $138.31 | $75.00 |
| 0001-0500 | Group 2 channelizing devices (512SD20-0024) | DAY | 30,000 | $1.35 | $0.17 | $2.50 |
| 0001-0510 | Port.changeable mess. sign (512SD20-0025) | HR | 4,000 | $7.00 | $5.11 | $40.00 |
| 0001-0520 | Electronic arrow board (512SD20-0026) | HR | 3,200 | $7.00 | $32.83 | $25.00 |
| 0001-0530 | Warning light TY. B (512SD20-0029) | DAY | 104 | $25.00 | $9.30 | $5.00 |
| 0001-0540 | Traffic barrier ser. conc. MB-7D PC (512SD20-0031) | LF | 4,700 | $60.00 | $57.74 | $69.00 |
| 0001-0550 | Eradicate linear PVMT MRKG (512SD20-0042) | LF | 25,000 | $0.65 | $2.39 | $2.37 |
| 0001-0560 | Eradicate nonlinear PVMT MRKG (512SD20-0043) | SF | 500 | $25.00 | $42.34 | $41.89 |
| 0001-0570 | Temp. pave. marker 1 way (512SD20-0044) | EACH | 500 | $26.00 | $23.25 | $23.00 |
| 0001-0580 | Temp. PVMT MRKG TY. A, 6" (512SD20-0047) | LF | 72,126 | $0.35 | $0.70 | $0.69 |
| 0001-0590 | Temp. PVMT MRKG TY. A, 8" (512SD20-0048) | LF | 13,000 | $0.55 | $0.72 | $0.71 |
| 0001-0600 | Mobilization (513SD20-0001) | LS | 1 | $260,000 | $648,060 | $499,018 |
| 0001-0610 | Flex. pave. tie-in planing 0"-2" (515SD20-0011) | SY | 2,926 | $14.00 | $9.64 | $16.10 |
| 0001-0620 | Construction surveying constr. (517SD20-0001) | LS | 1 | $32,000 | $31,382 | $31,050 |
| 0001-0630 | Topsoil class B (602SD20-0004) | CY | 1,613 | $165.00 | $218.47 | $187.97 |
| 0001-0640 | Temporary seed (603SD20-0002) | LB | 400 | $13.00 | $16.27 | $16.10 |
| 0001-0650 | Regular seed (603SD20-0003) | LB | 1,750 | $14.00 | $11.62 | $11.50 |
| 0001-0660 | Overseeding (603SD20-0004) | LB | 1,400 | $14.00 | $5.81 | $5.75 |
| 0001-0670 | Hydraulic erosion control product type 2 (603SD20-0008) | SY | 24,200 | $1.00 | $1.16 | $1.15 |
| 0001-0680 | Hydraulic erosion control product type 3 (603SD20-0009) | SY | 19,360 | $1.25 | $1.74 | $1.73 |
| 0001-0690 | Fertilizer nitrogen - N (603SD20-0014) | LB | 400 | $5.00 | $4.65 | $4.60 |
| 0001-0700 | Fertilizer phosphorous - P (603SD20-0015) | LB | 280 | $5.00 | $4.65 | $4.60 |
| 0001-0710 | Fertilizer potassium - K (603SD20-0016) | LB | 280 | $5.00 | $4.65 | $4.60 |
| 0001-0720 | Lime (603SD20-0017) | TON | 22 | $450.00 | $552.08 | $546.25 |
| 0001-0730 | Remove existing 1 post sign structure (700SD20-0003) | EACH | 17 | $400.00 | $801.92 | $393.30 |
| 0001-0740 | Remove existing 2 post sign structure (700SD20-0004) | EACH | 7 | $800.00 | $1,434.87 | $786.60 |
| 0001-0750 | Relocate EX. 1 post GRND mount SGN panel (700SD20-0012) | EACH | 1 | $250.00 | $859.51 | $201.25 |
| 0001-0760 | Sign post STP-1, 2", 14 gauge (700SD20-0034) | LF | 206 | $18.00 | $32.99 | $18.40 |
| 0001-0770 | Sign post STP-1, 2 3/16", 10 gauge (700SD20-0035) | LF | 12 | $25.00 | $51.93 | $21.85 |
| 0001-0780 | Sign post STP-1, 2 1/2", 10 gauge (700SD20-0036) | LF | 44 | $25.00 | $49.84 | $21.85 |
| 0001-0790 | Sign post STP-1, 2 1/2", 12 gauge (700SD20-0037) | LF | 22 | $25.00 | $42.66 | $20.70 |
| 0001-0800 | Conc. found. STP-1, TY. A (700SD20-0038) | EACH | 26 | $700.00 | $798.97 | $680.80 |
| 0001-0810 | Conc. found. STP-1, TY. B (700SD20-0039) | EACH | 4 | $1,000.00 | $1,798.12 | $1,031.55 |
| 0001-0820 | Sign panel (701SD20-0001) | SF | 278 | $30.00 | $43.73 | $32.10 |
| 0001-0830 | Type B class I PVMT line MRKG 8" (704SD20-0008) | LF | 1,824 | $4.00 | $8.41 | $8.33 |
| 0001-0840 | Type B class II PVMT line MRKG 4" (704SD20-0011) | LF | 360 | $6.00 | $15.41 | $15.25 |
| 0001-0850 | Type B class II PVMT line MRKG 24" (704SD20-0015) | LF | 1,054 | $50.00 | $40.92 | $40.49 |
| 0001-0860 | Type B class VI PVMT line MRKG 6" (704SD20-0027) | LF | 35,615 | $6.00 | $7.96 | $7.88 |
| 0001-0870 | Type B class VI PVMT line MRKG 8" (704SD20-0028) | LF | 479 | $10.00 | $9.90 | $9.80 |
| 0001-0880 | Type B class VI PVMT line MRKG 12" (704SD20-0029) | LF | 2,345 | $12.00 | $14.68 | $14.52 |
| 0001-0890 | Inlaid pavement marker asphalt (704SD20-0032) | EACH | 314 | $37.00 | $62.39 | $61.73 |
| 0001-0900 | Symb MRKG wrong-way arrow TY B CL II (704SD20-0063) | EACH | 1 | $675.00 | $862.60 | $853.48 |
| 0002-0910 | NS select material alternate shoulder material (305SX20-0006) | TON | 1 | $100.00 | $31.59 | $0.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of December 17, 2025. Compiled by Mirage Metrics.